Prompt payment interest calculator.
Interest on a late pay app from the amount, days late and the annual or monthly rate, with state presets.
Change any number. The result updates.
No sign-up. What you type stays in your browser.
Your numbers
Result
Simple interest, not compounded. A monthly rate is counted as 12 times itself a year. Presets are the fixed rates in our prompt payment laws guide, checked November 28, 2026; states with a floating rate or a rule we could not verify have no preset. Statutes differ on when interest starts, whether it compounds, caps, notice steps and disputed amounts. Not legal advice: read the statute or ask your attorney before you put a number on a demand.
How it works. The rules behind the numbers.
Amount, days and rate
Interest is the late amount times the rate times the time late. A monthly rate such as 1% a month is 12% a year. The calculator counts each day at one 365th of the yearly rate, or by 30-day months if you prefer to work it that way.
Presets come from the statutes
Each preset is a fixed rate from our prompt payment laws guide, with the statute next to it. States whose rate floats with prime or a Treasury rate, and states we could not verify, have no preset. Enter the current rate yourself for those.
When interest starts
Most clocks start on a proper, undisputed pay request, or on the day the prime is paid. Some statutes add a grace period or a notice step. Use the start field for any days that carry no interest. This is arithmetic, not legal advice.
Full guide: Prompt payment laws by state: construction payment deadlines and interest (2026)
More free tools. No sign-up either.
- Billing and retainage
Retainage calculator
Retainage held to date, with a step-down after 50 percent complete and the cash it ties up.
- Billing and retainage
Pay application (G702) calculator
Fill in the contract, change orders, work to date and retainage and get every G702 summary line.
- Billing and retainage
DSO and retention calculator
Days sales outstanding and how much cash retention ties up, from your AR and revenue.
Common questions. Answered plainly.
Something else? Ask the team
How do you calculate prompt payment interest?
Multiply the late amount by the yearly rate and by the days late divided by 365. At 12% a year, $100,000 paid 30 days late carries about $986. At 1.5% a month, $48,000 paid two months late carries $1,440 when counted by month.
What interest rate applies to a late construction payment?
It depends on the state, the project type and the tier. Many states we checked charge 1% to 1.5% a month. Federal contracts use the Treasury Prompt Payment rate, 4.75% a year for July 1 to December 31, 2026. Your contract may set its own rate where the statute allows.
Does prompt payment interest compound?
Most of the rules in our guide are written as simple rates, and the calculator uses simple interest. Wisconsin compounds monthly, and other statutes have their own methods, caps and notice steps. Read the section for your job before you send a demand.
Is the calculator legal advice?
No. It does the arithmetic for the rate and dates you enter. Confirm the rule for your job with your attorney or the state agency before you claim interest.
Get paid faster on every pay app.
Buildalytic tracks each pay application, retainage and lien waiver by job, shows what is holding payment, and has Brody follow up with the GC, owner or supplier until it moves.