On a Davis-Bacon job, every subcontractor at every tier must submit a certified payroll for each week it performs covered work, with a signed Statement of Compliance, and the prime contractor is responsible for collecting all of them. WH-347 is optional; the information is not. Many states add their own portal and schedule, such as California's DIR eCPR, Washington's PWIA and New Jersey's Wage Hub. Buildalytic helps primes collect subcontractor payrolls and track missing weeks.
What to take away
- Every covered subcontractor files its own certified payroll, no matter how far down the chain it sits.
- Federal rules require a payroll for each week covered work is performed; WH-347 is one optional format.
- State portals run on their own schedules: weekly in New Jersey, at least monthly in California and Washington, every 30 days in New York, by the 15th in Illinois.
- No-work weeks are handled differently by each system, so ask the prime what it wants before the first gap.
- Late or missing payrolls can lead to suspended payments under 29 CFR 5.5 and to payment holds in your subcontract.
Do subcontractors have to submit certified payroll?
Yes. On federally funded or assisted construction covered by Davis-Bacon and Related Acts, the contract clauses in 29 CFR 5.5 say the contractor or subcontractor must submit certified payrolls weekly, for each week in which covered work is performed. The same clauses must be inserted into every subcontract, along with a clause requiring each subcontractor to pass them down to its own lower-tier subs. That is why a second-tier drywall finisher or a third-tier traffic control company files just like the prime.
The prime contractor carries the collection duty. The regulation says the prime is responsible for the submission of all certified payrolls by all subcontractors, and it is responsible for lower-tier compliance with the contract clauses. In practice, that means the prime will chase you every week until your payroll arrives.
State prevailing wage laws add their own rules. California's DIR says all contractors and subcontractors on public works must submit certified payroll records directly to the Labor Commissioner, and that sending them to the prime or awarding body does not satisfy that requirement. Washington, New York, Illinois and New Jersey also require filing by each contractor, as covered below.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); California DIR, Frequently Asked Questions on Public Works
Certified payroll for lower-tier subcontractors
A lower-tier sub usually sends its payroll up the chain: to the sub that hired it, which forwards it to the prime, which submits the package to the agency or owner. Some primes ask lower-tier subs to send directly to them to save a step. Either way, the obligation is yours. If you hire your own subs, the flow-down clause means you must collect their payrolls too.
Lower-tier subs often learn they are on a prevailing wage job only when the first payroll request arrives. Ask before you mobilize: is the project covered, which wage determination applies, who receives the payroll, and on what day. Get the wage determination number and the classifications you will use in writing.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR)
What the prime contractor will ask you for
Expect a startup packet before your first day on site and a weekly packet after that. The exact list comes from your subcontract and the prime's own compliance program, so treat the table below as a typical starting point, not a legal minimum.
| Item | When | Why it matters |
|---|---|---|
| Signed subcontract with the labor standards clauses and wage determination | Before mobilizing | The clauses and wage determination must be in every subcontract under 29 CFR 5.5(a)(6) |
| Classification list mapping each worker to a wage determination classification | Before mobilizing | Workers must be paid for the classification of work actually performed |
| Apprentice registration evidence and program ratios | Before an apprentice works on site | Apprentice rates apply only to registered apprentices within the ratio |
| Fringe benefit plan documents | Before the first payroll that claims fringe credit | Supports the fringe credit you claim on the payroll |
| Weekly certified payroll with signed Statement of Compliance | Every week covered work is performed | Required by 29 CFR 5.5(a)(3)(ii) |
| No-work statement | Weeks with no work, if the prime or state requires it | Keeps the payroll sequence complete for reviewers |
| State portal confirmation | On the state's schedule | Shows the state filing was made, separate from the federal submission |
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR)
How to submit certified payroll as a subcontractor, step by step
1. Close the week. Collect daily hours by worker and by classification from timecards or daily reports. If a worker did two kinds of work, keep the hours separate; each classification goes on its own line.
2. Run payroll and check the rates. Compare each worker's hourly rate and fringe against the wage determination in your subcontract. Overtime is paid on the basic hourly rate, not on the fringe.
3. Prepare the certified payroll. Use WH-347 or any format that contains the same information. On the submitted copy, use an individual identifying number such as the last four digits of the Social Security number. Full Social Security numbers and home addresses must not appear on weekly transmittals, although the prime may require them for its own records.
