The short answer
To take a clash from report to closed RFI, run the clash test on the latest models and group the results, assign each group to the trade that has to move, and decide the fix in the coordination meeting. When the fix needs the design team, write an RFI with one question, the clash ID, the sheets and spec section, a proposed fix and the date you need the answer. Track who is ball-in-court, follow up before and after the due date, have the trade update its model, then rerun the test and close the clash and the RFI together. Buildalytic keeps the RFI log, and Brody, its AI agent, follows up with whoever owes the answer by call, text and email until it comes back, then records it and tells the field.
What to take away
- Group clashes before you assign them. One duct crossing ten beams is one problem, not ten.
- Assign every group to the trade that moves, with a due date, before the meeting.
- Most clashes are fixed between trades. Only design questions become RFIs.
- Link each RFI to its clash ID so the answer can be checked in the model.
- Close a clash only after the updated model passes a rerun and the answer has reached the field.
Before you start
You need the current model from each discipline, the clash rules the team agreed in the BIM execution plan, the RFI log and the coordination meeting schedule. Models need enough development to coordinate. BIMForum's LOD Specification says LOD 300 elements are not necessarily clash-free, and LOD 350 is the level meant for construction-level coordination, which usually needs trade knowledge.
Agree on one ID for each clash group and use it everywhere: in the clash tool, the meeting minutes and the RFI. That one number is what lets someone close the loop later.
Sources: BIMForum: Level of Development (LOD) Specification 2025, Part I
Step 1: Run the clash test and group the results
Load the latest models into your coordination tool and run the agreed tests: hard clashes where objects intersect, and clearance clashes where something sits inside a space that must stay open. In Autodesk Forma Model Coordination, clashes are detected automatically once multi-discipline models are uploaded. In Navisworks Manage, you run the tests in a combined model.
Then clean the list. Remove duplicates and contacts you expect, such as a pipe resting on its own hanger. Mark what is not an issue. Group the rest by the cause, so one duct run crossing a line of beams becomes one item. A long raw list hides the five problems that matter.
Sources: Autodesk Forma: Clash detection in Model Coordination (checked November 28, 2026); Autodesk: Model management with Autodesk Forma and Navisworks
Step 2: Assign each group by trade
Give every group one owner: the trade expected to move, with a due date. Lines that need slope, such as sanitary and storm, are hard to move, so smaller and more flexible runs usually give way. Follow the priority order in your BIM execution plan.
Forma lets you turn a clash into an issue and assign an owner by role or company, with a due date. Revizto ties each issue to its exact spot in the model. Whatever tool you use, the owner should see the item before the meeting, not in it.
Sources: Autodesk Forma: Clash detection in Model Coordination (checked November 28, 2026); Revizto (checked November 28, 2026)
Step 3: Decide in the coordination meeting
Walk the model area by area with the trades. For each group, record one of three outcomes: a trade fix with an owner and a date, not an issue with the reason, or a design question that needs an RFI.
Write the decision in the minutes as an action, with the clash ID, one owner, the outcome and a due date. A line that says MEP to coordinate is not an action. A line that says sheet metal lowers the 24 by 14 supply duct at grid C/4 to clear beam B-12 by Thursday is.
Step 4: Write the RFI for design questions
A clash needs an RFI when the fix changes what the design team drew: a ceiling height, a beam penetration, a rated wall, a slope, an equipment location. Trades can agree to move their own work. They cannot agree to change the design.
Write one question per RFI. Include these items.
- The clash ID and a screenshot or saved viewpoint from the model
- The sheets, details and spec section involved
- What conflicts, in one or two sentences
- A proposed fix from the trades, such as lowering the duct 4 inches
- The date you need the answer, tied to the work it holds up
- Who is ball-in-court: the architect, the structural engineer or the MEP engineer
Step 5: Track ball in court
Log the RFI with its number, the clash ID, the date sent, the person who owes the answer, the due date and the work it holds up. Keep the clash open in the coordination tool with the RFI number on it, so the two records point at each other.
