Construction contract notice deadlines: changes, delays, site conditions and claims

Common notice clauses in construction contracts, with the windows AIA A201-2017, ConsensusDocs 200 and federal FAR clauses set, and how to track and send each notice. Not legal advice.

By Buildalytic editorial team8 min read

A project administrator compares a drawing reference with a separate correspondence sheet in a site office.
On this page12 sections

The short answer

Most construction contracts require written notice within a set time after a change, a delay, a differing site condition or a claim, or the right to more time or money can be lost. Published summaries of AIA A201-2017 describe 21 days to give notice of a claim and 14 days for concealed or unknown conditions. ConsensusDocs 200 section 8.4 asks for notice within 14 days and supporting documentation within 21 days after that. Federal FAR clauses require differing site conditions notice before the conditions are disturbed, and 30 days to assert a change order adjustment. Subcontracts often set shorter windows. Track each window from the day the field reports the event, collect the backup, and send the notice by the method the contract requires. This guide is not legal advice; read your own contract and ask your counsel.

What to take away

  • Notice clauses decide whether a valid change, delay or claim gets paid. Find them before the job starts.
  • Your subcontract may set a shorter window than the prime contract. Track the shorter one.
  • The clock usually starts with the event or when you first recognize it, not when the PM hears about it.
  • Send each notice by the method the contract names, and keep proof of delivery.
  • This guide is not legal advice. Your contract and your counsel decide.

Why notice clauses matter

A notice clause tells you how long you have to put the other party on written notice after something happens. Miss the window and the contract may treat the claim as waived, even when the work was real and the cost is clear.

Notice protects both sides. It lets the owner or GC see the problem while it can still be checked, priced or avoided. That is why many clauses start the clock at the event, not at the end of the month when the paperwork catches up.

This guide summarizes common windows from published summaries of standard forms. Standard forms are often edited, and subcontracts often shorten the windows. Read the contract you signed, and ask your counsel what it means for your job. Nothing here is legal advice.

Common notice windows at a glance

The table below shows typical windows from published summaries of AIA A201-2017, ConsensusDocs 200 and two federal FAR clauses. Section numbers are from those summaries. Your edition, edits and subcontract may differ.

Common notice windows at a glance
Notice typeAIA A201-2017ConsensusDocs 200Federal (FAR)What to track
Changes and extra workMinor changes (§7.4): tell the architect before proceeding if cost or time is affected; otherwise any adjustment is waived§8.4: written notice within 14 days after the event or after you first recognize it, whichever is later52.243-4(e): assert the adjustment within 30 days after receiving a written change order; agencies may vary the periodDate of the direction, who gave it, photos, hours and quantities
Delays and timeClaims for Contract Time follow the same notice of claim rules as any other claim (§15.1)§6.3.1 defines excusable delays; claims for more time follow §8.4Varies by clause; check the contractStart of the delay, cause, activities affected and the lookahead
Differing or concealed site conditions§3.7.4: notice within 14 days after first observing the condition, cut from 21 days in 2007§3.16.2 is the differing site conditions clause; give notice as soon as the condition is found and before a notice of claim52.236-2: written notice before the conditions are disturbedLocation, photos before disturbance and the drawing or report it differs from
Claims§15.1.3.1: notice of claim within 21 days; notices of claim go by certified or registered mail or courier§8.4: notice within 14 days, supporting documentation within 21 days after notice; the owner responds within 14 days after receiptSee the clause the claim arises underThe claim amount, backup and proof of delivery

Sources: National Law Review: Notice requirements under the revised A201 general conditions (October 2, 2017; checked November 28, 2026); Amundsen Davis: Notice requirements under the revised A201-2017 (August 15, 2017; checked November 28, 2026); ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026); ConsensusDocs 200 Guidebook, 2016 edition (checked November 28, 2026); FAR 52.236-2 Differing Site Conditions (checked November 28, 2026); FAR 52.243-4 Changes (checked November 28, 2026)

Changes and extra work

Extra work is where most notices are lost. A superintendent asks the crew to add a few feet of forming, the foreman does it, and nobody writes it down until the pay application. By then the window may be closed.

Under ConsensusDocs 200, published summaries describe written notice within 14 days after the event or after you first recognize it, whichever is later, with documentation within 21 days after notice. Under the federal changes clause, the contractor asserts its right to an adjustment within 30 days after receiving a written change order, and an agency may vary that period. A201-2017 asks you to notify the architect before proceeding with a minor change that affects cost or time.

Many subcontracts shorten these windows to a few days. Track the window in the contract you signed, not the one above it.

Sources: ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026); FAR 52.243-4 Changes (checked November 28, 2026); Amundsen Davis: Notice requirements under the revised A201-2017 (August 15, 2017; checked November 28, 2026)

Delays and time extensions

A delay notice tells the other side that work is slipping and why. The 2017 A201 brought claims for Contract Time under the same notice of claim rules as any other claim, so the 21-day claim window applies. ConsensusDocs 200 defines excusable delays in §6.3.1, and claims for more time follow §8.4.

Delay notices are easier to support when the schedule is current. Record the start of the delay, the cause, the activities it holds up and what the lookahead now shows.

