The short answer
Prompt payment laws set how fast an owner must pay the prime and how fast the prime must pay its subs, and what interest runs on late money. Most states we checked give the owner 20 to 45 days from a proper pay request, give the prime 7 to 15 days to pay subs after it is paid, and charge 1% to 1.5% a month on late amounts. Public jobs are covered more often than private ones. This is a summary from each statute, not legal advice. Buildalytic is construction accounts receivable and collections software: Brody tracks every pay app through submitted, in review, approved and paid, and follows up by call, text and email until the late ones are paid.
What to take away
- Two clocks run on every job: owner to prime, and prime to sub. Many states set only the second one for private work.
- The clock usually starts on a proper, undisputed pay request, or on the day the prime is paid. Keep proof of both dates.
- Interest is usually 1% to 1.5% a month. Some states use a prime rate or a Treasury rate instead.
- Kentucky (2025) and Louisiana (2026) changed their rules recently. Check the current statute before you rely on an old chart.
- We could not verify every state. California, Illinois, Georgia and others are listed as not verified, not as having no law.
How prompt payment laws work
A prompt payment law puts a deadline on payment and a cost on missing it. Most set two deadlines. The first is the owner paying the prime contractor, counted from a proper pay request or invoice. The second is the prime paying its subs and suppliers, counted from the day the prime is paid. Many states pass the same rule down every tier.
Almost every statute lets a payer hold back an amount it disputes in good faith, as long as it pays the rest on time. Retainage usually follows its own rules; see our retainage laws guide.
Not legal advice. This guide summarizes each state's statute or official state page, checked November 28, 2026. Statutes have exceptions, contract caps, notice steps and effective dates that this summary leaves out. Confirm the rule for your job with your attorney or the state agency before you send a demand or claim interest.
Prompt payment laws by state: master table
Private means private commercial work unless noted. Public means state or local government work. "Not verified" means we could not confirm the rule on the official site on November 28, 2026. It does not mean the state has no law.
| State | Private projects | Public projects | Late interest | Statute |
|---|---|---|---|---|
| Federal (U.S. agency contracts) | Not covered | Agency: 14 days after a proper progress payment request. Prime to sub: 7 days after the prime is paid | Treasury Prompt Payment rate: 4.75% a year for July 1 to December 31, 2026 | 31 U.S.C. 3903, 3905; FAR 52.232-27 |
| Florida | Owner: when due under the contract. Contractor to sub: 30 days after receipt | Local government: 20 business days after the request is stamped received (25 if an agent must approve it). Prime to sub: 10 days | Private: the s. 55.03 rate plus 12% a year, from the 14th day after due. Local public: 2% a month or the contract rate, whichever is greater | Fla. Stat. 715.12, 713.346, 218.735 |
| New York | Owner approves within 12 business days and pays within 30 days after approval. Contractor to sub: 7 days after receipt of good funds | Local: 30 days after the requisition is approved (45 where an elected body approves). Prime to sub: 7 calendar days | Private: 1% a month. Public: rates set by the tax and finance laws | Gen. Bus. Law 756-a, 756-b; Gen. Mun. Law 106-b; State Fin. Law 139-f, 179-f |
| Pennsylvania | Owner: 20 days after the end of the billing period or the invoice, whichever is later. Contractor to sub: 14 days after receipt or the sub's invoice, whichever is later | Not verified | 1% a month | 73 P.S. 501 to 516 |
| Ohio | Contractor to sub: 10 days after receipt (owner deadline not verified) | Agency: 30 days after the approved estimate is filed. Prime to sub: 10 days | Sub: 18% a year. Public owner: average prime rate set by the statute | Ohio Rev. Code 4113.61, 153.14 |
| North Carolina | Contractor to sub: 7 days after receipt | Final balance: 45 days after acceptance, completion or occupancy. Prime to sub: 7 days | 1% a month from day 8 | N.C.G.S. 22C-3, 22C-5; 143-134.1 |
| Michigan | Not verified | 30 days after the architect or engineer certifies the work, or 15 days after grant funds arrive, whichever is later | "Reasonable interest" | MCL 125.1562 |
