How to fill out AIA G702 and G703: a line-by-line pay application example

How to fill out G702 and G703 line by line, with a $1,250,000 subcontract worked example: change orders, stored materials, retainage step-down and a checklist.

By Buildalytic Research Desk16 min read

Editorial scene of a subcontractor pay application being checked before submission
Illustrative editorial scene. The project and figures in the worked example are fictional; form structure summarized from AIA's published instructions, checked November 17, 2026.
The short answer

To fill out an AIA G702 and G703 pay application, complete the G703 continuation sheet first: one row per schedule of values line, with previous work, work this period, stored materials, total to date, percent complete and balance. Then carry the G703 totals to the G702 summary, apply retainage, subtract previous certificates to get the current payment due, sign and notarize. Buildalytic tracks where each pay app sits after you submit it.

What to take away

  • Fill out the G703 continuation sheet first, then carry its totals to the G702.
  • Column G on the G703 (previous plus this period plus stored) must equal line 4 on the G702.
  • Stored materials move from column F to column E only when they are installed, never because they were paid.
  • A retainage step-down changes line 5, and the release shows up in the current payment due.
  • Most rejections come from numbers that do not tie, missing backup, or an unsigned or unnotarized form.

What are AIA G702 and G703?

The G702 is the Application and Certificate for Payment. It is a one-page summary: contract sum, change orders, work completed and stored to date, retainage, previous payments and the payment due now. The G703 is the Continuation Sheet. It breaks the contract sum into the lines of your schedule of values and shows progress on each line.

There are two versions most subcontractors see. The G702 and G703 (1992 editions) are written for a contractor billing an owner, with an architect certifying the amount. The G702S and G703S (2017 editions) are the contractor to subcontractor versions. AIA's own description of the S versions says the subcontractor completes the G703S, transfers the summary to the G702S, signs it, has it notarized and sends both to the contractor. The S version drops the architect's certificate.

Many general contractors require the AIA forms; others accept a pay application in the same layout from billing software or their own portal. The math is identical either way. AIA notes its documents may need changes to comply with state or local law, so check your subcontract before you copy a format.

Sources: AIA Contract Documents: Instructions, G702-1992 Application and Certificate for Payment; AIA Contract Documents: Instructions, G702S-2017 Application and Certificate for Payment, Contractor-Subcontractor Version; AIA Contract Documents: Instructions, G703S-2017 Continuation Sheet, Contractor-Subcontractor Version

What you need before you fill out a pay application

Gather six things before you open the form. Billing from memory is how lines stop tying.

First, the approved schedule of values, the same one the GC accepted at the start. Second, the previous pay application as certified, not as you submitted it, because the GC may have cut lines. Third, the change order log with approval dates. Fourth, a stored materials log with invoices and delivery records. Fifth, the subcontract pages on retainage, billing dates, required backup and waiver forms. Sixth, the field quantities or percent complete for each line, signed off by the person who walked the work.

The worked example: a $1,250,000 electrical subcontract

Every number in this guide comes from one illustrative project so you can follow the math from the G703 to the G702. The subcontract and company are fictional. This is Application No. 6, for the period ending October 31, 2026.

Retainage terms in this example: 10 percent on completed work and stored materials until the subcontract is 50 percent complete, then 5 percent, with the GC's written approval. The GC approved the reduction before this billing, so this is the first application at 5 percent. Your contract terms will differ; use them, not these.

The worked example: a $1,250,000 electrical subcontract
ItemIllustrative value
Original subcontract sum$1,250,000
Change Order 1 (approved in an earlier month)+$42,000, added circuits for tenant equipment
Change Order 2 (approved this month)+$18,500, relocated panel
Change Order 3 (approved this month)minus $6,000, deleted card access rough-in
Previous applicationNo. 5, certified as submitted
Stored materials at end of No. 5$165,000 of switchgear in a bonded warehouse
Retainage10% until 50% complete, then 5% (reduction approved)

How to fill out the G703 continuation sheet, column by column

The G703 has nine lettered columns. AIA's instructions describe what each holds; the summary below is in plain words. The two rules people break most: column D never includes stored materials, and column F is recalculated from scratch each period.

