A construction WIP report, built every month from your ERP and pay apps.
Buildalytic is WIP report software for contractors. Brody, its AI assistant, builds your work in progress schedule each month from job cost in your ERP and the pay apps you sent, flags over and under billing and fades, ties them to your 13-week cash forecast and hands the schedule to your accounting team to review.

This month’s WIP. Every job, every flag.
The October close on one screen: where each job stands against its billing, and what Brody did about it.
How to prepare a WIP scheduleOctober WIP review
3 open jobs · $8,630,000 contract value · 3 flags
- Riverside Medical OfficeJob 2207 · $1,320,000 earnedStatus: Needs action: Underbilled: CO 14 approved, not billedComplete: 55%Over or under: $84,000 under
Brody · added CO 14 to pay app 13 and moved the cash into the forecast
- Bayview LibraryJob 2315 · $2,452,800 earnedStatus: Waiting: Overbilled: cash held for work aheadComplete: 56%Over or under: $175,200 over
Brody · kept the cost to finish that work in the 13-week forecast
- Elm Street Fire StationJob 2402 · $1,110,000 earnedStatus: Needs action: Fade: estimated profit down $140,000Complete: 60%Over or under: $40,000 over
Brody · asked the PM what moved the cost to complete and sent the answer to the controller
A WIP report. Built before the close.
Brody gathers the cost, the billing and the PM’s estimate, does the math on every job and puts the exceptions in front of your controller.
- Builds
- The WIP schedule every month from job cost in your ERP and the pay apps you sent
- Measures
- Percent complete by cost, earned revenue and over or under billing on every open job
- Flags
- Over and under billing past your threshold, and fades in estimated profit since last month
- Hands off
- The schedule and the month-end accruals to your accounting team, then to your bonding agent
Three jobs. One WIP schedule.
A worked example at October 31. Percent complete is cost to date over estimated cost. Earned revenue is contract value times percent complete. Billed to date minus earned revenue is the over or under billing.
| Job | Contract value | Estimated cost | Cost to date | Percent complete | Earned revenue | Billed to date | Over or under billed |
|---|---|---|---|---|---|---|---|
| Riverside Medical OfficeJob 2207 | $2,400,000 | $2,000,000 | $1,100,000 | 55% | $1,320,000 | $1,236,000 | $84,000 under |
| Bayview LibraryJob 2315 | $4,380,000 | $3,900,000 | $2,184,000 | 56% | $2,452,800 | $2,628,000 | $175,200 over |
| Elm Street Fire StationJob 2402 | $1,850,000 | $1,720,000 | $1,032,000 | 60% | $1,110,000 | $1,150,000 | $40,000 over |
| All three jobsNet position | $8,630,000 | $7,620,000 | $4,316,000 | $4,882,800 | $5,014,000 | $131,200 over |
Billed to date is gross billing, retainage included. Contract value and estimated cost include approved change orders only.
Over or under. Worked line by line.
The same math on every job, every month, with the inputs named so your controller can trace each number.
Job 2207 · Riverside Medical Office
Work in progress · through October 31
- Contract value
- $2,400,000
- Estimated total cost
- $2,000,000
- Cost to date
- $1,100,000
- Percent complete on cost
- 55%
- Earned revenue
- $1,320,000
- Billed to date
- $1,236,000
- Underbilled
- $84,000
Brody · found CO 14, approved and unbilled, and added it to pay app 13
Billed against earned, on every job
$1,100,000 ÷ $2,000,000 is 55% complete. 55% of the $2,400,000 contract is $1,320,000 earned. The job has billed $1,236,000, so it is $84,000 underbilled: work done and paid for that nobody has billed yet.
- Underbilled is earned revenue above billed to date, an asset
- Overbilled is billed to date above earned revenue, a liability
- Each flag carries its reason, such as an unbilled change order
- Pending change orders stay out until they are approved
A fade. Caught the month it starts.
Estimated profit is compared with last month on every job. A drop is flagged with the PM’s explanation before the schedule goes out.
Job 2402 · Elm Street Fire Station
Estimated profit · September against October
- Contract value
- $1,850,000
- Estimated cost, September
- $1,580,000
- Estimated cost, October
- $1,720,000
- Estimated profit, September
- $270,000 (14.6%)
- Estimated profit, October
- $130,000 (7.0%)
- Fade
- $140,000
- Profit to date, September then October
- $135,000 then $78,000
Brody · asked the PM by text what changed and attached the answer for the controller
Why one bad month shows up as a loss
With the higher estimate, profit to date falls from $135,000 to $78,000. The job is still profitable, but October books a $57,000 loss on it. Catching the change the month it happens keeps it from landing all at once at closeout.
- Estimated cost changes explained by the PM, in writing
- Fades listed by job and by size for the WIP meeting
- Cost overruns tied to change orders that could be priced
One month-end close. From cutoff to the bonding agent.
The October WIP, from reading the ERP to the approved schedule in the surety’s inbox.
- Nov 1
Cutoff read
October cost to date, commitments and budget read from the ERP. Billed to date carried from each pay app sent.
