Skip to content
Field notes / Construction finance and procurement

Mechanics lien deadlines by state (2026): notice, filing and suit in 15 states

Mechanics lien deadlines by state for the 15 largest construction markets: notice, filing and suit deadlines from each statute, plus a worked example.

By Buildalytic Research Desk19 min read

Editorial scene of a subcontractor reviewing unpaid invoices against lien deadlines
Illustrative editorial scene. Deadlines summarized from state statutes and official state pages, checked November 17, 2026. Not legal advice; confirm with the statute or an attorney.
The short answer

Mechanics lien deadlines vary by state: in the 15 largest construction states, a private-project lien is usually due between 75 days and 8 months after your last work or project completion. Suit deadlines run from 90 days after recording in California to 2 years in Illinois and Pennsylvania. Many states also require an early preliminary notice. This is a summary, not legal advice. Buildalytic tracks retainage and lien waivers by job.

What to take away

  • Lien deadlines run from different triggers: first furnishing, last furnishing, project completion, a recorded notice, or the month work was done.
  • Preliminary notices are due early, often 15 to 45 days after you start, and missing one can cut off lien rights for earlier work.
  • Standard commercial filing deadlines in these 15 states range from 75 days (Ohio) to 8 months (New York) after last work or completion, and a recorded notice can shorten them.
  • Texas shortened and simplified its deadlines for original contracts entered on or after January 1, 2022 (HB 2237).
  • Public projects use payment bond claims instead of liens; on federal jobs the Miller Act gives second-tier claimants 90 days for notice and 1 year to sue.

How mechanics lien deadlines work

A mechanics lien lets an unpaid contractor, sub or supplier put a claim against the property it improved. Every state sets strict deadlines, usually in three steps: a preliminary notice early in the job, the lien filing after work ends, and a lawsuit to enforce the lien. Miss any one and the lien can fail, even if the debt is real.

Not legal advice. This guide summarizes private-project rules from each state's statute or official state page, checked November 17, 2026. Statutes have exceptions by project type, owner type and claimant tier, and they change. Before you rely on a date, read the statute and confirm with a construction attorney in that state. Where we could not confirm a rule from an official source, the table says Not confirmed.

Mechanics lien deadlines by state: master table

Private projects, commercial unless noted. Deadlines are summarized; see the state sections for triggers and exceptions.

Mechanics lien deadlines by state: master table
StatePreliminary noticeFile the lienEnforce (file suit)
CaliforniaWithin 20 days of first furnishing (subs and suppliers; laborers exempt)90 days after completion; 60 days (direct contractor) or 30 days (others) after a recorded notice of completion90 days after recording
Texas (contracts from Jan 1, 2022)15th day of 3rd month after each month of unpaid work (2nd month residential)15th day of 4th month after last work (3rd month residential)1 year after the last day to file the lien affidavit
FloridaNotice to owner within 45 days of starting (claimants not in privity; laborers exempt)90 days after final furnishing1 year after recording
New YorkNone in Lien Law 108 months after completion or final furnishing; 4 months for a single-family dwellingLien expires 1 year after filing unless suit is started or the lien is extended
IllinoisSubs: notice within 90 days after completing their work; 60 days from first furnishing for owner-occupied single-familyContractor: 4 months after completion to bind third parties2 years after completion; 30 days after a written demand to sue
PennsylvaniaNotice of Furnishing within 45 days on $1.5M+ projects with a Notice of Commencement; subs give formal notice 30 days before filing6 months after completion of the claimant's work2 years after filing
OhioNotice of furnishing within 21 days of first furnishing, if a notice of commencement was recorded75 days after last work (60 days for 1 to 2 family homes and residential condos)Lien lasts 6 years; 60 days after a notice to commence suit
GeorgiaCheck the statute90 days after completing work or furnishing materials (2008 act text)365 days after filing the lien (2008 act text)
North CarolinaNotice to lien agent within 15 days of first furnishing ($40,000+ projects, with exceptions)120 days after last furnishing180 days after last furnishing
MichiganNotice of furnishing within 20 days of first furnishing (subs and suppliers)90 days after last furnishing1 year after recording
New JerseyResidential only: Notice of Unpaid Balance within 60 days after last work90 days after last work; residential 120 days, after arbitration1 year after last work; 30 days after a written notice to sue
Virginia1 to 2 family homes with a lien agent on the permit: 30 days after first furnishing90 days from the end of the month of last work, and no later than 90 days after completion6 months after recording or 60 days after completion, whichever is later
WashingtonNotice to owner from suppliers and lower tiers protects work from 60 days before the notice90 days after last furnishing8 calendar months after recording
ArizonaWithin 20 days of first furnishing (all but wage laborers)120 days after completion; 60 days after a recorded notice of completion6 months after recording
ColoradoNone; notice of intent at least 10 days before filing4 months after last labor or materials6 months after last work or completion