Total column C at the bottom of each page and again on the last page. It should start at the original contract sum and then reflect approved change orders. Percent complete is column G divided by column C, line by line and in total.

How to fill out the G703 continuation sheet, column by column
ColumnWhat goes in itCommon mistake
A: Item numberThe schedule of values line numberRenumbering lines between periods
B: Description of workThe scope for that line, as approvedChanging descriptions so lines no longer match the last application
C: Scheduled valueThe dollar value of the lineEditing base lines to absorb change orders
D: From previous applicationColumns D plus E from the last certified applicationIncluding last period's stored materials
E: This periodWork put in place this period, including stored items now installedBilling deliveries as installed work
F: Materials presently storedValue of materials stored and not yet installed, as of todayAdding to last month's figure instead of recounting
G: Total completed and stored to dateD plus E plus FArithmetic not matching the row
H: Balance to finishC minus GNegative balances from overbilling a line
I: RetainageUsed only if retainage varies by lineFilling it in when one flat rate applies

Sources: AIA Contract Documents: Instructions, G703-1992 Continuation Sheet; AIA Contract Documents: Instructions, G703S-2017 Continuation Sheet, Contractor-Subcontractor Version

G703 example: every line of Application No. 6

Here is the full continuation sheet for the illustrative project. Change orders sit at the bottom as their own lines, which is how AIA's instructions suggest handling them, rather than editing the base schedule.

Read across any row to check it: D plus E plus F equals G, and C minus G equals H. Then check down: the column totals must add up the same way. In this example, 563,500 plus 188,000 plus 160,000 equals 911,500, and 1,304,500 minus 911,500 equals 393,000. Total percent complete is 911,500 divided by 1,304,500, or 69.9 percent.

G703 example: every line of Application No. 6
AB: DescriptionC: ScheduledD: PreviousE: This periodF: StoredG: To dateG/CH: Balance
1Mobilization and general conditions$62,500$50,000$6,250$0$56,25090%$6,250
2Submittals and engineering$37,500$37,500$0$0$37,500100%$0
3Underground rough-in$150,000$150,000$0$0$150,000100%$0
4Branch rough-in$375,000$225,000$75,000$0$300,00080%$75,000
5Switchgear and distribution$300,000$60,000$45,000$120,000$225,00075%$75,000
6Lighting fixtures and devices$200,000$20,000$30,000$40,000$90,00045%$110,000
7Low voltage and fire alarm$75,000$0$7,500$0$7,50010%$67,500
8Testing, closeout and as-builts$50,000$0$0$0$00%$50,000
CO1Added tenant circuits$42,000$21,000$21,000$0$42,000100%$0
CO2Relocated panel$18,500$0$9,250$0$9,25050%$9,250
CO3Deleted card access rough-in (credit)minus $6,000$0minus $6,000$0minus $6,000100%$0
Totals$1,304,500$563,500$188,000$160,000$911,50069.9%$393,000

Sources: AIA Contract Documents: Instructions, G703-1992 Continuation Sheet

How to show change orders on a pay application

Bill only approved change orders as contract lines. Pending or disputed work belongs in your change order log and in a cover note, not in column C. AIA's instructions say undisputed amounts in a construction change directive should be rolled into change orders; disputed amounts follow the dispute process in the general conditions.

A deduct change order is a line with a negative scheduled value. In this example the deleted card access scope is taken as fully complete in the period it was approved, so it reduces the total earned at once and leaves no balance. Ask your GC how they want credits shown; some prefer the credit netted into the affected base line.

The G702 has a change order summary box that splits additions and deductions between earlier months and this month. Its net figure must equal line 2 on the G702 and the sum of the change order lines in column C of the G703.

