The short answer
A construction WIP schedule, or work in progress report, lists every open job with its contract value, estimated total cost, cost to date, percent complete, earned revenue, billed to date and over or under billing. To prepare it, close the month's job cost and get a current cost to complete from each project manager. Divide cost to date by estimated total cost for percent complete, multiply contract value by percent complete for earned revenue, then subtract earned revenue from billed to date. A positive result is an overbilling, a liability. A negative result is an underbilling, an asset. Compare each job's estimated profit with last month to catch fades, then have the controller review the schedule and book the over and under billing entry before it goes to your bonding agent and bank.
What to take away
- Percent complete on the cost-to-cost method is cost to date divided by estimated total cost.
- Earned revenue is contract value times percent complete.
- Over or under billing is billed to date minus earned revenue. Positive is overbilled; negative is underbilled.
- Cost to date must include accruals, and cost to complete must come from the PM this month.
- Compare estimated profit with last month on every job to catch fades early.
- Your CPA sets the revenue recognition method. This guide is general information, not accounting advice.
What a WIP schedule is and who reads it
A WIP schedule, also called a work in progress report, shows every open job at a month end. For each job it shows what the contract is worth, what the job is expected to cost, what it has cost so far, how far along it is, how much revenue that progress has earned, how much has been billed and the gap between the last two. Foundation's field guide lists the same key elements: contract amount, estimated costs, costs to date, percent complete, billed revenue, earned revenue and over or under billings.
Contractors that recognize revenue on the percentage of completion use it to set revenue for the period. Managers use it to find problem jobs while there is still time to act. Sureties and banks read it too. Foundation calls the over and under billing report a requirement of surety companies, and recommends running it monthly rather than only at year end, so trends show up.
Construction ERPs produce it from job cost. Vista lists monthly JC Work in Progress reports of earned revenue and over or under billing by contract. Spectrum shows over and under billed dollars on its Contract Status Report, which it also calls the WIP, Bonding or Bank report. Sage Intacct Construction automates the monthly WIP statement. Each report is only as good as its inputs, which is what most of this guide is about.
Sources: Foundation Software: the field guide to construction WIP reports (checked November 28, 2026); Foundation Software: over/under billing and bonding reports (checked November 28, 2026); Trimble Help: Vista job cost general reports (checked November 28, 2026); Trimble Help: Spectrum over/under billed dollars (checked November 28, 2026); Sage: Sage Intacct Construction WIP reporting (published August 27, 2024; checked November 28, 2026)
Before you start: what you need on your desk
Close job cost for the month first. A WIP schedule built on an open month will move after you send it.
- Job cost report through the period end, by job, with cost to date and open commitments
- Contract values with every approved change order, and a separate list of pending change orders
- Billed to date from each pay application sent, with retainage included
- A current estimate of cost to complete from each project manager
- The accrual list: received-not-invoiced costs, delivered materials with no invoice and unrecorded labor
- Last month's WIP schedule, to compare estimated profit job by job
Every column, in order
Formats vary by company, but most schedules carry these columns. The letters match the worked example below.
| Column | Label | How to get it |
|---|---|---|
| A | Contract value | Original contract plus approved change orders |
| B | Estimated total cost | Cost to date plus the PM's estimated cost to complete |
| C | Estimated gross profit | A minus B |
| D | Cost to date | Job cost through the period end, accruals included |
| E | Percent complete | D divided by B (the cost-to-cost method) |
| F | Earned revenue | A times E |
| G | Billed to date | Total billed on pay applications through the period end, retainage included |
| H | Overbilled | G minus F, when G is larger |
| I | Underbilled | F minus G, when F is larger |
| J | Cost to complete | B minus D |
| K | Gross profit to date | F minus D |
A worked example: three jobs at October 31
Three open jobs for one general contractor at October 31. The figures are an example, not a real company's jobs. Contract value and estimated cost include approved change orders only.
