Certified payroll / Field guide
Texas certified payroll and prevailing wage reporting.
Texas public works prevailing wage under Government Code Chapter 2258: who sets rates, payroll records, public body reporting rules, penalties and complaints.

01 / In practice
No central agency runs Texas prevailing wage
Texas has no state agency that administers prevailing wage on public works. Government Code Chapter 2258 places duties on the public body that awards the contract and on contractors and subcontractors. The public body sets the rates, puts them in the bid call and contract, hears complaints and withholds payment when needed. Contractors pay the rates and keep records. Reporting rules, such as certified payroll frequency and format, come from each public body's contract and specifications.
02 / In practice
Which projects are covered
Chapter 2258 applies to the construction of a public work paid for in whole or in part from public funds. That includes a building, highway, road, excavation, and repair work or other project development or improvement. It applies whether or not the work is done under public supervision. Workers employed by a contractor or subcontractor on the contract must receive at least the prevailing rate, including for legal holiday and overtime work. The pay requirement does not apply to maintenance work or to work done directly by a public utility under a public order.
03 / In practice
How the public body sets rates
For a contract awarded by a political subdivision, the public body determines the prevailing rate for each craft or type of worker. It either surveys wages on similar projects in the area or uses the Davis-Bacon rates set by the U.S. Department of Labor. Special rules apply to state contracts in counties on or next to the Mexican border. Rates must be a sum certain in dollars and cents and appear in the call for bids and the contract. The public body's determination is final.
04 / In practice
Keep records, then report as the contract requires
Section 2258.024 requires each contractor and subcontractor to keep a record of each worker's name, occupation and actual per diem wages paid. The record must be open to the public body's officers and agents at all reasonable hours. Texas law does not define certified payroll or set a state form. Review each payroll internally against the contract rates first. Then submit it as the public body requires. For example, TxDOT requires weekly certified payrolls in LCPTracker within 7 calendar days after the payroll period ends.
05 / In practice
Penalties in the statute
A contractor or subcontractor that underpays owes the state or political subdivision $60 for each worker for each calendar day or part of a day the worker is paid less than the contract rate. The public body must state this penalty in the contract. A municipality may collect it only if its population is over 10,000. There is no violation if the public body did not set and specify rates. Failing to keep the required records is a criminal offense, punishable by a fine up to $500, up to six months in jail, or both.
06 / In practice
Complaints, withholding and arbitration
The public body must act on complaints and withhold forfeited money from payments to the contractor. It must make an initial determination within 30 days of receiving information about an alleged violation and notify the contractor and affected workers in writing. If the parties do not settle within 14 days, the issue goes to binding arbitration. The public body uses retained money to pay workers what they are owed. A prime contractor may withhold money from a subcontractor whose violation caused a withholding.
Official sources
Start with the agency’s instructions.
Reporting requirements depend on the contract and applicable program. Check the current instructions with the team responsible for your project.
- Texas Legislature · Government Code Chapter 2258 ↗
- Texas Workforce Commission · Prevailing Wage Issues ↗
- TxDOT · Construction Contract Administration Manual, Labor Requirements ↗
Sources checked October 29, 2026.
Which state agency enforces Texas prevailing wage?
None. Chapter 2258 has no central enforcement agency. The public body that awards the contract determines rates, takes complaints, makes initial determinations and withholds payment. Unresolved disputes go to binding arbitration. Check the contract and the public body's instructions for reporting requirements.
Does Texas require a certified payroll form?
State law does not define certified payroll or set a form. Section 2258.024 requires records of each worker's name, occupation and actual wages paid. The Texas Workforce Commission says the federal WH-347 form would likely suffice. Many public bodies require certified payroll in their contracts, so follow the contract.
How often do I submit certified payroll in Texas?
The statute sets no submission schedule. The public body's contract and specifications control. TxDOT, for example, requires weekly certified payrolls within 7 calendar days after the end of each payroll period, filed in its LCPTracker system. Confirm the schedule and recipient with each public body before work starts.
What is the Texas prevailing wage penalty?
Section 2258.023 sets a penalty of $60 for each worker for each calendar day or part of a day the worker is paid less than the contract rate. It is paid to the state or political subdivision. A municipality can collect it only if its population is more than 10,000.
Can a public body use Davis-Bacon rates?
Yes. For contracts awarded by a political subdivision, Section 2258.022 lets the public body either survey local wages or use the prevailing rates set by the U.S. Department of Labor under the Davis-Bacon Act. The rates must be stated in the bid call and the contract.
Start with one project.
Bring your reporting requirements and a sample payroll. We’ll walk through collection, review and the final handoff with your team.