- Nov 2
Accruals booked
Received-not-invoiced costs and delivered materials with no invoice booked as accruals for the accountant to review.
- Nov 3
Cost to complete asked
Each PM texted last month’s cost to complete and this month’s cost to date. Two replied by text, one by call.
- Nov 4
Schedule drafted
Percent complete, earned revenue and over or under billing calculated on every job. Three flags with their reasons.
- Nov 6
Controller approves
The controller reviews the schedule, the accruals and the over and under billing entry, and approves them.
- Nov 7
Sent and carried forward
The approved WIP goes to the bonding agent. CO 14 goes on pay app 13, and the 13-week forecast updates.
October WIP · all open jobs
Three jobs · through October 31
- Contract value
- $8,630,000
- Earned revenue
- $4,882,800
- Billed to date
- $5,014,000
- Overbilled
- $215,200
- Underbilled
- $84,000
- Net position
- $131,200 overbilled
Brody · sent the approved schedule to the bonding agent with the job cost backup
Billing position. In cash terms.
An underbilling is cash you have earned and not billed. An overbilling is cash you hold for work not yet done. Both go into the 13-week forecast.
Cash flow forecasting13-week forecast · from the October WIP
Updated November 7
- Riverside underbilling, on pay app 13
- $84,000
- Expected in
- Week 5, from the owner’s pay history
- Overbilled cash held for work ahead
- $215,200
- Cost to finish kept in the forecast
- Bayview Library and Elm Street
Brody · moved the $84,000 into week 5 and kept the overbilled cash against the cost to finish
One picture of the money
Buildalytic builds a rolling 13-week cash forecast from your live pay apps, retainage and payables. The WIP schedule feeds it: what to bill next, and what the cash you already hold still has to pay for.
- Underbillings put on the next pay app and timed by how that payer pays
- Overbillings kept against the cost to finish the work
- Cost against budget tracked by job between closes
Every input checked. Before the schedule goes out.
A WIP schedule is only as good as its cost to date, cost to complete and billed to date. Brody gets each one right first.
Approved change orders not billedCost to date, complete
Received-not-invoiced costs and delivered materials with no invoice yet are booked as accruals for your accountant to review.
Cost to complete, from the PM
Each PM gets a text with last month’s cost to complete and this month’s cost to date, and replies with the new estimate.
Change orders in the contract
Approved change orders are added to contract value and estimated cost. Pending ones are listed apart, so nobody earns revenue on them early.
Billed to date, from the pay apps
Gross billings with retainage, carried from each G702 you sent, so billed to date matches what the owner has.
Over and under billing flagged
Every job past your threshold is flagged with the reason: an unbilled change order, a stored-materials line or a front-loaded schedule of values.
Fades flagged
Estimated profit is compared with last month on every job. A drop goes to the controller with the PM’s explanation.
Four steps. From the ERP to the surety.
Your accounting team reviews and approves every schedule. Brody does the gathering, the math and the follow-up.
Connect the ERP
Job cost, commitments, budgets and billings read from Vista, Spectrum, Sage, Foundation, QuickBooks and the other accounting systems you run.
Gather the inputs
Accruals booked for review, cost to complete asked of each PM by text, change orders added.
Draft and flag
Percent complete, earned revenue and over or under billing on every job, with fades and their reasons.
Approve and send
Your controller approves it. Brody sends it to the bonding agent and carries the results into billing and cash.
WIP tools and Brody. Compared plainly.
Construction ERPs and finance tools calculate the WIP. Brody gathers what feeds it, flags what it shows and follows up with the people who own each number.
AI construction accounting software| Tool | What it is | WIP and over or under billing, per its site | Works with |
|---|---|---|---|
| Buildalytic | An AI teammate on top of your ERP | Brody builds the WIP schedule each month from ERP job cost and your pay apps, gets cost to complete from each PM by text, flags over and under billing and fades, and ties both to the 13-week cash forecast | Reads Vista, Spectrum, Sage, Foundation, QuickBooks and others; the general ledger stays in your ERP |
| Foundation | Construction accounting software | View and post over/under billing (WIP) and overhead, including change orders and WIP adjustments; WIP reports among its reports | Its own general ledger and job cost |
| Sage Intacct Construction | Cloud construction accounting | Automates the monthly WIP statement, creates over and under billing GL transactions and sends WIP statements electronically to bonding companies | Its own general ledger |
| Vista (Trimble Viewpoint) | Construction ERP | Monthly JC Work in Progress reports: earned revenue and over/under billing by contract | Its own job cost and general ledger |
| Spectrum (Trimble Viewpoint) | Construction ERP | Calculates over/under as the difference between earned and billed to date; shown on the Contract Status Report, also called the WIP, Bonding or Bank report | Its own job cost and general ledger |
| Knowify | Job management for trade contractors | A real-time WIP calculation on any project showing over or under billing, on the Advanced and Enterprise plans | QuickBooks Online; QuickBooks Desktop on Enterprise |
| Agave | AI platform for construction finance | AI Analytics lists live WIP and over/under-billing reports, with budget against actuals pulled live from your ERP and cost to complete forecasts | Procore, Autodesk Build and 13+ construction ERPs |
| Adaptive | AI agents for construction finance | A WIP and Forecasting Analyst that keeps WIP live and builds revenue, margin and cash forecasts; its AI never auto-posts to the GL | Sage, QuickBooks and Foundation |
| Deltek ComputerEase | Construction accounting software | Specialized work-in-progress reporting for every job | Its own accounting |
Vendor details from each vendor’s own website or help pages, checked November 28, 2026. Confirm current features with each vendor.
