Communications
The challenge
Project managers spent hours each day answering the same questions from subs, owners and suppliers: is the inspection still on, when is the delivery, did the schedule move.
Updates went out one call or email at a time and were often missed, which sent crews to site on the wrong day.
The solution
Brody now sends every schedule change, inspection and delivery update the moment it happens, and makes sure each person confirms it.
Updates go out first
Schedule changes, inspections and deliveries are sent by text or email the moment they change.
Confirmed, not just sent
Each recipient confirms. Anyone who has not answered gets a call from Brody.
Questions answered
Brody answers follow-up questions from the schedule and the job record, day or night.
Only exceptions reach the PM
Conflicts and unanswered items go to the project manager. Everything else is handled.
“We used to spend our days answering where-are-we calls. Now Brody tells everyone what changed before they think to ask, and my project managers spend that time running their jobs.”
The results
Status calls to project managers fell 62%, from 120 to 46 a week, and each project manager gets back about 5 hours a week.
Same-day confirmation of schedule changes rose from 41% to 96%, and crew trips on the wrong day fell from six a month to one.
| Measure | Before | With Brody |
|---|---|---|
| Status calls to project managers a week | 120 | 46 |
| Hours per PM a week on status updates | 7 | 2 |
| Schedule changes confirmed the same day | 41% | 96% |
| Crew trips on the wrong day | 6 a month | 1 |
How it was measured. Before and after Brody, from call logs and the project schedule. Workflows used: Proactive follow up.