4. Sign the Statement of Compliance. The person who pays or supervises payment signs it, by hand or with a legally valid electronic signature. The signature certifies that the records are correct, workers were paid in full without improper deductions, and rates meet the wage determination.
5. Send it up the chain by the date in your subcontract. Keep proof of when you sent it.
6. File with the state, if required. A state portal filing is a separate step with its own deadline.
7. Keep everything. Federal rules require contractors and subcontractors to keep payrolls and basic records for at least 3 years after all work on the prime contract is completed. Illinois requires 5 years for its records.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); U.S. Department of Labor, Form WH-347 page; Illinois Prevailing Wage Act, 820 ILCS 130/5
WH-347 or your own format?
DOL says use of Form WH-347 is optional, but the weekly payroll information is required. Any format works if it contains everything the regulation lists and comes with the signed Statement of Compliance. The certification on the back of WH-347 satisfies the Statement of Compliance requirement when it is properly executed.
WH-347 payrolls are numbered in sequence starting at 1, and the form has a box to mark the final week of work. Keep your numbering continuous across the job, including any no-work statements, so a reviewer can see that no week is missing. For a column-by-column walkthrough, see our guide to filling out WH-347 line by line.
Sources: U.S. Department of Labor, Form WH-347 page; 29 CFR 5.5, Contract provisions and related matters (eCFR)
State certified payroll portals: California, Washington, New York, Illinois and New Jersey
State systems run alongside the federal requirement on projects where both apply, and on their own on state-funded public works. Each has its own schedule and its own way of handling gaps and fixes. The summary below is high level and comes from each agency's own pages; confirm the details for your project with the awarding agency.
| State | Where it goes | How often | No-work periods | Corrections |
|---|---|---|---|---|
| California | DIR eCPR, directly to the Labor Commissioner | At least monthly, within a month after the payroll period ends; weekly is DIR's stated best practice | Statement of Non-Performance | A Statement of Non-Performance amendment replaces a payroll filed for a period with no work |
| Washington | L&I online system (PWIA) | At least once a month (RCW 39.12.120) | No Work Performed Report in PWIA | Create Amendment on the filed report |
| New York | NYSDOL Certified Payroll portal; NYC public work uses NYC's own system | At least once every 30 days, for work from January 1, 2026 | Weeks with no work must be reported; a pause feature covers long gaps | Not described on the FAQ page |
| Illinois | IDOL Certified Transcript of Payroll portal | By the 15th of each month for the prior month | Not filed for months or weeks with no work | Withdraw for the current month only; prior months lock after the 15th |
| New Jersey | NJ Wage Hub, plus a hard copy to the contracting public body | Weekly, required since August 15, 2024 | Not stated in the NJDOL notice | Not stated in the NJDOL notice |
Sources: California DIR, Frequently Asked Questions on Public Works; Washington RCW 39.12.120, Certified payroll records; Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions; New York State DOL, Electronic certified payroll FAQ; Illinois Prevailing Wage Act, 820 ILCS 130/5; Illinois Department of Labor, Certified payroll FAQ; NJDOL, Public works contractors must report certified payroll on NJ Wage Hub
State portal details subcontractors trip on
California: DIR says each contractor and subcontractor must submit directly to the Labor Commissioner. Sending your payroll to the prime, a union or a labor compliance program does not count as the DIR filing. DIR lists exemptions for some legacy projects, qualifying project labor agreements and small projects under its dollar thresholds.
Washington: L&I's PWIA instructions say each contractor must file certified payroll using L&I's online system at least once a month, and that contractors can be penalized for failing to file. Primes can view and request their subs' reports inside PWIA, and the awarding agency or prime may also ask for copies directly.
New York: NYSDOL's FAQ says contractors and subcontractors must submit at least once every 30 days starting January 1, 2026, and that filings more than 14 days late incur a $100 per day penalty.
Illinois: the Prevailing Wage Act requires each contractor and subcontractor to file by the 15th day of each month for the preceding month, and only for months with construction. IDOL recommends that every contractor file its own payroll, even if a sub has been submitting through the general contractor. A general contractor may rely on a lower-tier sub's certification unless it knowingly relies on a false one.
