Certified payroll / Field guide
Indiana certified payroll and prevailing wage reporting.
Indiana repealed its Common Construction Wage Act effective July 1, 2015. Davis-Bacon still covers federally funded work over $2,000, with weekly certified payroll.

Compliance at a glance
Indiana prevailing wage and certified payroll rules.
Reviewed November 17, 2026. Each item comes from the agency or statute listed under official sources.
| Law | None. 2015 House Enrolled Act 1019 repealed the Common Construction Wage Act effective July 1, 2015. |
| Agency | No state prevailing wage agency. The U.S. Department of Labor enforces Davis-Bacon on federal work, including INDOT federal aid projects. |
| Covered projects | No state coverage. Davis-Bacon covers federally funded or assisted construction over $2,000. Old common wage contracts over $350,000 awarded before July 1, 2015 remain enforceable. |
| How rates are set | No state rates. On Davis-Bacon work, the U.S. Department of Labor sets rates in wage determinations published on SAM.gov, and the contracting agency puts the right one in the contract. |
| Certified payroll | Not required by state law. On Davis-Bacon work, payroll is due weekly with a signed Statement of Compliance. Form WH-347 is optional. |
| Where to file | On Davis-Bacon work, to the federal agency if it is a party to the contract, otherwise to the applicant, sponsor, or owner, which forwards them. |
| Apprentices | No state rules. On Davis-Bacon work, apprentices may be paid less only if individually registered in a registered program, within the program ratio. |
| Other requirements | On Davis-Bacon work, post the wage determination and the WH-1321 poster at the site where workers can easily see them. |
| Record retention | No state rule. On Davis-Bacon work, payroll records must be kept at least 3 years after all work on the prime contract is completed. |
| Penalties | No state penalties. On Davis-Bacon work, violations can bring withholding of payments, contract termination, and debarment for three years. |
| Recent changes | None found. |
| Federal overlay | Davis-Bacon applies to federally funded or assisted construction over $2,000 in addition to state law. |
01 / In practice
Indiana repealed its prevailing wage law in 2015
Indiana's prevailing wage law was the Common Construction Wage Act. House Enrolled Act 1019 repealed it effective July 1, 2015, according to the Indiana Department of Labor. The U.S. Department of Labor also lists Indiana among the states without a prevailing wage law. No state agency now sets wage rates for state or local public works, and Indiana has no state certified payroll form or filing system for them. On a project paid only with state or local money, payroll terms come from the owner's contract.
02 / In practice
How the old law worked
The law dated to 1935 and was retitled the Common Construction Wage Act in 1995. For projects without federal funds, local committees adopted wage scales for each project above a cost threshold. That threshold was $150,000, then $250,000 in 2011, and $350,000 in 2013. Federally funded projects and INDOT highway, street, and bridge contracts used Davis-Bacon rates instead. The U.S. Department of Labor notes that wages on contracts over $350,000 awarded before July 1, 2015 remain enforceable.
Where teams get burned
Most Indiana payroll problems are found after the money is gone.
Underpaid fringe, a missing week from one sub or an apprentice over the ratio usually surfaces in an audit or a withheld payment, months later, when the sub has been paid and the crew has moved on. Buildalytic checks every sub's payroll the week it arrives.
| Subcontractor | Payroll | What was flagged | Result |
|---|---|---|---|
| Ridgeline Electric | Week 6 | Electrician paid $46.10 base; determination is $48.20 | Short $84.00 for 40 hours |
| Valley Concrete | Week 6 | Fringe credit $9.50/hr from a health plan, not annualized | Credit should be $6.00/hr |
| Summit Drywall | Week 5 | Payroll not received | Brody called and texted the payroll contact twice |
| Summit Drywall | Week 6 | Three apprentices for one journeyworker; ratio is 1:1 | Two paid the journeyworker rate |
| Northside Mechanical | Week 6 | Worker classified as laborer, daily report shows pipefitting | Ask for split classification hours |
Sample exception report with illustrative subcontractors and rates.
