The short answer
A DOT job pays by bid item, so every quantity, haul ticket and labor hour should point back to the bid item it supports. Keep one job record where the foreman's daily quantities, each haul ticket and each week's certified payroll share the same job, date and bid item. On federal-aid highway work, FHWA-1273 says the contractor and each subcontractor submit certified payrolls weekly to the contracting agency, the prime is responsible for its subs' payrolls, the optional WH-347 may be used and records are kept for 3 years after the prime contract is complete. HCSS HeavyBid and HeavyJob are the established tools for estimating by pay item and tracking time cards and quantities. Buildalytic adds the follow-up: daily quantities by phone, haul tickets matched to invoices, and Brody chasing every missing ticket and payroll week.
What to take away
- Tie every quantity, haul ticket and labor hour to the bid item it supports.
- Match haul tickets to loads, units, rates and the hauler's invoice before you bill the item.
- On federal-aid work, the prime submits its own and every sub's certified payroll weekly.
- Missing tickets and payroll weeks are a follow-up problem. Chase them the day they are due.
- If you run HCSS, keep it. Add follow-up where people, not software, are the gap.
Why one record matters on a DOT job
On a unit price DOT job, you get paid for measured quantities of each bid item. The agency checks those quantities against field records, tickets and inspector notes. On federal-aid work it also checks that everyone on site was paid the right wage, week by week.
Those three records usually live in three places: quantities in the foreman's daily, haul tickets in a folder or a hauler's portal, and certified payroll with the payroll clerk and each sub. When they disagree, the pay estimate stalls or a payroll week goes missing.
The fix is to give each record the same keys: the job, the date, the bid item and the crew or sub. Then any quantity can be traced to the tickets and hours behind it.
Bid item quantities from the field
Set up the job with the bid items from the contract, each with its unit and planned quantity, and map your cost codes to them. Ask the foreman to report installed quantities by bid item every day, with the crew and equipment that did the work.
Keep the measured quantity separate from what you plan to bill. A daily quantity is evidence. The pay quantity is what the agency's measurement rules allow, and your PM or engineer confirms it.
- Bid item number, description and unit from the contract.
- Daily installed quantity by bid item, with location or station.
- Crew hours and equipment hours on the same item.
- Photos and inspector notes where the item needs them.
- Running total against the planned quantity.
Haul tickets matched to bid items
Each haul ticket should become one movement on the job: ticket number, issuer, truck, date, material, quantity and unit, and the bid item it supports. Match it to the hauler's or supplier's invoice by load, unit and rate, and flag duplicates before anything is counted twice.
Keep the source quantity as printed, with its unit. Tons, cubic yards and loads are not interchangeable without an authorized conversion. FHWA's e-Ticketing work under Every Day Counts describes exchanging and archiving material ticket data as construction records, which many agencies now ask for.
Sources: FHWA: Historical EDC-6 e-Ticketing and Digital As-Builts overview; Buildalytic: procurement and equipment, haul ticket matching
Certified payroll on federal-aid work
Form FHWA-1273, revised June 25, 2026, sets the Davis-Bacon provisions for federal-aid highway construction projects over $2,000. The contractor and each subcontractor must submit certified payrolls weekly, for each week covered work is performed, to the contracting agency. The prime contractor is responsible for submitting all subcontractors' payrolls.
Each payroll carries a signed Statement of Compliance. The optional Form WH-347 satisfies that requirement, and any format with the required information may be used. Weekly payrolls list an identifying number, such as the last four digits of the Social Security number, rather than the full number. Payroll records are kept for at least 3 years after all work on the prime contract is complete.
Since June 10, 2026, the form itself no longer has to be physically included in each contract, but the agency must still make sure the provisions apply. State DOTs often add their own portal or file format, so check the contract and the agency's instructions.
Tie payroll hours to the same job and bid item
Certified payroll reports hours by worker, classification and project. If the same hours are coded to bid items in the daily, you can check that the crew on the quantity is the crew on the payroll, and that a sub's workers on site appear in the sub's payroll for that week.