New Jersey: NJDOL announced that from August 15, 2024, registered public works contractors must submit certified payroll online through NJ Wage Hub and in hard copy to the contracting public body, under the Prevailing Wage Act's weekly payroll requirement.
Sources: California DIR, Frequently Asked Questions on Public Works; Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions; New York State DOL, Electronic certified payroll FAQ; Illinois Prevailing Wage Act, 820 ILCS 130/5; Illinois Department of Labor, Certified payroll FAQ; NJDOL, Public works contractors must report certified payroll on NJ Wage Hub
No-work certified payroll: what to file when your crew is off the job
Under the federal clause, a certified payroll is required for each week in which covered work is performed. The regulation does not require a payroll for a week with no work. Many primes still ask for a no-work statement so their weekly tracker shows a deliberate gap instead of a missing payroll. Check your subcontract and ask the prime how it wants gaps reported before the first one happens.
State systems differ. California offers a Statement of Non-Performance. Washington has a No Work Performed Report that covers a date range. New York requires weeks with no work to be reported and offers a pause for long breaks. Illinois says no filing is needed for a week or month with no work. A no-work statement for the federal side does not replace the state filing, and the reverse is also true.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); California DIR, Frequently Asked Questions on Public Works; Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions; New York State DOL, Electronic certified payroll FAQ; Illinois Department of Labor, Certified payroll FAQ
How to correct a certified payroll
Mistakes happen: a wrong classification, overtime paid at straight time, a fringe credit that does not match the plan. Fix the pay first. Pay the worker the difference, then submit a revised payroll for the same week and payroll number, clearly marked as revised, with a fresh signed Statement of Compliance. Keep the original and the revision together so a reviewer can see what changed and why.
On the state side, use the portal's own tool: Washington's Create Amendment, California's amendment process, or Illinois's withdrawal option for the current month. Do not wait for an audit. A clean correction trail is far easier to defend than an underpayment someone else finds.
Sources: Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions; California DIR, Frequently Asked Questions on Public Works; Illinois Department of Labor, Certified payroll FAQ
Fringe benefit and apprentice documentation
If you take credit for fringe benefits paid into a plan, 29 CFR 5.5(a)(3)(i)(C) requires records showing that the commitment to provide the benefits is enforceable, that the plan is financially responsible, that it was communicated in writing to the workers, and what it costs. Keep plan documents and contribution reports ready; the prime may ask for them before accepting your first payroll that claims fringe credit.
For apprentices, keep written evidence of the program's registration, each apprentice's registration, and the ratios and wage rates in the program. An apprentice may be paid less than the journeyworker rate only when individually registered in a program registered with DOL's Office of Apprenticeship or a recognized State Apprenticeship Agency, or during the first 90 days of certified probationary employment. Apprentices get fringe benefits as the program specifies; if the program is silent, they get the full fringe on the wage determination. An apprentice who is unregistered or over the allowed ratio must be paid the full rate for the work performed.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR)
What happens when a subcontractor's certified payroll is late
Federal rules give the agency real leverage. Under 29 CFR 5.5(a)(2), the agency may withhold from the prime's payments enough to cover unpaid wages owed by the prime or any subcontractor. If a contractor fails to submit required records, the agency may, after written notice, suspend further payments, advances or guarantees of funds until the violation stops. Failure to submit records on request can also be grounds for debarment, and falsifying a certification can lead to civil or criminal prosecution.
Because withholding hits the prime, most primes pass the pressure down. Subcontracts commonly let the prime hold a sub's progress payment until its payrolls are in and clean. Read the payment and compliance sections of your subcontract so you know exactly what a missing week will cost you. On state projects, add the state's own penalties, such as New York's $100 per day for filings more than 14 days late.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); New York State DOL, Electronic certified payroll FAQ
Week-by-week certified payroll calendar for a subcontractor
Here is a practical rhythm for a sub on a covered job. Due dates to the prime come from your subcontract; state dates come from the agency rules above.