| Arizona | Not verified | 14 days after approval; a request is deemed approved 7 days after submission. Prime to sub: 7 days | 1% a month | A.R.S. 34-221 |
| Washington | Not verified | 30 days after the invoice or receipt of goods, whichever is later. Prime to sub: 10 days | Agency: 1% a month. Sub: the maximum rate under RCW 19.52.025 | RCW 39.76.011, 39.04.250 |
| Virginia | Owner: 60 days after the invoice following satisfactory completion. Contractor to sub: 7 days after receipt or 60 days after the invoice, whichever is earlier | State: 30 days after a proper invoice or the goods, whichever is later. Local: 45 days. Prime to sub: 7 days | State: the Wall Street Journal prime rate. Sub: 1% a month. Local: up to 1% a month | Va. Code 11-4.6; 2.2-4347, 2.2-4352, 2.2-4354, 2.2-4355 |
| New Jersey | Owner: 30 days after the billing date; deemed approved 20 days after receipt. Contractor to sub: 10 days | The same act covers public owners, with an exception for owners that approve at a meeting. Prime to sub: 10 days | Prime rate plus 1% | N.J.S.A. 2A:30A-2 |
| Massachusetts | Contracts of $3 million or more: approve within 15 days, pay within 45 days after approval | Progress payment 15 days after the periodic estimate (30 for the Commonwealth). Prime pays subs "forthwith" | Public: 3 points above the Boston Federal Reserve rediscount rate | M.G.L. c.149 s.29E; c.30 s.39F, 39G |
| Maryland | Owner: 7 days after the contract due date; with no due date, 30 days after an occupancy permit or possession. Contractor to sub: 7 days | 30 days after payment is due and a proper invoice arrives. Prime to sub: 10 days | Public: 9% a year from the 31st day | Md. Real Prop. 9-302; State Fin. & Proc. 15-103, 15-104, 15-226 |
| Minnesota | Contractor to sub: 10 days after receipt | State: 30 days after the invoice. Local: 35 days (45 if the board meets less than monthly). Prime to sub: 10 days | 1.5% a month | Minn. Stat. 337.10, 16A.124, 471.425 |
| Missouri | Owner: under the contract terms | 30 days after delivery or the invoice, whichever is later. Prime to sub: 15 days | Private: a court may award up to 1.5% a month. Public: 1.5% a month | RSMo 431.180, 8.960 |
| Wisconsin | Not verified | Local government: 30 days after the invoice or acceptance. Prime to sub: 7 days | Rate under s. 71.82(1)(a), compounded monthly | Wis. Stat. 66.0135 |
| Oregon | Owner: 14 days after the billing is received. Contractor to sub: 7 days | Interest runs from 30 days after the invoice or 15 days after approval, whichever is earlier. Prime to sub: 10 days | Private: 1.5% a month. Public: 3 times the 90-day commercial paper rate, up to 30% | ORS 701.625, 701.630, 279C.570, 279C.580 |
| Nevada | Owner: on the written schedule, or 21 days after the request. Contractor to sub: 10 days | Interest if a progress bill is unpaid after 30 days. Prime to sub: 10 days | Private: prime rate at Nevada's largest bank plus 4%. Public: the rate in NRS 338.515 | NRS 624.609, 624.624, 624.630, 338.520 to 338.550 |
| South Carolina | Owner: 21 days after the pay request. Contractor to sub: 7 days | The same rules; "owner" includes government | 1% a month | S.C. Code 29-6-30, 29-6-50 |
| Louisiana | Owner: 35 days after a written request (up to 61 days by contract on a single-family home). Contractor to sub: 7 days | 45 days after a certified request | Private: 1.5% a month. Public: 0.5% a day, up to 15% | La. R.S. 9:2784 (Act 822 of 2026), 38:2191 |
| Kentucky | Owner: 30 business days after a proper, undisputed request. Contractor to sub: 15 business days | The same section applies; colleges and school boards get 45 business days | 12% a year | KRS 371.405 |
| Oklahoma | Not verified | 30 days after a proper invoice on contracts over $25,000. Prime to sub: 10 days | Sub: 1.5% a month | 61 O.S. 222 to 225 |
| Kansas | Owner: 30 days after a proper request. Contractor to sub: 7 business days | 30 days (45 with extenuating circumstances). Prime to sub: 7 business days | 18% a year | K.S.A. 16-1803, 16-1903 |
| Nebraska | Owner: 30 days after the request. Contractor to sub: 10 days | Political subdivisions: the same rules. The State is excluded | 1% a month, after notice | Neb. Rev. Stat. 45-1202 to 45-1205 |
| Maine | Owner: 20 days after the end of the billing period or the invoice, whichever is later. Contractor to sub: 7 days | The same rules; "owner" includes the State | 1-year Treasury bill rate plus 6% | 10 M.R.S. 1111 to 1114; 14 M.R.S. 1602-C |
