Review possible progress-payment overbilling by comparing cumulative billed value with verified work, eligible stored materials, the current contract basis and prior certificates. Distinguish a calculation discrepancy from unsupported progress, timing differences and confirmed overpayment.
What to take away
- Use the same cutoff and value definitions across records.
- Physical progress requires the designated project review.
- An unpaid draft correction is not a cash recovery.
Reconcile the authorized value before evaluating progress
Obtain the original contract amount, executed changes and current schedule of values. Compare them with the application summary. Identify pending changes and any special billing instruction separately. A commercially approved change may still have timing or performance conditions for billing.
Record the cutoff date and version for every source. A site assessment completed after the application date can explain a difference without proving the earlier request was accurate. Ask the project professional to establish the relevant progress at the period cutoff and preserve that evidence with the review.
Read current and cumulative values correctly
Check the form's definitions for prior, current and cumulative amounts. Reconcile line totals, retainage, stored value and prior certificates according to the applicable agreement. AIA's official G702 instructions address the summary and continuation-sheet relationship for that form. Use the licensed document where required.
Avoid comparing cumulative work to a single current-period payment and calling the difference overbilling. Keep actual cash received in a separate reconciliation. A prior certificate may remain unpaid while still being the relevant prior deduction in the next application. This distinction prevents a collection problem from becoming an incorrect billing calculation.
Sources: AIA Contract Documents: official G702 application and certificate instructions
Worked example: compare like with like
Assume a fictional project has $300,000 of supported cumulative installed work and $40,000 of eligible stored materials. Under an assumed flat 5% retainage, $340,000 less $17,000 leaves $323,000. With $250,000 previously certified, the current request is $73,000 before other adjustments.
If the draft requests $91,000, identify the source of the $18,000 difference. It could be a prior-value error, a progress disagreement or another contract-specific item. Do not assume the difference has already been paid. The table is an original illustration, not an official payment form or a recommendation to apply 5% retention.
| Illustrative input | Amount |
|---|---|
| Supported installed work | $300,000 |
| Eligible stored materials | $40,000 |
| Cumulative gross value | $340,000 |
| Assumed retainage | $17,000 |
| Previously certified | $250,000 |
| Current reviewed request | $73,000 |
Test apparent progress against the right evidence
Review the underlying quantities, inspection record, location and work package. Photographs can help identify work but may not establish quantities, quality or entitlement on their own. Assign physical verification to the designated professional and preserve their conclusion.
For stored materials, verify the applicable ownership, identification, insurance and approval conditions. Then check the transfer into installed value to avoid double counting. A general statement that materials are “on site” may not answer the agreement's specific conditions. Where federal payment clauses apply, use their actual requirements rather than extending them to every private project.
Sources: FAR 52.232-5: Payments under Fixed-Price Construction Contracts
Resolve disagreements before reporting a result
Present the requested and reviewed values with the source of each difference. Allow the contractor to provide missing records or explain the measurement. The authorized team decides certification and payment treatment under the contract; the audit record should preserve that decision and any reservation.
For Buildalytic, discuss collection of missing support and follow-up on the review question. Price assurance and progress verification are separate scopes to define and validate. Require the final result to identify whether a correction was proposed, agreed, reflected in a certificate or settled in cash. Each stage answers a different business question.
Common questions
Does overbilling always mean fraud?
No. Differences can come from errors, timing, unsupported estimates or disputes. Establish the cause and evidence before assigning a conclusion.
Can software certify physical progress?
Software can organize records and flag inconsistencies. The authorized project professional must perform the applicable verification and certification.
Sources and editorial notes
- AIA Contract Documents: official G702 application and certificate instructions
- FAR 52.232-5: Payments under Fixed-Price Construction Contracts
- Buildalytic: current custom-workflow scope
Prepared with AI assistance. Reference date: 2026-11-05. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.
How we prepare and update field notesScope one evidence-backed review workflow.
Bring a redacted contract, payment packet and one unresolved question. Discuss the supported collection and follow-up steps, any additional scope and the human review needed to validate the result.
Start with the call, text or record your team already handles. Review the expected outcome and the human handoff before choosing a rollout.
Discuss your review workflow Explore the relevant capability