| Column | Job 2207 Riverside Medical Office | Job 2315 Bayview Library | Job 2402 Elm Street Fire Station |
|---|---|---|---|
| A Contract value | $2,400,000 | $4,380,000 | $1,850,000 |
| B Estimated total cost | $2,000,000 | $3,900,000 | $1,720,000 |
| C Estimated gross profit | $400,000 (16.7%) | $480,000 (11.0%) | $130,000 (7.0%) |
| D Cost to date | $1,100,000 | $2,184,000 | $1,032,000 |
| E Percent complete | 55% | 56% | 60% |
| F Earned revenue | $1,320,000 | $2,452,800 | $1,110,000 |
| G Billed to date | $1,236,000 | $2,628,000 | $1,150,000 |
| H Overbilled | $0 | $175,200 | $40,000 |
| I Underbilled | $84,000 | $0 | $0 |
| J Cost to complete | $900,000 | $1,716,000 | $688,000 |
| K Gross profit to date | $220,000 | $268,800 | $78,000 |
How the worked numbers add up
Riverside Medical Office: $1,100,000 of cost against an estimated $2,000,000 is 55 percent complete. 55 percent of the $2,400,000 contract is $1,320,000 earned. The owner has been billed $1,236,000, so the job is $84,000 underbilled. In this example the gap is change order 14, approved but not yet billed. It belongs on the next pay application.
Bayview Library: $2,184,000 against $3,900,000 is 56 percent complete, so earned revenue is 56 percent of $4,380,000, or $2,452,800. Billed to date is $2,628,000, so the job is $175,200 overbilled. Some overbilling is normal on a job that bills mobilization and general conditions early, but that cash still has to pay for work not yet done.
Elm Street Fire Station: $1,032,000 against $1,720,000 is 60 percent complete, so earned revenue is $1,110,000. Billed to date is $1,150,000, so the job is $40,000 overbilled. The bigger message on this job is the fade in the next section.
All three together: earned revenue is $4,882,800 and billed to date is $5,014,000. Overbillings total $215,200 and underbillings $84,000, a net overbilling of $131,200. Report the two separately, because a net figure hides the underbilled job. Check each job: gross profit to date (K) equals estimated gross profit (C) times percent complete (E), for example $400,000 times 55 percent is $220,000.
Over and under billing, explained
An underbilling means you have earned more than you have billed. It sits on the balance sheet as an asset, often called costs and estimated earnings in excess of billings. Foundation's bonding article warns that underbilling can lead to serious cash flow problems and says to find out why the cost has not been billed. Common reasons are approved change orders not yet on a pay app, stored materials waiting on backup and progress the field reported that billing missed.
An overbilling means you have billed more than you have earned. It is a liability, often called billings in excess of costs and estimated earnings. It can be healthy, since you are working on the owner's money, but Foundation and Knowify both warn about job borrowing: using one job's overbilled cash to fund another. Trimble's Spectrum help uses the account names Costs in Excess of Billings, an asset, and Billings in Excess of Costs, a liability, for the two balances.
Sources: Foundation Software: over/under billing and bonding reports (checked November 28, 2026); Knowify: what is WIP and how is it calculated (checked November 28, 2026); Trimble Help: Spectrum work-in-progress billings over/under cost (checked November 28, 2026)
Fades: compare this month with last month
A fade is a drop in a job's estimated gross profit from one schedule to the next. Put last month's estimated profit beside this month's on every job, and ask the PM about every drop.
In September, Elm Street Fire Station carried an estimated cost of $1,580,000 and an estimated profit of $270,000, 14.6 percent of the contract. Cost to date was $790,000, so the job was 50 percent complete, with $925,000 earned and $135,000 of profit to date. In October the PM raised the estimated cost to $1,720,000. Estimated profit fell to $130,000, a $140,000 fade.
On the percentage of completion, the change flows through in the month it is made. Profit to date drops from $135,000 to $78,000, so October books a $57,000 loss on a job that is still profitable overall. October revenue is $185,000 ($1,110,000 minus $925,000) against $242,000 of October cost ($1,032,000 minus $790,000). Catching a fade the month it starts gives the PM time to price a change order or recover cost, instead of a large write-down at closeout.