Sources: California CSLB, Homeowner's guide to preventing mechanics liens; Texas HB 2237 (87th Legislature), enrolled text; Florida Statutes 713.08, Claim of lien; New York Lien Law section 10; Illinois Mechanics Lien Act, 770 ILCS 60/24; Pennsylvania Mechanics' Lien Law of 1963; Ohio Revised Code 1311.06; Georgia SB 374 (2008), mechanics and materialmen liens; North Carolina G.S. 44A-12; Michigan Construction Lien Act, MCL 570.1111; New Jersey P.L. 2010, c.119 (Construction Lien Law amendments); Code of Virginia 43-4; Washington RCW 60.04.091; Arizona Revised Statutes 33-993; Colorado Revised Statutes Title 38 (2024), sections 38-22-109 and 38-22-110

Preliminary notice requirements by state

A preliminary notice tells the owner, and often the prime and lender, that you are on the job and may claim a lien. In most states that require one, it is a condition of the lien itself. The clock usually starts on your first day of work or first delivery, which is why it gets missed: nobody is thinking about liens in week one.

Of the 15 states here, California, Arizona, Florida, Michigan, Ohio, North Carolina and Washington have early notice rules that reach many private jobs, with different scopes (Ohio's applies only when a notice of commencement is recorded, North Carolina's only where a lien agent is designated). Texas requires a monthly notice for each month of unpaid work rather than a single notice at the start. Pennsylvania's Notice of Furnishing applies only to projects of $1.5 million or more where the owner filed a Notice of Commencement. Virginia's applies only to one- and two-family homes where the permit names a lien agent. New Jersey requires a Notice of Unpaid Balance only on residential work. New York and Colorado have no early notice, though Colorado requires a notice of intent before filing.

Late notice is not always fatal, but it costs money. California and Arizona limit a late notice to work done in the 20 days before it was given and after. Michigan keeps the lien for earlier work except to the extent the owner already paid under a sworn statement or waiver. Washington's notice protects only work from 60 days before it was given. Send the notice at mobilization and keep proof of delivery.

Sources: California CSLB, Homeowner's guide to preventing mechanics liens; Arizona Revised Statutes 33-993; Florida Statutes 713.08, Claim of lien; Michigan Construction Lien Act, MCL 570.1111; Ohio Revised Code 1311.06; North Carolina G.S. 44A-12; Washington RCW 60.04.091; Texas HB 2237 (87th Legislature), enrolled text; Pennsylvania Mechanics' Lien Law of 1963; Code of Virginia 43-4; New Jersey P.L. 2010, c.119 (Construction Lien Law amendments); Colorado Revised Statutes Title 38 (2024), sections 38-22-109 and 38-22-110

How long do you have to file a mechanics lien?

For private commercial work in these states, the filing window runs from 75 days (Ohio) to 8 months (New York). Florida, Michigan, Washington, Georgia and New Jersey use 90 days from your last work. North Carolina gives 120 days, Colorado 4 months, Pennsylvania 6 months. Texas counts to the 15th day of the fourth month after the month you last worked. California and Arizona count from completion of the whole project, and a recorded notice of completion shortens the window sharply.