Sources: Amundsen Davis: Notice requirements under the revised A201-2017 (August 15, 2017; checked November 28, 2026); ConsensusDocs 200 Guidebook, 2016 edition (checked November 28, 2026); ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026)

Differing and concealed site conditions

When the ground, an existing wall or a buried line is not what the documents showed, notice is usually due fast and before the condition is disturbed. A201-2017 §3.7.4 sets 14 days after first observing the condition, shortened from 21 days in the prior edition. The federal clause, FAR 52.236-2, requires written notice before the conditions are disturbed, and the contracting officer may extend the time.

ConsensusDocs 200 §3.16.2 is its differing site conditions clause. A ConsensusDocs article advises giving notice as soon as the condition is found, before any notice of claim. Check your form for the exact wording.

Photos taken before anything is moved are the most useful backup. Ask the crew to stop, photograph and call before they dig further.

Sources: National Law Review: Notice requirements under the revised A201 general conditions (October 2, 2017; checked November 28, 2026); FAR 52.236-2 Differing Site Conditions (checked November 28, 2026); ConsensusDocs 200 Guidebook, 2016 edition (checked November 28, 2026); ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026)

Claims

A claim is a formal demand for money, time or another change in the contract terms. Published summaries of A201-2017 describe a notice of claim within 21 days under §15.1.3.1, and note that a notice of claim must go by certified or registered mail, or by courier. Email may not be enough for a claim even when it is fine for other notices.

Under ConsensusDocs 200 §8.4, notice is due within 14 days and supporting documentation within 21 days after notice, unless the parties agree to more time. The owner responds within 14 days after receiving the claim.

Sources: National Law Review: Notice requirements under the revised A201 general conditions (October 2, 2017; checked November 28, 2026); Amundsen Davis: Notice requirements under the revised A201-2017 (August 15, 2017; checked November 28, 2026); ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026)

How to track notice deadlines

Build the notice list before the job starts. Read the prime contract and your subcontract, list each notice clause with its section, window, trigger and required delivery method, and note where the subcontract is shorter.

Then start the clock from the field. The trigger is the event, so the date has to come from the foreman or superintendent who saw it.

  • List every notice clause with its section, window and delivery method.
  • Use the shorter window when the subcontract and prime contract differ.
  • Log the event date from the field the same day.
  • Count the deadline from the trigger the clause names.
  • Remind the PM well before the window closes, not on the last day.
  • Keep the backup with the notice: photos, hours, quantities and schedule.

How to send a notice

A notice should name the contract section, describe the event and its date, say what you expect it to affect, and say that cost and time are still being assessed if they are. It does not need the final price.

Send it to the person and address the contract names, by the method it names. Keep proof of delivery: the certified mail receipt, the courier record or the email the contract allows. Then follow up until you have a response, and log it.

A short, timely notice that preserves your rights is usually better than a complete claim that arrives late. Your counsel can tell you what your contract requires.

How Buildalytic tracks notice deadlines

Buildalytic's Brody reads the contracts you connect and flags risky clauses, obligations and notice deadlines, naming the page and clause behind each one. He compares obligations and flow-downs with your scope, insurance and schedule assumptions, then routes the judgment to a qualified reviewer before you commit.

On the job, the change order notice window from your subcontract is tracked from the first text. When a foreman calls or texts about extra work, a delay or a site condition, Brody records the date, collects photos, hours and quantities by call and text, and reminds your PM before the window closes. Your PM or reviewer approves and sends each notice. Brody says he is an AI assistant on every call, and your team approves every decision.

Sources: Buildalytic: AI contract review software for contractors; Buildalytic: extra work documentation; Buildalytic: construction workflows

Common questions

What is a notice deadline in a construction contract?

It is the time the contract gives you to send written notice after an event such as a change, a delay, a differing site condition or a claim. Missing it can waive your right to more time or money. Read your own contract for the exact window.

How many days do you have to give notice of a claim under AIA A201-2017?

Published summaries describe 21 days for a notice of claim under §15.1.3.1, delivered by certified or registered mail or courier. Your contract may edit this, so read the signed version.

What is the notice period for concealed conditions under A201-2017?

Section 3.7.4 sets 14 days after first observing the condition, shortened from 21 days in the 2007 edition, according to published summaries.

What does ConsensusDocs 200 require for claims?

Section 8.4 calls for written notice within 14 days after the event or after you first recognize it, whichever is later, and supporting documentation within 21 days after notice, unless the parties agree to more time.

Can a subcontract have shorter notice windows than the prime contract?

Yes, and many do. A sub often needs time to notify the GC before the GC's own window to the owner closes. Track the window in the contract you signed.

Is this legal advice?

No. This guide summarizes published descriptions of standard forms. Your contract and your counsel decide what applies to your job.

Sources and editorial notes

  1. National Law Review: Notice requirements under the revised A201 general conditions (October 2, 2017; checked November 28, 2026)
  2. Amundsen Davis: Notice requirements under the revised A201-2017 (August 15, 2017; checked November 28, 2026)
  3. ConsensusDocs: You are on notice, by Peckar and Abramson (August 6, 2022; checked November 28, 2026)
  4. ConsensusDocs 200 Guidebook, 2016 edition (checked November 28, 2026)
  5. FAR 52.236-2 Differing Site Conditions (checked November 28, 2026)
  6. FAR 52.243-4 Changes (checked November 28, 2026)
  7. Buildalytic: AI contract review software for contractors
  8. Buildalytic: extra work documentation
  9. Buildalytic: construction workflows

Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.