On a DOT-assisted contract with a DBE goal, a bidder must either document enough DBE participation to meet the goal or document adequate good faith efforts to meet it, under 49 CFR 26.53. That means listing each DBE's name, work, dollar amount, written commitment and confirmation, and keeping quotes when a non-DBE was selected over a DBE. Buildalytic tracks DBE outreach, responses and coverage by scope, and Brody follows up with each firm.
What to take away
- Meet the goal or document good faith efforts; both paths need records.
- A DBE counts only if certified in a NAICS code for the work it will perform.
- A DBE regular dealer can count at 60 percent of material cost, a distributor at 40 percent.
- Keep every quote when a non-DBE is chosen over a DBE.
What the rule requires
On U.S. Department of Transportation assisted contracts with a disadvantaged business enterprise (DBE) contract goal, 49 CFR 26.53 says the contract goes only to a bidder that makes good faith efforts to meet the goal. A bidder shows that in one of two ways: it documents enough DBE participation to meet the goal, or it documents adequate good faith efforts even though it fell short. If the efforts are adequate, the award can't be denied just for missing the goal.
Bidders must submit the names and addresses of participating DBEs, a description of each DBE's work, the dollar amount of each, written documentation of the bidder's commitment to use each DBE, and written confirmation from each DBE that it is participating as described. The agency decides whether that comes with the bid or no later than 5 days after bid opening.
Check eligibility before you count anyone
To count toward a goal, each DBE must be certified in a NAICS code that applies to the work it will perform on the contract. A firm certified for trucking doesn't count for traffic control unless it also holds a code for that work. Check each firm's current certification and codes in the state Unified Certification Program directory when you list it.
USDOT changed the DBE program's eligibility rules in 2025, and certified firms have been re-evaluated under the new standards. Confirm current status with the agency rather than relying on last year's list.
Suppliers count differently
Material from a DBE supplier counts at a reduced rate. Under 26.53 the agency makes a preliminary determination of whether each DBE supplier qualifies for 60 percent credit as a regular dealer or 40 percent as a distributor, based on its demonstrated capacity and intent to perform that role. The bidder is responsible for checking that what the supplier says is consistent with how its participation is counted. Overcounting supplier participation is a common reason a bid's DBE total doesn't hold up.
Worked example: a 12 percent goal on a $6.5 million bid
Illustrative numbers. The goal is $780,000 of DBE participation.
| DBE firm | Work | Committed amount | Counts as | Credit |
|---|---|---|---|---|
| Firm A | Trucking (certified for trucking) | $210,000 | Subcontract | $210,000 |
| Firm B | Erosion control | $145,000 | Subcontract | $145,000 |
| Firm C | Pipe and fittings, regular dealer | $300,000 | 60% of material cost | $180,000 |
| Firm D | Traffic control | $120,000 | Subcontract | $120,000 |
| Total | $775,000 | $655,000, or 10.08% |
Falling short: what to do with a $125,000 gap
In the example, the bid is $125,000 short of the goal, mostly because the supplier's $300,000 counts as $180,000. The estimator has two paths before the deadline: find more DBE participation in scopes still open, or prepare complete good faith efforts documentation.
The documentation must include copies of each DBE and non-DBE subcontractor quote submitted when a non-DBE was selected over a DBE for work on the contract. Appendix A to Part 26 gives agencies guidance for judging good faith efforts, including soliciting DBEs through reasonable means early enough for them to respond, breaking work into economically feasible pieces, giving DBEs plans and specifications in time, negotiating in good faith, and not rejecting DBEs without sound reasons.
Sources: eCFR: 49 CFR 26.53, good faith efforts procedures; eCFR: 49 CFR Part 26, Appendix A, guidance concerning good faith efforts
Outreach that holds up later
Good faith efforts are judged on the record, so the record has to exist. For each scope, keep who was contacted, how and when, whether they received the plans, their response, any quote, and if they weren't selected, why. A phone call nobody logged doesn't count for much in a reconsideration.
Start early. Invitations sent two days before bid day don't give a small firm time to price the work, and timing is part of what reviewers look at.