| When | Subcontractor task | Who receives it |
|---|---|---|
| Two weeks before mobilizing | Get the wage determination, map classifications, collect apprentice and fringe documents, register on the state portal | Prime (startup packet) |
| Week 1, Monday to Saturday | Track daily hours by worker and classification | Internal |
| Following Monday | Close the week, run payroll, check rates and fringe | Internal |
| By the subcontract due date | Send payroll 1 with signed Statement of Compliance | Prime or upper-tier sub |
| Each following week | Repeat; send a no-work statement for gap weeks if the prime asks | Prime or upper-tier sub |
| Weekly (New Jersey) | File on NJ Wage Hub and give a hard copy to the public body | State and public body |
| At least every 30 days (New York) | File on the NYSDOL portal, including no-work weeks | State |
| At least monthly (California, Washington) | File on DIR eCPR or L&I PWIA | State |
| By the 15th of the next month (Illinois) | File the prior month on the IDOL portal | State |
| Final week | Mark the final payroll and confirm nothing is missing | Prime and state |
| 3 years after the prime contract work is done (5 in Illinois) | Keep payrolls and basic records | Internal |
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); California DIR, Frequently Asked Questions on Public Works; Washington RCW 39.12.120, Certified payroll records; New York State DOL, Electronic certified payroll FAQ; Illinois Prevailing Wage Act, 820 ILCS 130/5; NJDOL, Public works contractors must report certified payroll on NJ Wage Hub
Worked example: one subcontractor's first month on a federal job
Illustrative example. A drywall sub starts on a federally funded building on Monday, March 2, 2026. Payroll weeks end on Saturday. The wage determination in its subcontract (rates invented for this example) lists drywall hanger at $38.50 per hour plus $14.20 in fringe. The sub pays fringe in cash. It has one registered apprentice whose program sets 60 percent of the journeyworker rate and does not specify fringe, so the full fringe applies.
Week ending March 7: a journeyworker works 40 hours. Base pay is 40 x $38.50 = $1,540.00 and fringe is 40 x $14.20 = $568.00, so total pay is $2,108.00. The apprentice works 32 hours at 0.60 x $38.50 = $23.10, which is $739.20, plus 32 x $14.20 = $454.40 fringe, for $1,193.60. Payroll 1 goes to the prime with the signed statement.
Week ending March 14: a second journeyworker works 42 hours, and payroll 2 pays all 42 at straight time. Week ending March 21: the crew is off site waiting on framing, and the sub sends a no-work statement because the prime asked for one. Week ending March 28: the prime's reviewer spots the overtime error on payroll 2.
The fix: 2 overtime hours should have been paid at 1.5 x $38.50 = $57.75. The shortfall is 2 x ($57.75 minus $38.50) = 2 x $19.25 = $38.50. Fringe does not change, because it is owed per hour worked, not at time and a half. The sub pays the worker $38.50, sends a revised payroll 2 with a new signed statement, and sends payroll 4 on time. Its April pay application goes through without a hold.
| Week ending | Payroll | What happened | Status |
|---|---|---|---|
| March 7, 2026 | 1 | Journeyworker $2,108.00; apprentice $1,193.60 | Accepted |
| March 14, 2026 | 2 | 42 hours paid at straight time | Returned for correction |
| March 21, 2026 | 3 | No work; no-work statement sent | Accepted |
| March 28, 2026 | 4 and revised 2 | $38.50 back pay paid; revised payroll 2 sent | Accepted |
Subcontractor certified payroll requirements checklist
Run this before you send each week's payroll.
| Check | Done when |
|---|---|
| Correct project, payroll number and week ending | Matches the prime's tracker with no gaps |
| Every worker on site is listed | Daily reports and timecards reconcile to the payroll |
| Classifications match the work performed | Split lines for workers in two classifications |
| Rates meet the wage determination | Base and fringe checked line by line |
| Overtime paid on the basic rate | Hours over 40 at 1.5 times the basic hourly rate |
| Fringe credit supported | Plan documents on file; cash in lieu shown separately |
| Apprentices registered and within ratio | Registration evidence on file for each apprentice |
| No full Social Security numbers or addresses on the submitted copy | Identifier is a worker number or last four digits |
| Statement of Compliance signed | Handwritten or valid electronic signature |
| State filing made | Portal confirmation saved |
| Lower-tier payrolls collected | Every sub you hired has filed for the week |
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); U.S. Department of Labor, Form WH-347 page
How primes collect certified payroll from many subcontractors
A prime with 20 subs on a 40-week job is tracking up to 800 sub-weeks. The ones that cause trouble are the ones nobody noticed were missing. A workable system has four parts: a list of every employer expected on the job, including lower tiers; the expected reporting periods for each; a status for every employer and week (missing, received, under review, accepted, no work); and a named owner for each open item.
