The short answer
To build a submittal register from the spec book, start with the current specs and addenda, read the Division 01 submittal procedures, then go section by section and list every required submittal as its own row with its spec section, type, responsible sub and reviewer. Set each submit-by date backward from the date the field needs the material: subtract the lead time, the review period and one resubmittal cycle. Have your PM check the list against the book once, then keep it current as addenda and bulletins arrive. Procore, Autodesk Forma and Buildalytic can draft the register from the spec book for you to check.
What to take away
- Read Division 01 first. It sets review periods, numbering and format for every section.
- One row per required item, linked to its spec section and paragraph.
- Work backward from the field's need date, not forward from today.
- Budget one resubmittal cycle on long-lead items. It is cheaper than a late delivery.
- A tool can draft the register in minutes. A person still checks it against the book.
What a submittal register is for
A submittal register lists every product data sheet, shop drawing, sample, test report and closeout item the specs require, with who owes it, who reviews it and when it is due. It turns a spec book of hundreds of pages into a list your team can work every week.
A good register answers three questions at a glance: what is late, who holds it now, and which work it will hold up. Federal guide specifications go as far as attaching a submittal register to the submittal procedures section.
Step 1: Get the current spec book and addenda
Build from the conformed set: the issued specs with every addendum folded in. A register built from the bid set misses scope added in addenda and keeps items that were deleted. Note the date and addendum number you built from at the top of the register.
Step 2: Read Division 01 first
Division 01 sets the rules for every other section. In MasterFormat numbering, Section 01 33 00 Submittal Procedures usually states the review period, the numbering system, the transmittal format, how many copies or what electronic format, and how resubmittals are handled. Closeout submittals often sit in their own Division 01 sections.
Write down the review period the architect is allowed, for example 14 days, and any longer period for items that go to a consultant. You will need both in Step 6.
Sources: NYC: MasterFormat numbers and titles; WBDG: UFGS 01 33 00 Submittal Procedures
Step 3: Go section by section
Open each technical section and find the submittals article in Part 1. Most specs split it into action submittals, which need a review decision, and informational submittals, which are for the record. List both.
Then scan Parts 2 and 3. Mockups, field tests, manufacturer field reports, certifications and warranty forms are often required there without a mention in Part 1. These are the items registers miss most.
- Product data
- Shop drawings
- Samples and color selections
- Mockups
- Test reports and certifications
- Delegated design calculations
- Operation and maintenance data, warranties and other closeout items
Step 4: One row per required item
Give each item its own row. “Door hardware submittals” is not a row; the hardware schedule, the product data and the keying schedule are three rows with different reviewers and timing. Each row should carry the fields below.
- Spec section and paragraph
- Item description and submittal type
- Responsible subcontractor or supplier
- Reviewer: architect, engineer or consultant
- Review period from Division 01
- Lead time after approval
- Date needed on site, from the schedule
- Submit-by date and current ball in court
Step 5: Assign each row to a subcontractor
Match each row to the subcontract or purchase order that carries the scope. Where scope is split, such as fire caulking or access panels, name one owner. A row with no owner is a row nobody submits.
Step 6: Set dates backward from the need date
Take the date the field needs the material on site from the schedule. Subtract the lead time to get the approval date. Subtract the review period to get the first submit date. On long-lead items, subtract one more review period for a resubmittal.
The example below assumes a 14-day review period and one resubmittal cycle. The lead times are assumptions for illustration, not quotes.
| Spec section | Item | Needed on site | Lead time | Approval needed by | Submit by, with one resubmittal |
|---|---|---|---|---|---|
| 23 73 13 | Air handling units, product data and shop drawings | January 18, 2027 | 16 weeks | September 28, 2026 | August 31, 2026 |
| 08 71 00 | Door hardware schedule and product data | March 2, 2027 | 10 weeks | December 22, 2026 | November 24, 2026 |
| 09 91 23 | Interior paint product data and color samples | February 8, 2027 | 2 weeks | January 25, 2027 | December 28, 2026 |
Step 7: Check it and send it
Have your PM walk the register against the spec book once, section by section. Then send each sub its rows with the submit-by dates, and share the list with the architect so reviewers can plan for the busy weeks.
Step 8: Keep it current
A register is only useful if it changes with the job. Add rows when an addendum, bulletin or change adds scope. Update the need date when the schedule moves. Record each revise and resubmit comment, and send it to the sub the same day.
Rank late items by the work they hold up, not by how late they are. A late paint sample matters less than an air handler with a sixteen-week lead time.
Tools that draft the register from the spec book
Several tools now read the spec book and draft the register. Procore's submittal builder scans the spec book and generates a submittal log inside Procore. Autodesk's AutoSpecs analyzes the spec documents to build a submittal register in Forma Build and flags items that may be missing. Trunk Tools' TrunkRegister reads a whole spec book, builds the register and pushes it back to your project system.
Buildalytic builds the register from the spec book with one row per required item and its spec section, type and owner, and each row carries the date the field needs the material. Your PM reviews the list once before follow-up starts. Then Brody checks each submittal against its spec section and calls, texts and emails whoever is ball in court, writing the status to Buildalytic, Procore or Forma.
Whichever tool drafts it, use Steps 3 and 7 as the check. Items buried in Parts 2 and 3 are the ones to confirm by hand.
Sources: Procore: submittals (checked November 28, 2026); Autodesk: construction submittal software (checked November 28, 2026); Trunk Tools (checked November 28, 2026); Buildalytic: submittal software
Common questions
What goes in a submittal register?
Every submittal the specs require, one row each, with its spec section, type, responsible sub, reviewer, review period, lead time, the date the field needs the material and the submit-by date. Add the current ball in court once submittals start moving.
Where do I find the submittal requirements in the specs?
Start with Division 01, usually Section 01 33 00 Submittal Procedures, for the rules. Then read the submittals article in Part 1 of each technical section, and scan Parts 2 and 3 for mockups, tests and certifications.
How do I set submittal due dates?
Work backward from the date the material is needed on site. Subtract the lead time, then the review period, then one more review period on long-lead items to allow for a resubmittal.
Can software build the submittal register for me?
Yes. Procore's submittal builder, Autodesk's AutoSpecs in Forma Build, Trunk Tools' TrunkRegister and Buildalytic all draft the register from the spec book. Have your PM check the draft against the book before it goes to subs.
Who approves submittals?
The architect or engineer of record reviews and approves each submittal. Your team checks it against the spec first. Brody records the decision and tells the field and procurement.
Sources and editorial notes
- WBDG: UFGS 01 33 00 Submittal Procedures
- NYC: MasterFormat numbers and titles
- Procore: submittals (checked November 28, 2026)
- Autodesk: construction submittal software (checked November 28, 2026)
- Trunk Tools (checked November 28, 2026)
- Buildalytic: submittal software
Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.