Get cost to date right: accruals and cutoff
On the cost-to-cost method, cost to date drives percent complete. A missing cost understates percent complete and earned revenue, and makes a job look more overbilled than it is. Before you run the schedule, accrue the costs that belong to the month: material delivered with no invoice yet, subcontractor work billed late, equipment rentals and labor for the last payroll period.
The opposite error matters too. Material delivered and paid for but not installed can push percent complete ahead of the work. Many contractors leave uninstalled material out of cost to date for the WIP, or adjust for it, based on their accountant's guidance.
Cost to complete: the number that moves everything
Estimated total cost is cost to date plus the PM's estimate of cost to complete. It sets both percent complete and estimated profit, so it has to be current every month. Foundation's field guide describes the split: project managers supply the cost to complete, and accounting supplies costs and billings to date.
Ask each PM for cost to complete against the job cost report, with last month's figure beside it. A cost to complete that has not changed in three months on an active job is a question, not an answer. An estimate that is too low overstates percent complete and earned revenue, hides a fade and can make an overbilled job look underbilled.
Sources: Foundation Software: the field guide to construction WIP reports (checked November 28, 2026)
The month-end entry
The schedule's over and under billing totals are booked to the balance sheet at month end. One entry brings the underbilling asset to the schedule's total. The other brings the overbilling liability to its total. Both offset to contract revenue. Trimble's Spectrum help describes the same two adjustments against a Net Over / Under Billings revenue account.
In the example, the underbilling asset is $84,000 and the overbilling liability is $215,200. If last month's balances were different, the entry books only the change. Sage Intacct Construction creates the over and under billing GL transactions from its WIP feature; in other systems your accountant books them. Your CPA sets the method, and this guide is general information, not tax or accounting advice.
Sources: Trimble Help: Spectrum work-in-progress billings over/under cost (checked November 28, 2026); Sage: Sage Intacct Construction WIP reporting (published August 27, 2024; checked November 28, 2026)
What your bonding agent and bank look for
Sureties and banks read the WIP schedule to see whether jobs earn what they were bid at, whether billing keeps pace with the work and whether cash from one job is funding another. Foundation's bonding article says the report is one piece of the bonding criteria, and that bond producers above all want to see a well-managed, profitable company.
Send it on the schedule your surety asks for, monthly or quarterly, and in the same format each time. Explain large underbillings and every fade before they ask: the change order behind the gap, the date it will be billed and what the PM is doing about the cost.
Sources: Foundation Software: over/under billing and bonding reports (checked November 28, 2026)
From the WIP schedule to the cash forecast
The WIP schedule is a billing and cash document as much as an accounting one. Each underbilling is cash you can bill on the next pay application. Each overbilling is cash you already hold that has to pay for the remaining work. Put both into your 13-week cash forecast: underbillings in the week each payer usually pays, overbillings against the cost to finish.
Retainage is part of billed to date on the WIP schedule but arrives much later as cash. Keep retainage held and its expected release date as separate lines in the forecast.
A checklist before the controller signs
Run these checks every month before the schedule leaves accounting.
| Check | Why it matters |
|---|---|
| Job cost closed through the period end | An open month moves the schedule after you send it |
| Accruals booked for received-not-invoiced cost | Missing cost understates percent complete |
| Cost to complete updated by every PM this month | A stale estimate hides fades |
| Contract value includes approved change orders only | Pending changes would overstate earned revenue |
| Billed to date ties to the pay applications sent | The owner's number and yours have to agree |
| Overbillings and underbillings listed separately | A net figure hides problem jobs |
| Every fade explained in writing | Your surety and bank will ask |
| Totals tie to the month-end entry | The schedule and the general ledger have to agree |
Mistakes that distort the WIP schedule
The common ones: using billed percent instead of cost percent, so every job shows no over or under billing at all; carrying last quarter's cost to complete; counting pending change orders in contract value; leaving out accruals; netting overbillings against underbillings; and treating uninstalled material as progress.
