3-week lookahead template.

A Gantt-style lookahead by activity, crew, constraint and date, with float to the need-by date. Download as CSV.

Fill in the rows. Download the lookahead.

No sign-up. What you type stays in your browser.

Your window

Ready to start2
Constraint still open2
Finishing after need-by1

Activities, crews and constraints

ActivityLocationCrewConstraintOwnerClearedStartDaysNeed-byFloat
1
0
3
-1
2

Three-week chart

Week 1 Mon
Week 1 Tue
Week 1 Wed
Week 1 Thu
Week 1 Fri
Week 2 Mon
Week 2 Tue
Week 2 Wed
Week 2 Thu
Week 2 Fri
Week 3 Mon
Week 3 Tue
Week 3 Wed
Week 3 Thu
Week 3 Fri
Deck rebarLevel 3, Ironworkers (6) · Ready
Deck pourLevel 3, Concrete crew (8) · Constraint open
Electrical rough-inLevel 2, Electricians (4) · Ready
In-wall inspectionLevel 2, City inspector · Finishes after need-by
Drywall hangLevel 1, Drywall crew (5) · Constraint open
ReadyConstraint openFinishes after need-byFloat

Float here is the workdays between the planned finish and the need-by date, counted Monday to Friday. Use the need-by from your CPM schedule or the next trade's start. Work that finishes past the window is cut off at the third Friday.

How it works. The rules behind the numbers.

  • Three weeks, workday by workday

    A lookahead breaks the next three weeks of the master schedule into the activities crews will actually do. Each row has a location, a crew and size, a start day and a duration in workdays, Monday to Friday.

  • One constraint per row

    Name what must be true before the work can start: a delivery confirmed, a submittal approved, an inspection passed. Give it an owner. Work only shows as ready when its constraint is cleared.

  • Float to the need-by date

    Float is the workdays between the planned finish and the date the work must be done, taken from the CPM schedule or the next trade’s start. Zero float has no slack. Below zero, the work finishes late and needs a decision now.

Full guide: Two-week lookahead constraint log: turn a start date into ready work

Common questions. Answered plainly.

Something else? Ask the team

What is a 3-week lookahead schedule?

A short-range schedule that shows the work planned for the next three weeks in more detail than the master schedule, by activity, crew and day. Teams update it every week and use it to clear constraints before the work starts.

How is float calculated in a lookahead?

Here it is the number of workdays from the planned finish to the need-by date. A task finishing Wednesday that must be done by Friday has two days of float. A task finishing after its need-by date has negative float.

Can I open the lookahead in Excel?

Yes. Download the CSV and open it in Excel, Google Sheets or Numbers. It has one column for each of the 15 workdays, marked X where the activity is planned, so you can shade it as a bar chart.

What is the difference between a 2-week and a 3-week lookahead?

Only the window. Three weeks gives more time to clear deliveries, submittals and inspections. Our two-week constraint log guide shows how to track each constraint to closure.

Keep the lookahead, inspections and turnover moving.

Buildalytic confirms crews, deliveries and inspections by call and text, chases turnover documents until they are accepted, and files every answer to the job.