Retainage laws by state (2026): caps, release deadlines and subcontractor pass-through in 12 states

Construction retainage laws for California, Texas, Florida, New York, Illinois, Washington, Pennsylvania, Massachusetts, Georgia, Arizona, Colorado and North Carolina: public and private caps, release deadlines and 2026 changes.

By Buildalytic Research Desk8 min read

Editorial scene of a retainage schedule reviewed at job closeout
Illustrative editorial scene. State rules summarized from statute text, checked November 15, 2026. Not legal advice.
The short answer

Most states cap retainage on public construction at 5 percent, and a growing number cap private work too: California at 5 percent for private contracts entered on or after January 1, 2026, New York at 5 percent for private projects of $150,000 or more, Colorado at 5 percent on private contracts of $150,000 or more. Release deadlines run from 14 to 65 days after completion, and subs usually get their share within 7 to 20 days. Buildalytic tracks retainage by job and follows up on release.

What to take away

  • Public retainage is capped at 5 percent in most of these states; some allow 10 percent until 50 percent complete.
  • California (2026), New York and Colorado now cap private retainage at 5 percent, with exceptions.
  • Release deadlines run from 14 days to 65 days after completion, depending on the state and owner.
  • Subcontractors usually must receive their retainage within 7 to 20 days after the prime receives it.

How retainage laws work

Retainage is the part of each progress payment an owner holds back until the work is complete, usually 5 to 10 percent. State laws limit how much can be held, set deadlines to release it, and require the prime contractor to pass the subcontractors' share through promptly. Public projects are covered in every state on this list; private projects in some.

The rules below come from each state's statutes. Contracts can be stricter than the statute, and some states have exceptions by project type or size, so read your contract and the statute before relying on a summary.

Retainage rules in 12 states

From statute text, checked November 15, 2026. Release timing is for the owner to the prime unless noted.

Retainage rules in 12 states
StatePublic capPrivate capPublic releaseSub pass-through
California5%5% for contracts entered on or after Jan 1, 2026 (exceptions)Within 60 days after completionPublic: 7 days; private: 10 days
Texas10% under $5M; 5% at $5M or moreNo percentage capCan't be held after completion of the workPublic: 10 days; private: 7 days
Florida5% on contracts over $200,000No cap20 business days after the punch list, less 150% of punch list costPublic: "timely"; local: 10 days
New York5% (up to 10% without full bonds)5% on projects of $150,000 or moreAt substantial completion, less 2x remaining items7 days
Illinois10%, then 5% after 50% complete, from June 1, 202710%, then 5% after 50% completeNot confirmed before 2027Private: 15 days
Washington5%No statute found60 days after completion, after lien period and tax clearances10 days
PennsylvaniaCommonwealth agencies: 10%, then 5% after 50% completeNo percentage cap45 days after substantial completion, less 1.5x minor itemsPublic: 20 days; private: 14 days
Massachusetts5%5% where the prime contract is $3M or morePublic buildings: 65 days after substantial completionPublic: promptly; private: tiered
Georgia5% for contracts on or after July 1, 2022Not confirmed30 days after invoice at substantial completion, less 200% of incomplete items10 days
Arizona10%, then 5% after 50% completeNo percentage cap60 days after completion7 days
Colorado5% on contracts over $150,0005% on contracts of $150,000 or moreFinal settlement within 60 days after acceptanceNot confirmed
North Carolina5% on projects of $150,000 or more; none underNo cap; sub retainage can't exceed the owner's60 days after pay request at substantial completion7 days

What changed recently

California: SB 61 added Civil Code 8811, capping private retainage at 5 percent of each payment and of the contract price for contracts entered on or after January 1, 2026. It excludes certain subcontractors who don't provide a requested bond and non-mixed-use residential projects of four stories or fewer. Private owners must pay retention within 45 days after completion, primes must pass it to subs within 10 days, and late payment carries a 2 percent per month penalty.

New York: the private-contract cap of 5 percent applies to projects with an aggregate cost of $150,000 or more, with residential exclusions. The current General Business Law 757 adds a subdivision making any clause that requires retainage above 5 percent void and unenforceable. Release is due within 30 days after final approval, with 1 percent per month interest for late release.

Colorado: HB26-1311, signed May 7, 2026, requires owners to accept a qualifying surety bond of up to 5 percent in place of retainage on contracts created on or after its effective date. Illinois: Public Act 104-0168 brings the private 10 percent then 5 percent structure to state and local public works from June 1, 2027, excluding IDOT.