An outreach tracker by scope
Illustrative tracker two weeks before bid day.
| Scope | DBE firms identified | Contacted | Plans sent | Responded | Quoting | Next step |
|---|---|---|---|---|---|---|
| Trucking | 6 | 6 | 6 | 4 | 2 | Get Firm A's signed commitment and confirmation |
| Erosion control | 3 | 3 | 3 | 2 | 1 | Request written confirmation from Firm B |
| Traffic control | 4 | 4 | 4 | 2 | 1 | Second call to two non-responders |
| Landscaping | 5 | 5 | 3 | 1 | 0 | Send plans to two firms; ask what would help them bid |
| Pipe supply | 2 | 2 | 2 | 2 | 1 | Confirm regular dealer role in writing |
Break work into pieces DBE firms can bid
Small firms often can't bond or staff a whole scope. Appendix A lists selecting portions of the work, including breaking contract work into economically feasible units, as one of the kinds of efforts agencies consider. In practice, a $900,000 landscaping scope might be split into seeding and erosion matting, plant material supply, and irrigation, so a smaller DBE can price one piece. Record the split and who was invited for each piece; it is part of the good faith record whether or not a DBE wins it.
Sources: eCFR: 49 CFR Part 26, Appendix A, guidance concerning good faith efforts
Common mistakes on bid day
Counting a DBE in a scope it isn't certified for. Counting a supplier at 100 percent instead of 60 or 40. Listing a firm without its written confirmation of participation. Starting outreach too late for firms to price the work. Losing the quotes from DBEs that weren't selected, which the rule requires when a non-DBE is chosen over a DBE. And relying on memory of phone calls instead of a dated log.
What to measure
Per bid, track DBE firms identified and contacted by scope, days between first invitation and bid day, response and quote rates, committed and countable participation against the goal, and whether the good faith file is complete before bid opening. Across bids, the same numbers show which scopes rarely attract DBE quotes and where earlier outreach or smaller work packages would help.
Participation meetings and reconsideration
Some agencies hold outreach or participation meetings; when one is required, track invitations, confirmations, attendance and follow-up by firm. If the agency finds a bidder didn't make adequate good faith efforts, 26.53 requires an opportunity for administrative reconsideration before award, including written documentation and an in-person meeting with an official who wasn't part of the original decision. Your outreach record is the evidence you bring.
After award
Commitments don't end at award. Replacing a listed DBE generally requires the agency's approval, and participation is tracked through the job. Keep the commitment letters and confirmations with the subcontracts, and track payments to each DBE so final reporting matches what was committed.
How Buildalytic helps
Buildalytic tracks DBE outreach by scope: firms identified, contacted, plans sent, responses and quotes, with every attempt logged. Brody calls and texts each firm with the invitation and follows up until it declines or quotes, so the coverage board and the good faith record build up as the bid progresses. The estimator still decides who is selected and how participation is counted.
Common questions
What are DBE good faith efforts?
Documented efforts by a bidder to meet a DBE contract goal on a DOT-assisted contract. Under 49 CFR 26.53, adequate good faith efforts allow award even if the goal isn't met.
How much does a DBE supplier count toward the goal?
The agency determines whether a DBE supplier counts at 60 percent of material cost as a regular dealer or 40 percent as a distributor.
When is DBE information due?
The agency decides: either with the bid or initial proposal, or no later than 5 days after bid opening.
What documents are needed if the goal isn't met?
Evidence of good faith efforts, including copies of each DBE and non-DBE quote when a non-DBE was selected over a DBE.
Sources and editorial notes
- eCFR: 49 CFR 26.53, good faith efforts procedures
- eCFR: 49 CFR Part 26, Appendix A, guidance concerning good faith efforts
- Buildalytic: subcontractor bid follow-up
Prepared with AI assistance. Reference date: 2026-11-14. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.
How we prepare and update field notesBuild the good faith record while you build the bid.
Bring a DOT bid with a DBE goal. See outreach tracked by scope and Brody following up with each firm.
Start with the call, text or record your team already handles. Review the expected outcome and the human handoff before choosing a rollout.
See bid follow-up Explore the relevant capability