| Vermont | Owner: 20 days after the end of the billing period or the invoice, whichever is later. Contractor to sub: 7 days | The same rules; "owner" includes the State | The rate in 12 V.S.A. 2903(b) | 9 V.S.A. 4001 to 4003 |
| Montana | Owner: request deemed approved after 21 days; pay 7 days after approval. Contractor to sub: 7 days | Covers local governments | 1.5% a month once more than 30 days late | MCA 28-2-2101 to 28-2-2104 |
| Idaho | Not verified | 60 days after billing | The rate in Idaho Code 63-3045 | Idaho Code 67-2302 |
| Iowa | Not verified | Interest if an approved payment is unpaid 14 days after the request (up to 30 by contract). Prime to sub: 7 days | The rate in Iowa Code 573.14 | Iowa Code 573.12 |
| Texas | Not verified (the state statute site did not load) | State agencies: overdue on the 31st day after the goods or the invoice, whichever is later | Prime rate plus 1% (7.75% for fiscal 2027) | Tex. Gov't Code ch. 2251 |
Sources: FAR 52.232-27, Prompt Payment for Construction Contracts (checked November 28, 2026); 31 U.S.C. 3905, payment provisions for construction contracts (checked November 28, 2026); Bureau of the Fiscal Service: Prompt Payment interest rates (checked November 28, 2026); Florida Statutes 715.12 (checked November 28, 2026); Florida Statutes 713.346 (checked November 28, 2026); Florida Statutes 218.735 (checked November 28, 2026); New York General Business Law 756-a (checked November 28, 2026); New York General Business Law 756-b (checked November 28, 2026); New York General Municipal Law 106-b (checked November 28, 2026); New York State Finance Law 139-f (checked November 28, 2026); Pennsylvania Contractor and Subcontractor Payment Act (Act 7 of 1994) (checked November 28, 2026); Ohio Revised Code 4113.61 (checked November 28, 2026); Ohio Revised Code 153.14 (checked November 28, 2026); North Carolina General Statutes Chapter 22C (checked November 28, 2026); North Carolina General Statutes 143-134.1 (checked November 28, 2026); Michigan Compiled Laws 125.1562 (checked November 28, 2026); Arizona Revised Statutes 34-221 (checked November 28, 2026); Revised Code of Washington 39.76.011 (checked November 28, 2026); Revised Code of Washington 39.04.250 (checked November 28, 2026); Code of Virginia 11-4.6 (checked November 28, 2026); Code of Virginia 2.2-4354 (checked November 28, 2026); Code of Virginia 2.2-4352 (checked November 28, 2026); New Jersey P.L. 2006, c.96 (N.J.S.A. 2A:30A-2) (checked November 28, 2026); Massachusetts General Laws c.149 s.29E (checked November 28, 2026); Massachusetts General Laws c.30 s.39G (checked November 28, 2026); Maryland Real Property 9-302 (checked November 28, 2026); Maryland State Finance and Procurement 15-226 (checked November 28, 2026); Minnesota Statutes 337.10 (checked November 28, 2026); Minnesota Statutes 471.425 (checked November 28, 2026); Missouri Revised Statutes 431.180 (checked November 28, 2026); Missouri Revised Statutes 8.960 (checked November 28, 2026); Wisconsin Statutes 66.0135 (checked November 28, 2026); Oregon Revised Statutes Chapter 701 (checked November 28, 2026); Oregon Revised Statutes Chapter 279C (checked November 28, 2026); Nevada Revised Statutes Chapter 624 (checked November 28, 2026); Nevada Revised Statutes Chapter 338 (checked November 28, 2026); South Carolina Code Title 29, Chapter 6 (checked November 28, 2026); Louisiana Act 822 of 2026 (HB 638), enrolled, amending R.S. 9:2784 (checked November 28, 2026); Louisiana R.S. 38:2191 (checked November 28, 2026); Kentucky Revised Statutes 371.405 (effective June 27, 2025) (checked November 28, 2026); Oklahoma Statutes Title 61, Section 222 (checked November 28, 2026); Kansas Statutes 16-1803 (checked November 28, 2026); Kansas Statutes 16-1903 (checked November 28, 2026); Nebraska Revised Statutes 45-1203 (checked November 28, 2026); Maine Revised Statutes Title 10, 1113 (checked November 28, 2026); Vermont Statutes Title 9, Chapter 102 (checked November 28, 2026); Montana Code Annotated 28-2-2103 (checked November 28, 2026); Idaho Code 67-2302 (checked November 28, 2026); Iowa Code 573.12 (checked November 28, 2026); Texas Comptroller: prompt payment interest liability (checked November 28, 2026)
Federal projects: 7 days to pay subs
On federal construction contracts, the Prompt Payment Act and FAR 52.232-27 apply. A progress payment is due 14 days after the payment office receives a proper request. The prime must pay each sub within 7 days after it is paid, and the same clause flows down to every tier. Late payments carry interest at the Treasury's Prompt Payment rate, which is 4.75% a year for July 1 to December 31, 2026.
