Free tool
Pay application (G702) calculator.
Fill in the contract, change orders, work to date and retainage and get every G702 summary line.
No sign-up. What you type stays in your browser.
Your numbers
Result
Lines 6 + 9 always equal line 3. A negative payment due usually means previous certificates were overstated or retainage changed; reconcile before you submit.
How it works
The rules behind the numbers.
Lines 1 to 3: the contract
Line 1 is the original contract sum, line 2 the net of approved change orders, and line 3 their total.
Lines 4 to 6: earned to date
Line 4 is completed work plus stored materials from the G703 continuation sheet. Line 5 is retainage. Line 6 is earned less retainage.
Lines 7 to 9: this payment
Line 7 is the total of previous certificates, line 8 the current payment due (line 6 less line 7) and line 9 the balance to finish including retainage.
Full guide: How to fill out AIA G702 and G703: a line-by-line pay application example
How do you calculate the current payment due on a G702?
Total earned less retainage (line 6) minus previous certificates for payment (line 7).
Do lines 6 and 9 add up to line 3?
Yes. Earned less retainage plus balance to finish including retainage always equals the contract sum to date.
Get paid faster on every pay app.
Buildalytic tracks each pay application, retainage and lien waiver by job, shows what is holding payment, and has Brody follow up with the GC, owner or supplier until it moves.
One full Platform plan. No standard setup fee. Start with one supported workflow.
Plan your rollout
Pricing, security reviews, procurement and rollout across your projects and regions.