That check catches the common gaps: a sub who worked but did not send a payroll, a classification that does not match the work, or a missing week before the pay estimate goes in.
Where HCSS fits
HCSS is the established software for heavy civil contractors, and it is a fair first look for a DOT contractor. HeavyBid serves heavy civil bidding by pay item, and HCSS's Estimate Builder Agent, in beta with general availability planned for February 2027, builds a first-pass estimate from a list of pay items or project documents, with every AI value flagged for review. HeavyJob creates time cards for crew hours, equipment hours and quantities, and exports approved time cards to your payroll or accounting system.
For hauling, HCSS describes automating the documentation of every dump and load event to meet e-ticketing requirements. If your company already runs HeavyBid and HeavyJob, keep them as the record of estimate, time and quantity.
Sources: HCSS: HeavyJob construction field and project management software (checked November 28, 2026); HCSS: fall 2026 product release (checked November 28, 2026); HCSS: go paperless, truck tickets (checked November 28, 2026)
Where Buildalytic fits
Buildalytic adds the follow-up a DOT job runs on. A foreman calls or texts the company number at the end of the shift, and Brody writes the daily report with installed quantities, labor and equipment coded to the same job and activity. Haul, waste and concrete tickets are matched to invoices, and Brody asks the hauler or supplier for the missing ticket or the corrected quantity.
For certified payroll, Buildalytic collects, checks and corrects every subcontractor's weekly payroll, and Brody chases each missing week by call and text. From the checked data it produces the WH-347 and the state file each project needs, for your team to certify. Certified payroll is quoted separately from Brody's communications price.
Brody says he is an AI assistant on every call. Your team confirms quantities and certifies each payroll.
Sources: Buildalytic: certified payroll; Buildalytic: daily reports by phone; Buildalytic: procurement and equipment, haul ticket matching
A weekly routine for a DOT job
One way to run the week, whichever tools you use:
- Daily: quantities by bid item, crew and equipment hours, and haul tickets logged the same day.
- Daily: duplicate or unreadable tickets flagged and sent back to the hauler.
- Weekly: each sub's certified payroll collected and checked against the daily crew lists.
- Weekly: payrolls submitted to the agency by the prime, with any missing week chased before the deadline.
- Monthly: bid item quantities reconciled with tickets and inspector records before the pay estimate.
Common questions
Who submits certified payroll on a federal-aid highway job?
Under FHWA-1273, the contractor and each subcontractor submit certified payrolls weekly to the contracting agency, and the prime contractor is responsible for submitting all subcontractors' payrolls. The agency may allow or require an electronic system.
Is Form WH-347 required?
No. FHWA-1273 says the optional WH-347 may be used, or any other format with the required information, as long as each payroll carries a signed Statement of Compliance.
How long do I keep certified payroll records on a DOT job?
FHWA-1273 says for at least 3 years after all the work on the prime contract is complete. Your state DOT may ask for longer.
Should a haul ticket be tied to a bid item?
Yes, when the material it carries supports a pay item. Keep the ticket's own quantity and unit, match it to the invoice, and map it to the bid item so the quantity can be traced.
Can Buildalytic replace HCSS?
Most HCSS customers keep HeavyBid and HeavyJob. Buildalytic adds the calls and texts that collect daily quantities, missing haul tickets and sub payroll weeks, and produces the WH-347 and state file from checked payroll data.
Sources and editorial notes
- FHWA: Form FHWA-1273, Required Contract Provisions, revised June 25, 2026 (checked November 28, 2026)
- FHWA: Historical EDC-6 e-Ticketing and Digital As-Builts overview
- HCSS: HeavyJob construction field and project management software (checked November 28, 2026)
- HCSS: fall 2026 product release (checked November 28, 2026)
- HCSS: go paperless, truck tickets (checked November 28, 2026)
- Buildalytic: certified payroll
- Buildalytic: daily reports by phone
- Buildalytic: procurement and equipment, haul ticket matching
Prepared with AI assistance. Reference date: 2026-11-28. Worked scenarios use typical figures and are not customer results. Product details can change; confirm the current scope and terms before rollout.