Sources: California Civil Code 8811 (private retention cap); New York General Business Law 757; Colorado HB26-1311; Illinois Public Act 104-0168

California in detail

On public works, retention is capped at 5 percent of each payment and of the contract price, unless the project was found substantially complex before bid. The public owner must release it within 60 days after completion, the prime passes it to subs within 7 days, and late public release carries a 2 percent per month charge in place of interest. On private work, the 2026 cap, 45-day release and 10-day pass-through apply.

Sources: California Public Contract Code 7107; California Civil Code 8811 (private retention cap)

Texas in detail

On public works covered by Government Code chapter 2252, retainage is capped at 10 percent for contracts under $5 million and 5 percent for contracts of $5 million or more, and the public entity may not keep retainage after the work is complete, including during the warranty period. Primes may not withhold a higher percentage from subs than is withheld from them. Private work has no percentage cap, but subs must be paid within 7 days of the contractor's receipt, and late payments carry 1.5 percent per month. Separately, private owners must reserve 10 percent for 30 days after completion as a lien fund.

Sources: Texas Government Code Chapter 2252; Texas Property Code Chapter 28

Florida and New York

Florida public entities may withhold no more than 5 percent of each progress payment on contracts over $200,000. After substantial completion a punch list is developed and the balance, including retainage, is due within 20 business days, less 150 percent of the cost to finish listed items. Private Florida jobs have no cap; retainage is due within 14 days after substantial completion and punch list events.

New York public owners may retain no more than 5 percent of each progress payment, or up to 10 percent when full bonds aren't required, and must pay the balance at substantial completion less twice the value of remaining items.

Sources: Florida Statutes 255.078; New York General Municipal Law 106-b

The 50 percent step-down

Several states let owners hold 10 percent until the work is half done, then cut retainage to 5 percent: Arizona on public work, Pennsylvania on Commonwealth agency contracts, and Illinois on private work (and public work from 2027). North Carolina stops further retainage at 50 percent completion if performance is satisfactory. Set the step-down as a rule in your billing so nobody keeps applying 10 percent by habit.

Worked example: a $2.4 million subcontract in California

Illustrative private job, contract entered in March 2026.

Worked example: a $2.4 million subcontract in California
ItemOld contract termsUnder the 2026 cap
Retainage rate10%5%
Held at $1.8 million billed$180,000$90,000
Cash released to the sub during the job$90,000 more
Owner pays retention after completionPer contractWithin 45 days
Prime pays sub's sharePer contractWithin 10 days of receipt
Late paymentPer contract2% per month penalty

How to get retainage released faster

Release usually waits on paperwork: punch list completion, closeout documents, final lien waivers and, on bonded work, consent of surety. Start closeout early, track punch items by trade, and submit the retainage billing with a complete package. Calendar the statutory deadline from the completion date and follow up the day after it passes; interest and penalties under these statutes only help if someone asks for them.

For subcontractors

Know the pass-through deadline in your state and the trigger: it usually runs from the date the prime receives retainage, not from your completion. Ask the prime when the owner released retainage, and keep the written record. Your own final waiver should list unpaid retainage as an exception until it's paid.

How Buildalytic helps

Buildalytic tracks retainage per project, sub and pay period, applies step-downs and caps from the contract, and shows what is holding release: a punch item, a closeout document or a missing waiver. Brody follows up with the owner, GC or subs on each item until retainage is paid.

Common questions

What is the maximum retainage in construction?

It depends on the state and whether the project is public or private. Most of the 12 states here cap public retainage at 5 percent; some allow 10 percent until 50 percent complete. California, New York and Colorado cap private retainage at 5 percent with conditions.

Does California cap retainage on private projects?

Yes. For private contracts entered on or after January 1, 2026, Civil Code 8811 caps retainage at 5 percent, with exceptions including non-mixed-use residential projects of four stories or fewer.

How fast must a prime pay a sub's retainage?

Usually within 7 to 20 days after the prime receives it, depending on the state: for example 7 days on California public work, 10 days in Washington and 14 days on Pennsylvania private work.

Can retainage be held during the warranty period in Texas?

Not on public works covered by Government Code 2252; retainage may not be withheld after completion of the work, including during warranty.

Sources and editorial notes

Prepared with AI assistance. Reference date: 2026-11-12. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.

How we prepare and update field notes
See it on your workflow

See what is holding every retainage dollar.

Bring your open retainage by job. See the release deadline, what's holding it, and Brody following up.

Start with the call, text or record your team already handles. Review the expected outcome and the human handoff before choosing a rollout.

See retainage tracking Explore the relevant capability