Residential work often has shorter or different deadlines. Ohio drops to 60 days for one- and two-family homes, Texas to the 15th day of the third month, New York to 4 months for a single-family dwelling, and New Jersey routes residential claims through a Notice of Unpaid Balance and arbitration before the lien can be filed.

Sources: Ohio Revised Code 1311.06; New York Lien Law section 10; Florida Statutes 713.08, Claim of lien; Michigan Construction Lien Act, MCL 570.1111; Washington RCW 60.04.091; Georgia SB 374 (2008), mechanics and materialmen liens; New Jersey P.L. 2010, c.119 (Construction Lien Law amendments); North Carolina G.S. 44A-12; Colorado Revised Statutes Title 38 (2024), sections 38-22-109 and 38-22-110; Pennsylvania Mechanics' Lien Law of 1963; Texas HB 2237 (87th Legislature), enrolled text; California CSLB, Homeowner's guide to preventing mechanics liens; Arizona Revised Statutes 33-993

Deadline to enforce a mechanics lien

Filing the lien is not the end. In every state here, the lien expires unless you file suit to foreclose it within a set time, and several states let the owner shorten that time with a demand or notice. California gives 90 days after recording. Arizona and Virginia give about 6 months. Washington gives 8 calendar months after recording. Florida, Michigan, New York and New Jersey use 1 year. Illinois and Pennsylvania use 2 years. Ohio's lien lasts 6 years, but an owner can serve a notice to commence suit that gives you only 60 days.

Owner-triggered shortcuts matter: Florida's notice of contest cuts the time to 60 days, Illinois's written demand to 30 days, New Jersey's written notice to 30 days, and Ohio's notice to commence suit to 60 days. If one arrives, call your attorney that day.

Sources: California CSLB, Homeowner's guide to preventing mechanics liens; Arizona Revised Statutes 33-993; Code of Virginia 43-4; Washington RCW 60.04.091; Florida Statutes 713.08, Claim of lien; Michigan Construction Lien Act, MCL 570.1111; New York Lien Law section 10; New Jersey P.L. 2010, c.119 (Construction Lien Law amendments); Illinois Mechanics Lien Act, 770 ILCS 60/24; Pennsylvania Mechanics' Lien Law of 1963; Ohio Revised Code 1311.06

Lien deadlines in California, Washington, Arizona and Colorado

California: subs and suppliers serve a preliminary notice within 20 days of starting work or delivering materials; laborers do not need one. A lien must be recorded within 90 days of completion of the work. If the owner records a notice of completion, the prime has 60 days and subs and suppliers have 30 days. The lien and a Notice of Mechanics Lien must be served on the owner, and foreclosure suit must be filed within 90 days of recording. We summarized California from the Contractors State License Board's official guide because the legislature's code site blocked our automated reader; check Civil Code sections 8200 to 8494 before filing.

Washington: a notice to owner protects lien rights only for work and materials supplied from 60 days before the notice (10 days on a new single-family home). People who contract directly with the owner, laborers, and subs who contract directly with the prime are exempt, except on owner-occupied residential remodels. The lien must be recorded within 90 days after you stop furnishing, and suit filed within 8 calendar months after recording, with the owner served within 90 days of filing.

Arizona: everyone except people performing labor for wages serves a 20-day preliminary notice. The lien is due 120 days after completion, or 60 days after a recorded notice of completion, and the lien lasts 6 months after recording unless suit is filed and a notice of pending action recorded.

Colorado: no preliminary notice, but a notice of intent to file must be served at least 10 days before the lien statement is filed. Most claimants have 4 months after their last labor or materials to file, and suit plus a recorded notice of the action must come within 6 months after last work or completion.

Sources: California CSLB, Homeowner's guide to preventing mechanics liens; Washington RCW 60.04.091; Arizona Revised Statutes 33-993; Colorado Revised Statutes Title 38 (2024), sections 38-22-109 and 38-22-110

Texas lien deadlines after HB 2237

Texas rewrote much of its lien law in HB 2237, effective January 1, 2022. The changes apply only to original contracts entered into on or after that date; older contracts follow the prior law. The enrolled bill confirms the new deadlines below.