Ball-in-court changes as the RFI moves. The engineer may send it back for more information, or ask the architect to weigh in. Update the log each time, so everyone can see who has it now.
| Field | Example |
|---|---|
| RFI number | RFI 047 |
| Clash ID | L2-MECH-STR-012 |
| Question | Can the supply duct at grid C/4 drop 4 inches below beam B-12? |
| Ball in court | Mechanical engineer |
| Needed by | Wednesday, before ceiling framing starts Thursday |
| Holds up | Level 2 ceiling framing, east wing |
| Model update owner | Sheet metal detailer |
Step 6: Follow up before and after the due date
Send a reminder before the RFI is due. If the date passes, call. Rank late items by the work they hold up, not only by age. A two-week-old RFI on a room that is months out matters less than a two-day-old RFI on a ceiling that closes Thursday.
Bring the open RFIs and late actions to the next coordination meeting, by owner. That is often the first time anyone sees that one engineer holds most of the open items.
Step 7: Update the model
When the answer comes back, send it to the trade that owns the model update and to the field. The trade updates its model and republishes it. If the answer changes the drawings, track the revision the design team issues.
Do not close the RFI on the reply alone. The answer is only useful once it is in the model the next clash run uses, and on the sheet the foreman builds from.
Step 8: Rerun and close
Rerun the clash test on the updated models. If the group clears, close the clash, record the RFI answer on it and close the RFI. If it moved the problem somewhere else, open a new group with a new ID and start again at step 2.
Keep the closed items. At turnover, the history of what moved and why, with the RFI behind each design change, answers questions that come up long after the coordination meetings end.
How Buildalytic handles steps 4 to 8
Clash detection stays in your BIM tools. Buildalytic picks up the follow-up. It keeps the RFI log and submittal register, or works with your log in Procore or Autodesk Forma (formerly Autodesk Construction Cloud). Brody, Buildalytic's AI agent, checks the current drawings, specs and past RFIs first, so a question already answered is not sent again. For a design question, he drafts a focused RFI with the sheet, detail and spec section cited for your PM to issue.
Brody follows up with whoever is ball-in-court before the due date and after it, by call, text and email, until the answer comes back. Late items are ranked by the work they hold up. When the response lands, he records it on the log, and the foreman who asked gets it by text. Coordination meeting minutes become an action log with one owner and a due date per action, and Brody follows up with each owner. Submittals are checked against their spec sections, and foremen can text a question and get the answer from the specs, drawings and RFIs with the source named.
Your PM issues every RFI, and the architect or engineer of record answers it. Design decisions stay with the design team.
Sources: Buildalytic: RFI software; Buildalytic: AI construction project management; Buildalytic: Submittal software; Buildalytic: Field answers by text
Common questions
What is BIM coordination?
BIM coordination is combining the models from each discipline, finding where they conflict, deciding who moves and getting design questions answered, so the work is resolved in the model before it is built.
Does every clash need an RFI?
No. Most clashes are fixed between trades in the coordination meeting. A clash needs an RFI when the fix changes the design, such as a ceiling height, a beam penetration or a rated wall.
Who writes the RFI for a clash?
Usually the general contractor's PM or project engineer issues it, with input from the trades on a proposed fix. The architect or engineer of record answers it.
What should a clash RFI include?
One question, the clash ID and a model screenshot or viewpoint, the sheets and spec section, a proposed fix, the date the answer is needed and the work it holds up.
When is a clash closed?
After the trade updates its model, the clash test is rerun and the group clears. Close the RFI at the same time, with the answer recorded on the clash.
How does Buildalytic help with clash follow-up?
Buildalytic keeps the RFI log. Brody drafts RFIs for your PM, follows up by call, text and email until each answer comes back, records it and sends it to the field. Meeting actions get an owner and a due date, and Brody follows up on each one.
Sources and editorial notes
- BIMForum: Level of Development (LOD) Specification 2025, Part I
- Autodesk Forma: Clash detection in Model Coordination (checked November 28, 2026)
- Autodesk: Model management with Autodesk Forma and Navisworks
- Revizto (checked November 28, 2026)
- Buildalytic: RFI software
- Buildalytic: AI construction project management
- Buildalytic: Submittal software
- Buildalytic: Field answers by text
Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.