People often quote 14 days for subs. That is the agency's deadline to the prime. The flow-down deadline is 7 days.
Sources: FAR 52.232-27, Prompt Payment for Construction Contracts (checked November 28, 2026); 31 U.S.C. 3905, payment provisions for construction contracts (checked November 28, 2026); Bureau of the Fiscal Service: Prompt Payment interest rates (checked November 28, 2026)
Private projects: where the law is strongest
Some states set both private clocks. Pennsylvania gives the owner 20 days after the end of the billing period or the invoice, whichever is later, and gives the contractor 14 days to pay subs, with 1% a month on late amounts. Maine and Vermont use the same 20-day and 7-day pattern. South Carolina uses 21 days and 7 days at 1% a month. Kansas uses 30 days and 7 business days at 18% a year. New Jersey uses 30 days and 10 days at prime plus 1%.
Other states set only the flow-down. Florida requires a contractor to pay undisputed amounts to subs within 30 days after it is paid. North Carolina gives 7 days at 1% a month from day 8. Ohio gives 10 days at 18% a year. Minnesota requires 10 days at 1.5% a month.
New York's private law has its own shape. The owner approves or rejects an invoice within 12 business days and pays within 30 days after approval, and the contractor pays subs within 7 days after it receives good funds, at 1% a month.
Sources: Pennsylvania Contractor and Subcontractor Payment Act (Act 7 of 1994) (checked November 28, 2026); Maine Revised Statutes Title 10, 1113 (checked November 28, 2026); Vermont Statutes Title 9, Chapter 102 (checked November 28, 2026); South Carolina Code Title 29, Chapter 6 (checked November 28, 2026); Kansas Statutes 16-1803 (checked November 28, 2026); New Jersey P.L. 2006, c.96 (N.J.S.A. 2A:30A-2) (checked November 28, 2026); Florida Statutes 713.346 (checked November 28, 2026); North Carolina General Statutes Chapter 22C (checked November 28, 2026); Ohio Revised Code 4113.61 (checked November 28, 2026); Minnesota Statutes 337.10 (checked November 28, 2026); New York General Business Law 756-a (checked November 28, 2026); New York General Business Law 756-b (checked November 28, 2026)
Public projects: agency deadlines and flow-down
Public prompt pay laws are more common. Florida local governments pay within 20 business days after the request is stamped received, or 25 if an agent must approve it, and the prime pays subs within 10 days, at 2% a month or the contract rate. Arizona treats a request as approved 7 days after submission, pays within 14 days after approval, and gives the prime 7 days, at 1% a month. Washington pays within 30 days and gives the prime 10 days.
Virginia state agencies pay within 30 days and local governments within 45 days, and the prime pays subs within 7 days. Maryland pays within 30 days, with 9% a year from the 31st day, and gives the prime 10 days. Minnesota state agencies pay within 30 days and local governments within 35, at 1.5% a month.
Sources: Florida Statutes 218.735 (checked November 28, 2026); Arizona Revised Statutes 34-221 (checked November 28, 2026); Revised Code of Washington 39.76.011 (checked November 28, 2026); Revised Code of Washington 39.04.250 (checked November 28, 2026); Code of Virginia 2.2-4352 (checked November 28, 2026); Code of Virginia 2.2-4354 (checked November 28, 2026); Maryland State Finance and Procurement 15-226 (checked November 28, 2026); Minnesota Statutes 471.425 (checked November 28, 2026)
Recent changes: Kentucky and Louisiana
Kentucky amended KRS 371.405, effective June 27, 2025. A contracting entity pays within 30 business days after a timely, properly completed, undisputed request (45 business days for colleges and school boards), and the contractor pays subs within 15 business days after it is paid, including released retainage. Interest is 12% a year. The contractor must notify the owner by certified mail if it is not paid 25 business days after the request, with the date interest begins.