Claimants other than the original contractor must send a notice of claim for unpaid labor or materials to both the owner and the original contractor by the 15th day of the third month after the month the work was done or materials delivered (second month on residential projects). Notice to the original contractor alone is not enough. Each unpaid month needs its own notice.

The lien affidavit is due by the 15th day of the fourth month after the month you last provided labor or materials (third month residential). For original contractors, the count starts from the month the original contract was completed, terminated or abandoned. Suit to foreclose must be filed by the first anniversary of the last day you could have filed the lien affidavit, and the owner can agree in a recorded writing to extend that to 2 years after you filed. Retainage claims have separate notice and filing rules in sections 53.057 and 53.052(d).

Sources: Texas HB 2237 (87th Legislature), enrolled text

Lien deadlines in Florida, Georgia, North Carolina and Virginia

Florida: lienors not in privity with the owner, except laborers, serve a notice to owner before starting or within 45 days after starting; sub-subs and suppliers to subs also serve the contractor. The claim of lien is due within 90 days after final furnishing and must be served on the owner within 15 days of recording. The lien lasts 1 year after recording, or 60 days after an owner's notice of contest.

Georgia: the 2008 act that rewrote Georgia's lien statute, effective March 31, 2009, sets the claim of lien deadline at 90 days after completion of the work or furnishing of materials, and requires a lien action within 365 days of filing, with a notice of the action filed within 30 days after suit. We could not read the current official code text, and we could not confirm the notice to contractor deadline from an official source, so verify both before relying on them.

North Carolina: on projects costing $40,000 or more, other than an owner-occupied single-family home, the owner designates a lien agent. Claimants send a notice to the lien agent within 15 days of first furnishing; a late notice can leave the lien behind a later recorded mortgage or sale. The claim of lien is due 120 days after last furnishing and suit 180 days after last furnishing.

Virginia: the memorandum of lien is due within 90 days from the last day of the month you last worked, and no later than 90 days after the project is completed or work otherwise ends. It may not include work done more than 150 days before your last day, though retainage up to 10 percent of the contract can be included. Suit is due by the later of 6 months after recording or 60 days after completion.

Sources: Florida Statutes 713.08, Claim of lien; Georgia SB 374 (2008), mechanics and materialmen liens; North Carolina G.S. 44A-12; Code of Virginia 43-4

Lien deadlines in New York, New Jersey and Pennsylvania

New York: no preliminary notice. File within 8 months after completion of the contract or final performance or furnishing, or 4 months on a single-family dwelling. The lien lasts 1 year after filing. You can extend it by filing an extension within that year, except on a single-family dwelling, which needs a court order.

New Jersey: on commercial work, the lien claim is due within 90 days after the last work, services, material or equipment. On residential work, you first lodge a Notice of Unpaid Balance and Right to File Lien within 60 days, demand arbitration within 10 days of that, and file the lien within 10 days after the arbitrator's decision and within 120 days of last work. Suit is due within 1 year of last work, or within 30 days of a written notice requiring you to sue.

Pennsylvania: on projects of $1.5 million or more where the owner filed a Notice of Commencement in the State Construction Notices Directory, subs file a Notice of Furnishing within 45 days of first work. Subs must also give the owner formal written notice of intent at least 30 days before filing. The claim is due within 6 months after completion of your work, notice of filing must be served within 1 month, suit must start within 2 years of filing, and judgment must be entered within 5 years.

Sources: New York Lien Law section 10; New Jersey P.L. 2010, c.119 (Construction Lien Law amendments); Pennsylvania Mechanics' Lien Law of 1963

Lien deadlines in Illinois, Ohio and Michigan

Illinois: subs serve written notice of their claim on the owner and lender within 90 days after completing their work. On an existing owner-occupied single-family home, subs must notify the occupant within 60 days of first furnishing. A contractor's lien binds other creditors and buyers only if filed within 4 months after completion; as to the owner, it may be filed within 2 years. Suit is due within 2 years after completion, or 30 days after a written demand.