How to show change orders on a pay application
Change order summaryAdditionsDeductions
Approved in previous months$42,000$0
Approved this month$18,500$6,000
Totals$60,500$6,000
Net change by change orders$54,500

Sources: AIA Contract Documents: Instructions, G703-1992 Continuation Sheet

Stored materials: how column F works and what backup to attach

Column F is a snapshot of what is stored and not yet installed today. Start from last period's stored balance, subtract what was installed (that value moves to column E), and add new deliveries. Payment for stored materials does not reduce column F; installation does.

In this example, $45,000 of the warehoused switchgear was set this month, so it leaves column F and appears in column E on line 5. Lighting fixtures worth $40,000 arrived on site and were not yet hung, so they enter column F on line 6.

Backup is where stored materials get cut. Most subcontracts ask for some combination of the supplier invoice, a delivery ticket or bill of lading, photos showing the material tagged to the project, proof of insurance covering the stored location, and, for offsite storage, a bill of sale or warehouse receipt and a right for the GC or owner to inspect. Read your subcontract's stored materials clause and attach exactly what it lists, matched to the dollar amount in column F.

Stored materials: how column F works and what backup to attach
Stored materials roll-forwardLine 5 switchgearLine 6 fixturesTotal
Stored at end of Application No. 5$165,000$0$165,000
Less: installed this period (moves to column E)minus $45,000$0minus $45,000
Plus: new deliveries stored$0$40,000$40,000
Stored now (column F)$120,000$40,000$160,000

Sources: AIA Contract Documents: Instructions, G703S-2017 Continuation Sheet, Contractor-Subcontractor Version

How to fill out the G702 line by line

With the continuation sheet done, the G702 is mostly transfer work. Fill the header first: who the application goes to, the project, application number, period ending date and subcontract date. Then work down the numbered lines. The descriptions below are paraphrased.

Line 7 is the amount most often entered wrong. Use line 6 from the previous certified application, meaning what was actually approved, not what you asked for. If the GC cut your last pay app, your line 7 is smaller than your own records suggest.

How to fill out the G702 line by line
G702 lineWhat it isHow it is calculatedExample
1Original contract (or subcontract) sumFrom the contract$1,250,000
2Net change by change ordersNet of the change order summary$54,500
3Contract sum to dateLine 1 plus or minus line 2$1,304,500
4Total completed and stored to dateColumn G total on the G703$911,500
5aRetainage on completed workRate times columns D plus E5% of $751,500 = $37,575
5bRetainage on stored materialsRate times column F5% of $160,000 = $8,000
5 totalTotal retainage5a plus 5b, or column I total$45,575
6Total earned less retainageLine 4 minus line 5 total$865,925
7Less previous certificates for paymentLine 6 from the prior certified application$655,650
8Current payment dueLine 6 minus line 7$210,275
9Balance to finish, including retainageLine 3 minus line 6$438,575

Sources: AIA Contract Documents: Instructions, G702S-2017 Application and Certificate for Payment, Contractor-Subcontractor Version

Retainage reduction: how a step-down changes the pay app

Application No. 5 had $728,500 completed and stored (the $563,500 now in column D plus the $165,000 that was stored). At 10 percent, retainage was $72,850 and line 6 was $655,650. That is the line 7 figure above.

In Application No. 6, retainage is figured at 5 percent on everything to date, so total retainage drops to $45,575. The $27,275 difference is released inside this payment. Gross progress this period was $183,000 (column G rose from $728,500 to $911,500), and $183,000 plus the $27,275 release equals the $210,275 current payment due.

Two cautions. First, do not reduce retainage on your own; bill at the reduced rate only after written approval, and attach it. Second, some contracts reduce the rate only on future work, leaving earlier retainage at 10 percent. That math is different, so follow the clause. State law can also cap or regulate retainage, so check the statute for your state before you assume a rate.