Louisiana rewrote R.S. 9:2784 in Act 822 of the 2026 session. A private owner pays within 35 days of a written request, or up to 61 days by written contract on a single-family home. A contractor or sub pays the next tier within 7 days after it is paid. Late amounts carry a penalty of 1.5% a month, and the court awards costs and attorney fees to the prevailing party. Confirm the act's effective date and which contracts it reaches before you rely on it.
Sources: Kentucky Revised Statutes 371.405 (effective June 27, 2025) (checked November 28, 2026); Louisiana Act 822 of 2026 (HB 638), enrolled, amending R.S. 9:2784 (checked November 28, 2026)
States we could not verify
We left a state out of the table, or marked a cell not verified, when the official statute site would not load or the text could not be confirmed on November 28, 2026. That includes California, Illinois, Georgia, Tennessee, Connecticut, Colorado, Alabama, Indiana, Utah, New Mexico, Hawaii, West Virginia, Delaware, Alaska, Arkansas, Mississippi, New Hampshire, North Dakota, Rhode Island, South Dakota and Wyoming, plus private work in Texas and public work in Pennsylvania. Several of these states do have prompt payment laws. Read the statute or ask counsel before you act on a job there.
Worked example: what late money costs
This is arithmetic, not advice on any state's method. At 1.5% a month, $48,000 that is paid two months late carries $1,440 of interest. At 12% a year, $100,000 that is 30 calendar days late carries about $986. Statutes differ on when interest starts, whether it compounds and whether disputed amounts count, so read the section before you put a number on a demand.
To run your own numbers, use our free prompt payment interest calculator. Enter the amount, the days late and the rate, or pick a state preset from the table above. It shows the interest and the total, and it does simple interest only.
Sources: Buildalytic: free prompt payment interest calculator
What to do when a pay app is late
Most late payments are not disputes. The pay app is sitting in someone's queue. A steady follow-up with the right person usually gets it moving before you need the statute.
- Confirm the pay app was received and is complete. Most clocks start on a proper request, so a missing waiver or backup can stop it.
- Ask where it sits: in review, approved, or waiting on the owner's money. Get a payment date in writing.
- If you are the sub, ask the prime whether it has been paid. Most flow-down clocks run from that day.
- Pull the statute for the job's state and project type, and note the deadline and the interest rule.
- Send any notice the statute requires, such as Kentucky's certified mail notice at 25 business days.
- Keep going until the money lands. Log every promise to pay and move a missed one up the list.
How Buildalytic follows up on late pay apps
Buildalytic is construction accounts receivable and collections software for subcontractors and general contractors. Brody, its AI assistant, tracks every G702 and G703 pay app across every GC and owner through submitted, in review, approved and paid. He follows up by call, text and email on a cadence per customer, logs each promise to pay, and moves a missed promise up a queue ranked by dollars at risk.
Waivers, insurance certificates and certified payroll a customer needs before paying are prepared with the receivable, so a missing document does not stop the clock. Held retainage is billed the day it is due, and each payment is matched to its invoice, job and GL account in your ERP. Brody also tracks preliminary notice and lien deadlines. Your team decides when to send a demand, claim interest or call your attorney.
Brody is part of the Brody platform: an Operator seat with Brody is $69 a month ($59 billed annually), and Brody Starter is $239 per company ($199 billed annually). Subs and crews are free.
Sources: Buildalytic: construction accounts receivable and collections software; Buildalytic: pricing and usage (checked November 28, 2026)
Common questions
What is a prompt payment law in construction?
A state or federal law that sets how fast an owner must pay the prime contractor and how fast the prime must pay its subs and suppliers, and what interest or penalty runs on late payments. Many apply only to public projects. Some also cover private work.
How many days does a general contractor have to pay a subcontractor?
It depends on the state and the project. In the states we verified, the prime usually has 7 to 15 days after it is paid. Florida private work allows 30 days. On federal jobs the prime has 7 days. Your subcontract can set a shorter time.
What interest can I charge on a late construction payment?
Usually what the statute sets, often 1% to 1.5% a month. New Jersey uses prime plus 1%, Kentucky 12% a year and Kansas 18% a year. Read the section for when interest starts and whether disputed amounts count, and confirm with counsel.
Does pay-if-paid stop prompt payment interest?
Not always. Many prompt payment statutes start the sub's clock when the prime is paid, so a prime that has been paid must pay on time. Whether a pay-if-paid clause is enforceable is a separate state question. Ask your attorney.
Does California have a prompt payment law?