Ohio: if a notice of commencement was recorded, subs and suppliers serve a notice of furnishing within 21 days of first furnishing. The lien affidavit is due 75 days after last work, or 60 days on one- or two-family homes and residential condo units. The lien lasts 6 years, but a notice to commence suit gives you 60 days.

Michigan: subs and suppliers serve a notice of furnishing within 20 days after first furnishing. A late notice does not defeat the lien for later work, and earlier work survives except to the extent the owner already paid. The claim of lien is due within 90 days after last furnishing and suit within 1 year after recording.

Sources: Illinois Mechanics Lien Act, 770 ILCS 60/24; Ohio Revised Code 1311.06; Michigan Construction Lien Act, MCL 570.1111

How to calculate a lien deadline

Start by identifying the trigger. There are five common ones: your first day of work or delivery (preliminary notices), your last day of work or delivery or the completion of your own work (most lien deadlines, including Pennsylvania's), completion of the whole project (California, Arizona and Illinois's contractor rule), a recorded document such as a notice of completion or the lien itself (enforcement deadlines), and the calendar month (Texas and Virginia).

Then count exactly. Day counts are calendar days. Month counts end on the same date months later. Texas counts to the 15th of a later month, so work done anytime in June has the same deadline. Write down the last furnishing date the day it happens, with the delivery ticket or daily report that proves it.

Do not count on extra work to reset the clock. Whether punch list, warranty or corrective work extends a deadline depends on the state and the facts, and courts often look closely at it. File early, ahead of weekends and holidays, rather than testing the last day.

Worked example: one unpaid sub, seven states

Illustrative example. A mechanical sub on a private commercial job first delivers on February 2, 2026 and last works on June 12, 2026. It is unpaid for April, May and June. The prime's contract was signed in 2025. The table shows the deadlines the same facts would produce in seven states, assuming no notice of completion, notice to commence suit or other owner action.

The arithmetic: February 2 plus 15 days is February 17; plus 20 days is February 22; plus 45 days is March 19. June 12 plus 90 days is September 10; plus 120 days is October 10; plus 180 days is December 9. Four months after June 12 is October 12, and 8 months is February 12, 2027. In Texas, April work is noticed by July 15, May work by August 15 and June work by September 15, and the affidavit is due October 15.

Worked example: one unpaid sub, seven states
StatePreliminary noticeFile the lien bySue by
TexasJuly 15 (April), Aug 15 (May), Sept 15 (June)October 15, 2026October 15, 2027
FloridaMarch 19, 2026September 10, 20261 year after recording
North CarolinaFebruary 17, 2026 (lien agent)October 10, 2026December 9, 2026
MichiganFebruary 22, 2026September 10, 20261 year after recording
WashingtonSend early; protects work from 60 days before the noticeSeptember 10, 20268 months after recording
ColoradoNotice of intent at least 10 days before filingOctober 12, 2026December 12, 2026
New YorkNoneFebruary 12, 20271 year after filing

Sources: Texas HB 2237 (87th Legislature), enrolled text; Florida Statutes 713.08, Claim of lien; North Carolina G.S. 44A-12; Michigan Construction Lien Act, MCL 570.1111; Washington RCW 60.04.091; Colorado Revised Statutes Title 38 (2024), sections 38-22-109 and 38-22-110; New York Lien Law section 10

Public projects: bond claims, not liens

You generally cannot lien public property. On public jobs, the prime posts a payment bond and unpaid subs and suppliers make a claim against the bond instead. Each state has its own bond claim deadlines for state and local projects, separate from the lien rules above.

On federal projects, the Miller Act applies. A claimant with a direct contract with a subcontractor but no contract with the prime must give written notice to the prime within 90 days after its last labor or materials. Any suit on the bond must be brought no later than 1 year after the claimant's last labor or materials. First-tier subs with a direct contract with the prime may sue after 90 days unpaid, within the same 1-year limit.

Sources: 40 U.S.C. 3133 (Miller Act), GovInfo

Lien deadline tracking checklist

Use this for every private job, starting before you mobilize.