03 / In practice
Davis-Bacon still applies to federally funded work
The repeal did not change federal rules. The Indiana Department of Labor says projects paid with federal money, such as federal buildings, military bases, and INDOT roadway projects, were not affected. The Davis-Bacon Act covers federal contracts over $2,000 for construction, alteration, or repair of public buildings or public works. Related acts extend the same rules to many projects built with federal grants, loans, or other assistance. When coverage applies, the contract includes the Davis-Bacon clauses and a wage determination.
04 / In practice
Find the wage determination on SAM.gov
The Department of Labor publishes Davis-Bacon wage determinations on SAM.gov. The contracting agency picks the one that fits the project's county and construction type and puts it in the contract. Classify each worker by the work performed. Post the wage determination and the WH-1321 poster where workers can easily see them. Apprentices can be paid apprentice rates only when they are individually registered in a registered apprenticeship program.
05 / In practice
Submit weekly certified payroll on covered projects
Each contractor and subcontractor submits payroll information every week. Payrolls go to the federal agency when it is a party to the contract. Otherwise they go to the applicant, sponsor, or owner, such as INDOT or a local government, which sends them on. Form WH-347 is optional, but each payroll needs a signed Statement of Compliance. Review each week internally first, then submit as the contract directs. Violations can lead to withholding, termination, and three year debarment.
State guides
Certified payroll and prevailing wage rules in every state and territory.
Filing systems, thresholds, rates and deadlines by state, from each state's agency and statutes. Federal Davis-Bacon rules apply on top of state law on federally funded work.
- Federal (Davis-Bacon)
- Alabama
- Alaska
- American Samoa
- Arizona
- Arkansas
- California
- Colorado
- Connecticut
- Delaware
- District of Columbia
- Florida
- Georgia
- Guam
- Hawaii
- Idaho
- Illinois
- Indiana
- Iowa
- Kansas
- Kentucky
- Louisiana
- Maine
- Maryland
- Massachusetts
- Michigan
- Minnesota
- Mississippi
- Missouri
- Montana
- Nebraska
- Nevada
- New Hampshire
- New Jersey
- New Mexico
- New York
- North Carolina
- North Dakota
- Northern Mariana Islands
- Ohio
- Oklahoma
- Oregon
- Pennsylvania
- Puerto Rico
- Rhode Island
- South Carolina
- South Dakota
- Tennessee
- Texas
- US Virgin Islands
- Utah
- Vermont
- Virginia
- Washington
- West Virginia
- Wisconsin
- Wyoming
Compare every state side by side in the prevailing wage laws by state table, or work out a paycheck with the prevailing wage calculator.
Official sources
Start with the agency’s instructions.
Reporting requirements depend on the contract and applicable program. Check the current instructions with the team responsible for your project.
- Indiana Department of Labor · Effects of the Repeal of the Indiana Common Construction Wage Act (2021) ↗
- U.S. Department of Labor · Dollar Threshold Amount for Contract Coverage Under State Prevailing Wage Laws ↗
- U.S. Department of Labor · Fact Sheet #66: Davis-Bacon and Related Acts ↗
- U.S. Department of Labor · Instructions for Form WH-347 ↗
- eCFR · 29 CFR 5.5 Contract provisions ↗
Sources checked November 17, 2026.
Does Indiana still have a prevailing wage law?
No. House Enrolled Act 1019 repealed the Common Construction Wage Act effective July 1, 2015. Prevailing wages still apply on federally funded or assisted construction covered by the Davis-Bacon Act and related acts, including many INDOT projects.
What happens to contracts awarded before July 1, 2015?
The U.S. Department of Labor notes that common construction wages on contracts over $350,000 awarded before July 1, 2015 remain enforceable. Contracts awarded on or after that date are not covered by the old law. Federal rules still apply to federally funded work.
Do INDOT projects require certified payroll?
INDOT highway, street, and bridge contracts were never under the state common wage law. The Indiana Department of Labor says federally funded INDOT roadway projects use Davis-Bacon rates and were not affected by the repeal. On those projects, follow the contract's weekly certified payroll requirements.
How often do I submit certified payroll on a federal project in Indiana?
Weekly. Each contractor and subcontractor submits payroll information every week to the contracting agency, or to the local owner when the federal agency is not a party. Form WH-347 is optional, but a signed Statement of Compliance must go with each payroll.