Yes, California has prompt payment rules for private and public work, but the state's statute site blocked our checks on November 28, 2026, so we did not put California figures in the table. Read Civil Code 8800 and Public Contract Code 7107 on the official site or ask counsel.
Can software calculate prompt payment interest for me?
Buildalytic tracks every pay app's status, follow-up and promise to pay, and predicts a likely collection date for each open receivable. Your team or your attorney decides what the statute allows and whether to claim interest.
Sources and editorial notes
- FAR 52.232-27, Prompt Payment for Construction Contracts (checked November 28, 2026)
- 31 U.S.C. 3905, payment provisions for construction contracts (checked November 28, 2026)
- Bureau of the Fiscal Service: Prompt Payment interest rates (checked November 28, 2026)
- Florida Statutes 715.12 (checked November 28, 2026)
- Florida Statutes 713.346 (checked November 28, 2026)
- Florida Statutes 218.735 (checked November 28, 2026)
- New York General Business Law 756-a (checked November 28, 2026)
- New York General Business Law 756-b (checked November 28, 2026)
- New York General Municipal Law 106-b (checked November 28, 2026)
- New York State Finance Law 139-f (checked November 28, 2026)
- Pennsylvania Contractor and Subcontractor Payment Act (Act 7 of 1994) (checked November 28, 2026)
- Ohio Revised Code 4113.61 (checked November 28, 2026)
- Ohio Revised Code 153.14 (checked November 28, 2026)
- North Carolina General Statutes Chapter 22C (checked November 28, 2026)
- North Carolina General Statutes 143-134.1 (checked November 28, 2026)
- Michigan Compiled Laws 125.1562 (checked November 28, 2026)
- Arizona Revised Statutes 34-221 (checked November 28, 2026)
- Revised Code of Washington 39.76.011 (checked November 28, 2026)
- Revised Code of Washington 39.04.250 (checked November 28, 2026)
- Code of Virginia 11-4.6 (checked November 28, 2026)
- Code of Virginia 2.2-4354 (checked November 28, 2026)
- Code of Virginia 2.2-4352 (checked November 28, 2026)
- New Jersey P.L. 2006, c.96 (N.J.S.A. 2A:30A-2) (checked November 28, 2026)
- Massachusetts General Laws c.149 s.29E (checked November 28, 2026)
- Massachusetts General Laws c.30 s.39G (checked November 28, 2026)
- Maryland Real Property 9-302 (checked November 28, 2026)
- Maryland State Finance and Procurement 15-226 (checked November 28, 2026)
- Minnesota Statutes 337.10 (checked November 28, 2026)
- Minnesota Statutes 471.425 (checked November 28, 2026)
- Missouri Revised Statutes 431.180 (checked November 28, 2026)
- Missouri Revised Statutes 8.960 (checked November 28, 2026)
- Wisconsin Statutes 66.0135 (checked November 28, 2026)
- Oregon Revised Statutes Chapter 701 (checked November 28, 2026)
- Oregon Revised Statutes Chapter 279C (checked November 28, 2026)
- Nevada Revised Statutes Chapter 624 (checked November 28, 2026)
- Nevada Revised Statutes Chapter 338 (checked November 28, 2026)
- South Carolina Code Title 29, Chapter 6 (checked November 28, 2026)
- Louisiana Act 822 of 2026 (HB 638), enrolled, amending R.S. 9:2784 (checked November 28, 2026)
- Louisiana R.S. 38:2191 (checked November 28, 2026)
- Kentucky Revised Statutes 371.405 (effective June 27, 2025) (checked November 28, 2026)
- Oklahoma Statutes Title 61, Section 222 (checked November 28, 2026)
- Kansas Statutes 16-1803 (checked November 28, 2026)
- Kansas Statutes 16-1903 (checked November 28, 2026)
- Nebraska Revised Statutes 45-1203 (checked November 28, 2026)
- Maine Revised Statutes Title 10, 1113 (checked November 28, 2026)
- Vermont Statutes Title 9, Chapter 102 (checked November 28, 2026)
- Montana Code Annotated 28-2-2103 (checked November 28, 2026)
- Idaho Code 67-2302 (checked November 28, 2026)
- Iowa Code 573.12 (checked November 28, 2026)
- Texas Comptroller: prompt payment interest liability (checked November 28, 2026)
- Buildalytic: free prompt payment interest calculator
- Buildalytic: construction accounts receivable and collections software
- Buildalytic: pricing and usage (checked November 28, 2026)
Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.