Retainage reduction: how a step-down changes the pay app
FigureIf retainage stayed at 10%With approved step-down to 5%
Line 4: completed and stored$911,500$911,500
Line 5: total retainage$91,150$45,575
Line 6: earned less retainage$820,350$865,925
Line 7: previous certificates$655,650$655,650
Line 8: current payment due$164,700$210,275
Line 9: balance including retainage$484,150$438,575

Does your pay application tie? Five checks before you sign

Run these checks every time. They take ten minutes and catch most of what a GC's reviewer would catch.

Does your pay application tie? Five checks before you sign
CheckMust equalExample
G702 line 3G703 column C total$1,304,500 = $1,304,500
G702 line 4G703 column G total$911,500 = $911,500
G702 line 2Change order summary net and change order lines in column C$54,500 = $42,000 + $18,500 minus $6,000
G703 column DPrevious certified application columns D plus E$563,500
G702 lines 6 plus 9G702 line 3$865,925 + $438,575 = $1,304,500

The certification, signature and notarization block

The signature block on the G702 is a certification, not a formality. In your own words, the signer is stating that the work billed was done per the contract documents, that you have paid for the work covered by earlier payments you received, and that the current amount is due. Do not sign it if lower tiers from last month are still unpaid without telling the GC.

AIA's instructions say the contractor or subcontractor signs and has the form notarized. The signer should show the capacity they sign in, such as president or partner, and the authority they act under, and attach a copy of the authorizing resolution where appropriate.

Whether a wet-ink notary, an electronic notary or no notary is acceptable depends on your subcontract and the GC's process, so ask once at the start of the job and write the answer down. Fill the notary section completely: state, county, date, notary signature and commission expiration. A blank commission date is an easy reason to send a pay app back.

Sources: AIA Contract Documents: Instructions, G702-1992 Application and Certificate for Payment; AIA Contract Documents: Instructions, G702S-2017 Application and Certificate for Payment, Contractor-Subcontractor Version

The architect's certificate for payment

On the prime G702, the lower right section is the architect's certificate. After reviewing the G702 and G703, the architect certifies the amount they find due. AIA's instructions allow the architect to certify a different amount than requested; when that happens, the architect initials each changed figure on both forms, attaches an explanation and forwards the forms to the owner. The owner pays the contractor the certified amount.

Subcontractors do not fill out this section. The G702S drops it, and your pay app is reviewed by the GC, who rolls it into their own G702 to the owner. That is why your billing date matters: if your pay app reaches the GC after they compile the owner application, your work waits a month. When the architect cuts a line on the GC's application, expect the GC to pass the cut to the matching line on yours, and ask for the initialed explanation.

Sources: AIA Contract Documents: Instructions, G702-1992 Application and Certificate for Payment; AIA Contract Documents: Instructions, G702S-2017 Application and Certificate for Payment, Contractor-Subcontractor Version

Common reasons a G702 and G703 get rejected

Most returns are fixable in a day, but they cost a full billing cycle if they miss the GC's cutoff. These are the patterns to look for before you submit.

Common reasons a G702 and G703 get rejected
Rejection reasonHow to prevent it
Column D does not match last month's certified columns D plus EStart from the certified copy, not your draft
Stored materials billed with no invoice or insurance backupAttach a backup set that adds to column F exactly
Pending change order billed in column CBill only fully executed change orders
Retainage reduced without approvalAttach the written approval with the first reduced pay app
Percent complete higher than the field supportsHave the superintendent sign off quantities before billing
Unsigned, unnotarized or incomplete notary blockCheck the signature page last, every time
Missing lien waivers or certified payrollsMatch the GC's required attachment list
Submitted after the GC's billing cutoffCalendar the cutoff for every job

Pre-submission checklist for an AIA pay application

Print this or build it into your billing routine. Every item should be checked before the pay app leaves your office.