Another is rebuilding the schedule each month in a spreadsheet keyed from the ERP. Formulas drift and a pasted column lands on the wrong job. Pull cost and billing from the system of record, and keep last month's schedule beside this month's.
How Buildalytic prepares it each month
Buildalytic builds the WIP schedule every month from job cost in your ERP and the pay apps you sent. Brody, its AI assistant, books the month-end accruals for your accounting team to review, asks each PM for cost to complete by text, adds approved change orders and calculates percent complete, earned revenue and over or under billing on every job. He flags the jobs past your threshold and every fade, with the reason.
Underbillings go onto the next pay app and into the rolling 13-week cash forecast Buildalytic builds from live pay apps, retainage and payables. After your controller approves the schedule, Brody sends it to your bonding agent. Your accounting team reviews and approves every schedule and entry, and the general ledger stays in your ERP.
Sources: Buildalytic: WIP report; Buildalytic: 13-week cash flow forecasting; Buildalytic: AI construction accounting software
Common questions
What is a WIP schedule in construction?
A WIP schedule, or work in progress report, lists every open job with its contract value, estimated total cost, cost to date, percent complete, earned revenue, billed to date and over or under billing. Contractors prepare it monthly to recognize revenue on the percentage of completion, to find problem jobs and to send to their surety and bank.
How do you calculate over and under billing?
Divide cost to date by estimated total cost for percent complete. Multiply contract value by percent complete for earned revenue. Subtract earned revenue from billed to date. A positive result is an overbilling and a negative result is an underbilling. A job 55 percent complete on a $2,400,000 contract has earned $1,320,000; if it has billed $1,236,000, it is $84,000 underbilled.
Is overbilling good or bad?
Some overbilling is normal and helps cash, because you are working on the owner's money. It becomes a problem when the cash is spent on other jobs or overhead, since the work it was billed for still has to be paid for. Large or growing overbillings are worth explaining to your surety before they ask.
What is a profit fade?
A fade is a drop in a job's estimated gross profit from one WIP schedule to the next, usually because the estimated cost went up. On the percentage of completion the change flows through in the month it is made, so one month can show a loss on a job that is still profitable overall.
Which percent complete method should a WIP schedule use?
Most contractors use cost to cost: cost to date divided by estimated total cost. Some use units installed or a physical estimate on certain jobs. Your CPA sets the method for your financial statements. Use the same method every month so the schedule compares.
How often should you prepare a WIP schedule?
Monthly, after job cost closes. Foundation recommends running the over and under billing report regularly, such as monthly, rather than only at year end, so trends show up while there is time to act. Send it to your surety on the schedule it asks for.
Do you include retainage in billed to date?
Yes. Billed to date is the gross amount billed on your pay applications, retainage included. Retainage is billed and earned but held by the owner, so track it as its own receivable and forecast its release date separately in your cash forecast.
Can software prepare the WIP schedule?
Yes. Vista, Spectrum, Foundation and Sage Intacct Construction produce WIP or over and under billing reports from job cost. Buildalytic builds the WIP schedule each month from your ERP and pay apps, books the accruals for review, asks each PM for cost to complete by text, flags over and under billing and fades, and hands the schedule to your accounting team. The general ledger stays in your ERP.
Sources and editorial notes
- Foundation Software: the field guide to construction WIP reports (checked November 28, 2026)
- Foundation Software: over/under billing and bonding reports (checked November 28, 2026)
- Trimble Help: Vista job cost general reports (checked November 28, 2026)
- Trimble Help: Spectrum over/under billed dollars (checked November 28, 2026)
- Trimble Help: Spectrum work-in-progress billings over/under cost (checked November 28, 2026)
- Sage: Sage Intacct Construction WIP reporting (published August 27, 2024; checked November 28, 2026)
- Knowify: what is WIP and how is it calculated (checked November 28, 2026)
- Buildalytic: WIP report
- Buildalytic: 13-week cash flow forecasting
- Buildalytic: AI construction accounting software
Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.



