A San Luis Obispo general contractor covers 94% of bid packages by the due date

Brody sends every invitation, reminds each trade before the deadline and flags uncovered scopes while there is still time to fill them.

Key results

of bid packages fully covered by the due date, up from 62%
94%
saved per bid
11 hrs
bids per scope, up from 1.9
3.4

Preconstruction

The challenge

The estimating team sent invitations by hand from a spreadsheet of trades, then spent the last two days before each due date calling to see who was actually bidding.

Gaps in coverage often surfaced the night before bid day, when it was too late to find another trade.

The solution

The team now sends each bid package through Brody, which runs invitations, reminders and coverage tracking from the same trade list the estimators already kept.

  1. Invites go out by trade and area

    Brody sends each package to the right trades with the plans link, scope notes and due date.

  2. Reminders before the deadline

    Trades who have not answered get a reminder by text or email on the schedule the team sets.

  3. Coverage tracked by scope

    Every reply is matched to its scope, so open scopes are visible days before bids are due.

  4. Gaps flagged early

    The estimator is told which scopes still need bids, with enough time to invite more trades.

“Bid coverage used to depend on how many calls our estimators could make in the last two days. Now every scope is tracked from the day the invitation goes out, and we walk into bid day knowing exactly where we stand.”

CEO, general contractor in San Luis Obispo, CA

The results

Fully covered bid packages rose from 62% to 94%, and bids per scope went from 1.9 to 3.4, so the team compares real options on every scope.

Estimators now spend about 3 hours per bid on follow-up instead of 14, and uncovered scopes surface days before the due date rather than on bid day.

Results before and after Brody
MeasureBeforeWith Brody
Packages fully covered by the due date62%94%
Bids received per scope1.93.4
Estimator time per bid on follow-up14 hrs3 hrs
Scopes found uncovered on bid day4 per bid0 to 1

How it was measured. Before and after Brody, from the estimating team’s bid logs. Workflows used: Bid solicitation.

All customer stories
  • Compliance

    Electrical subcontractor · San Diego, CA · 120 people

    $384Kin progress payments no longer held for late certified payroll, down to $0

    certified payrolls on time, from 74%
    100%
    payroll admin saved a month
    30 hrs

    “Late certified payroll used to mean held payments and weeks of back and forth with the general contractor. Now every report goes in on time, our progress payments arrive on schedule, and my payroll team has its week back.”

    CEO
  • Field operations

    Mechanical subcontractor · New York, NY · 80 people

    97%of daily reports filed the same day, up from 55%

    saved per foreman a day
    18 min
    jobs reporting by phone
    14

    “Our foremen call in on the drive home, and the report is filed before they get there. Project managers start the morning with complete reports instead of chasing them.”

    Operations Manager

See Brody on your own jobs.

Bring a real workflow, and watch Brody run it end to end.