When another tool fits. And where Brody works beside it.
A fair read on who should pick what. Most contractors keep their ERP’s WIP report and add Brody for the inputs and the follow-up.
Your ERP already prints the WIP
Vista, Spectrum, Foundation and Sage Intacct Construction each produce a WIP or over and under billing report. Keep it. Brody gathers the cost to complete and the accruals behind it, and follows up on what it flags.
You want WIP inside job management
Knowify shows a real-time WIP calculation on its Advanced and Enterprise plans, with QuickBooks Online. It fits trade contractors who run jobs, billing and job cost in one tool.
You want finance agents in one app
Adaptive offers a WIP and Forecasting Analyst, and Agave lists live WIP reports across Procore and many ERPs. Choose Brody when the missing numbers sit with PMs and supers who need a text or a call.
Related workflows. The rest of the finance cycle.
Common questions. Answered plainly.
Something else? Ask the team
What is a WIP report in construction?
A work in progress report, or WIP schedule, shows every open job’s contract value, estimated total cost, cost to date, percent complete, earned revenue, billed to date and the over or under billing between them. Contractors prepare it every month to recognize revenue on the percentage of completion, to spot problem jobs and to send to their bonding agent and bank. Buildalytic prepares it each month from your ERP and pay apps for your accounting team to review.
How do you calculate over and under billing?
Divide cost to date by estimated total cost to get percent complete. Multiply contract value by percent complete to get earned revenue. Subtract earned revenue from billed to date. A positive result is an overbilling, a liability. A negative result is an underbilling, an asset. On Riverside Medical Office, $1,100,000 of $2,000,000 is 55% complete, earned revenue is $1,320,000 and billed to date is $1,236,000, so the job is $84,000 underbilled.
What does Brody do each month to build the WIP schedule?
He reads cost to date, commitments and budget by job from your ERP and billed to date from the pay apps you sent. He books the month-end accruals for review, asks each PM for cost to complete by text, adds approved change orders and calculates percent complete, earned revenue and over or under billing. Then he flags the jobs that need a look and sends the draft to your accounting team. He works with Vista, Spectrum, Sage, Foundation, QuickBooks and the other accounting systems you run.
Where does the cost to complete come from?
From your project managers. Brody texts each PM with last month’s cost to complete, this month’s cost to date and open commitments, and asks for the new estimate. A PM who is late gets a reminder, then a call. The answer goes on the schedule with the PM’s note, so the controller sees why a number moved.
What is a fade, and how does Brody flag it?
A fade is a drop in a job’s estimated profit from one month to the next, usually because the estimated cost went up. Brody compares estimated profit with last month on every job. On Elm Street Fire Station, estimated cost rose from $1,580,000 to $1,720,000, so estimated profit fell from $270,000 to $130,000. He flags the $140,000 fade, asks the PM what changed and puts the answer in front of the controller.
How does the WIP report tie to the 13-week cash forecast?
An underbilling is cash you have earned and not billed. When it goes on the next pay app, the forecast shows it in the week that owner or GC usually pays. An overbilling is cash you already hold for work not yet done, so the forecast keeps the cost to finish that work. Both sit in the rolling 13-week forecast Buildalytic builds from live pay apps, retainage and payables.
Who approves the WIP schedule and the entries?
Your accounting team. The controller reviews the schedule, the month-end accruals Brody booked and the over and under billing entry, and approves them. The general ledger stays in your ERP. Your CPA sets your revenue recognition method, and the guides on this site are general information, not tax or accounting advice.
Can Brody send the WIP schedule to our bonding agent?
Yes. Once your controller approves the schedule, Brody sends it to your bonding agent with the job cost backup, on the schedule your surety asks for. Questions that come back go to the controller with the job they are about.
Our ERP already has a WIP report. Why add Brody?
Keep the report. A WIP report is only as good as its inputs: a complete cost to date, a current cost to complete from every PM and billed to date that matches the pay apps. Brody gathers those inputs before the close, follows up with whoever is late and acts on what the schedule shows, such as an approved change order nobody billed.
How is it priced and how do we start?
From $25 per office user per month, billed annually. Crews and subs are free. No setup fee. Money moves through your own bank and ERP. Buildalytic is not a lender or a payment processor. Start with a demo on last month’s WIP, then go live on one real close.
Bring last month’s WIP.
Share a job cost report and last month’s schedule. See Brody build this month’s WIP, flag the over and under billing and fades, and hand it to your accounting team. Start with a demo on your own work, then go live on one real close.