Set expectations in the subcontract: the due day, the format, how no-work weeks are reported, and what happens to payment when payrolls are late. Ask each sub to name one payroll contact. Where the state portal lets primes see their subs' filings, as Washington's PWIA does, use it to confirm the state side. Remember that receipt is not approval: a file that arrived still needs review against the wage determination before anyone treats it as complete.
Sources: 29 CFR 5.5, Contract provisions and related matters (eCFR); Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions
How Buildalytic helps
Buildalytic Certified Payroll lets a prime set up each project's employers and expected reporting periods, receive subcontractor payroll files against the right employer and week, and see which weeks are missing, which are received but awaiting review, and which are marked no work. Reminders and Brody-assisted follow-up go out for outstanding payrolls, and revised files stay with the original reporting period so reviewers can follow the history.
Your authorized team still reviews and certifies the records. A received or reviewed status in Buildalytic is not a government filing receipt or a guarantee of compliance. Certified payroll is separately scoped and quoted; confirm accepted formats and the final submission handoff with the Buildalytic team.
Common questions
Do lower-tier subcontractors have to submit certified payroll?
Yes. Federal labor standards clauses must flow down to every lower-tier subcontract, and each covered employer submits a weekly certified payroll for weeks it performs covered work. The prime is responsible for collecting all of them, so lower-tier payrolls usually travel up through the sub that hired them.
How do I submit certified payroll as a subcontractor?
Prepare a weekly payroll on WH-347 or an equivalent format, sign the Statement of Compliance, and send it to the prime or upper-tier sub by the date in your subcontract. If a state law applies, file separately on the state's portal, such as California DIR eCPR or Washington PWIA.
Do I need to file certified payroll for a week with no work?
Federally, payrolls are required for weeks with covered work, but many primes ask for a no-work statement to keep the sequence clean. States differ: California has a Statement of Non-Performance, Washington a No Work Performed Report, New York requires reporting no-work weeks, and Illinois requires nothing.
Is WH-347 required for subcontractors?
No. DOL says WH-347 is optional. You may use any format that contains all the required payroll information and is accompanied by a signed Statement of Compliance. Your prime or a state portal may require a specific format, so check before the first week.
Can the prime hold my payment for late certified payroll?
Often, yes, if your subcontract allows it. Under 29 CFR 5.5 the agency can suspend payments to the prime when required records are not submitted and withhold funds for unpaid wages, so primes commonly tie subcontractor payments to complete payrolls.
Should certified payroll include full Social Security numbers?
Not on the submitted copy. Federal rules require an individual identifying number, such as the last four digits, instead of full Social Security numbers and addresses on weekly transmittals. A prime may still ask for full details for its own records.
How long must subcontractors keep certified payroll records?
Under federal rules, at least 3 years after all work on the prime contract is completed. Some states require longer; Illinois requires 5 years from the last payment on the contract or subcontract.
Sources and editorial notes
- 29 CFR 5.5, Contract provisions and related matters (eCFR)
- U.S. Department of Labor, Form WH-347 page
- California DIR, Frequently Asked Questions on Public Works
- Washington RCW 39.12.120, Certified payroll records
- Washington L&I, Prevailing Wage Intent and Affidavit step-by-step instructions
- New York State DOL, Electronic certified payroll FAQ
- Illinois Prevailing Wage Act, 820 ILCS 130/5
- Illinois Department of Labor, Certified payroll FAQ
- NJDOL, Public works contractors must report certified payroll on NJ Wage Hub
Prepared with AI assistance. Reference date: 2026-11-18. Worked examples are illustrative and are not customer results. Product details can change; confirm the current scope and terms before rollout.
How we prepare and update field notesSee every missing payroll week before the pay app.
Bring one job's subcontractor list. See expected weeks, what's missing, what's awaiting review, and follow-up on the gaps.
Start with the call, text or record your team already handles. Review the expected outcome and the human handoff before choosing a rollout.
See payroll collection Explore the relevant capability