Lien deadline tracking checklist
StepWhenRecord
Identify the state, owner, property and whether the job is public or privateBefore signingLegal description and owner name from the contract or public records
Check for a notice of commencement, lien agent or permit designationBefore mobilizingCopy of the notice or permit
Log the first furnishing dateDay oneDelivery ticket or daily report
Send the preliminary noticeDay one, inside the state's windowProof of delivery
Track unpaid amounts by monthEach billing cycleAging report by job; Texas monthly notices sent
Log the last furnishing dateLast day on siteDelivery ticket or daily report
Calendar the lien and suit deadlinesSame dayTwo reminders before each deadline
Serve notice of intent, where requiredBefore filingProof of service
File and serve the lienWell before the deadlineRecorded copy and proof of service
Calendar the enforcement deadlineDay of recordingAttorney engaged
Watch for owner notices that shorten deadlinesUntil paidNotice of contest or demand to sue logged the day received

Common lien deadline mistakes

Counting from the wrong date: using invoice dates instead of the last day labor or materials were furnished, or your own completion when the state counts from project completion.

Skipping the preliminary notice because the GC 'always pays.' The notice costs little and keeps the option open.

Assuming one state's rules apply everywhere. A sub working in Ohio and Michigan faces 21-day and 20-day notice rules and different filing windows.

Filing the lien and forgetting the suit deadline. In California, that window is 90 days from recording.

Signing an unconditional waiver before the money clears, which can give up the very rights the deadlines protect. See our guide to statutory lien waiver forms by state.

How Buildalytic helps

Buildalytic tracks retainage per line and per job, forecasts release against contract terms, and generates the correct conditional or unconditional, progress or final lien waiver with the right amount and date, so nothing is signed early and nothing is left uncollected. Brody can follow up with the right contact on payment status by call or text.

Buildalytic does not determine your legal deadlines. Record the dates your attorney confirms, and use the shared job record to keep the notices, waivers and payment history in one place.

Common questions

How long do you have to file a mechanics lien?

It depends on the state. In the 15 largest construction states, private commercial filing deadlines range from 75 days after last work in Ohio to 8 months in New York, with many states at 90 days. Some states count from project completion instead of your last day.

Which states require a preliminary notice to file a lien?

Among the 15 states here, California, Arizona, Florida, Michigan, Ohio, North Carolina and Washington have early notice rules that reach many private jobs. Texas requires monthly notices of unpaid work, and Pennsylvania, Virginia and New Jersey require notices only on certain projects.

What is the lien deadline in Texas?

For original contracts from January 1, 2022, subcontractors and suppliers file the lien affidavit by the 15th day of the fourth month after the month they last worked, or the third month on residential projects, and must sue within one year after the last day to file.

What is the lien deadline in California?

Generally 90 days after completion of the project. If the owner records a notice of completion, the direct contractor has 60 days and subs and suppliers have 30 days. Suit to foreclose must be filed within 90 days after the lien is recorded.

Does the lien deadline run from my last invoice?

Usually not. Most states count from the last day you furnished labor or materials, or from project completion. Invoice dates and payment due dates are generally not the trigger, so keep delivery tickets and daily reports that prove your last day.

Can I file a mechanics lien on a public project?

Generally no. Public projects use payment bond claims instead. On federal jobs, the Miller Act requires second-tier claimants to give notice within 90 days after last furnishing, and any suit must be filed within one year.

Is this guide legal advice?

No. It summarizes statutes and official state pages checked November 17, 2026. Lien laws have exceptions by project and claimant type and change often. Confirm every deadline with the statute or a construction attorney in the state before relying on it.

Sources and editorial notes

Prepared with AI assistance. Reference date: 2026-11-18. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.

How we prepare and update field notes
See it on your workflow

Keep every waiver and payment on one job record.

Bring one open job. See retainage held, the waiver each payment needs, and Brody following up on payment status.

Start with the call, text or record your team already handles. Review the expected outcome and the human handoff before choosing a rollout.

See lien waiver tracking Explore the relevant capability