Pre-submission checklist for an AIA pay application
ItemCheck
HeaderApplication number, period ending date and project name match the GC's records
Schedule of valuesSame lines, same order and same values as the approved schedule
Column DTies to the last certified application
Column ESupported by field quantities or a signed percent complete
Column FRecounted this period; backup totals match
Change ordersOnly executed change orders; summary box matches line 2
RetainageRate and any reduction match the contract and approvals
Line 7Equals line 6 of the previous certified application
Tie-outLines 6 plus 9 equal line 3
Signature and notarySigner, capacity, date and full notary block complete
AttachmentsConditional waiver for this amount, unconditional for last payment, payrolls or other required documents
DeliverySent through the GC's required method before the cutoff

Submitting through GC pay application portals

Many GCs now take pay applications through a payment portal rather than email. GCPay, for example, says GCs on its platform can require subcontractors to submit official AIA G702 and G703 forms on designated projects and can run lien waiver exchange inside the same process (checked November 17, 2026).

Portals change the steps, not the math. Usually you enter or upload the schedule of values once, update columns E and F each period, attach backup and waivers, and sign electronically. Check three things on your first billing in a new portal: that the schedule of values matches your approved one, that the previous application totals carried over correctly, and whether the GC still wants a notarized PDF uploaded alongside the portal entry.

If you bill several GCs, keep your own master record of each pay app: amount, date submitted, portal status and what was cut. Portals show one GC's view; your cash depends on all of them.

Sources: GCPay: AIA form for subcontractor payment application

How Buildalytic helps after the pay app is submitted

Buildalytic payment intelligence for subcontractors shows where each pay application sits across every GC and owner: submitted, reviewed, approved, released, paid. It tracks retainage per project and pay period with release forecasts, flags approved change orders that have not been billed, and tracks conditional and unconditional lien waivers so a payment is not held over a missing one.

Brody then follows up with the right contact on what is stuck, in priority order, and records the answer. Your team still prepares and signs the pay application.

Sources: Buildalytic: Payment intelligence for subcontractors

Common questions

How do you fill out a G702 and G703?

Fill out the G703 first, one row per schedule of values line: previous work, this period, stored materials, total, percent and balance. Carry the column C and G totals to G702 lines 3 and 4, calculate retainage, subtract the previous certified line 6, then sign and notarize.

What is the difference between G702 and G702S?

The G702 is for a contractor billing an owner and includes an architect's certificate for payment. The G702S is the contractor to subcontractor version from 2017. The subcontractor sends it to the contractor, and it has no architect certification section.

Do I have to notarize an AIA G702?

AIA's instructions say the form should be signed and notarized. Whether your GC requires a notary, accepts electronic notarization or waives it is set by your subcontract and their process. Ask at the start of the job and keep the answer with your billing records.

What goes in column F of the G703?

Column F holds the value of materials stored and not yet installed, as of this application. Recalculate it each period. When stored items are installed, their value moves to column E. Payment for stored materials does not reduce column F.

How is retainage calculated on a G702?

Line 5a is the retainage rate times completed work (G703 columns D plus E). Line 5b is the rate times stored materials (column F). If retainage varies by line, use the column I total instead. Line 6 is line 4 minus total retainage.

What is line 7 on the G702?

Line 7 is previous certificates for payment: line 6 from the prior application as it was certified. If the GC or architect cut your last application, use the certified amount, not the amount you requested, or your current payment due will be wrong.

Can I bill a pending change order on a pay application?

Normally no. Bill only executed change orders as lines on the G703 and in the change order summary. Track pending or disputed changes in your change order log and raise them separately, unless your subcontract says otherwise.

Where can I get official AIA G702 and G703 forms?

AIA sells them through AIA Contract Documents. On November 17, 2026, its site listed the G702S and G703S at $59.99 each for one-time use, with a subscription option. Many billing tools and GC portals produce the same layout.

Sources and editorial notes

Prepared with AI assistance. Reference date: 2026-11-17. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.

How we prepare and update field notes
See it on your workflow

Know where every pay app sits.

Bring your open pay applications across GCs. See status, retainage and unbilled change orders in one view, with Brody following up on what is stuck.