Puerto Rico certified payroll and prevailing wage reporting.
Puerto Rico certified payroll: why the Davis-Bacon Act itself does not apply, which federal programs bring its rates, the $10.50 minimum wage, and the $15 rule.

Compliance at a glance
Puerto Rico prevailing wage and certified payroll rules.
Reviewed November 17, 2026. Each item comes from the agency or statute listed under official sources.
| Law | No general Puerto Rico prevailing wage statute confirmed. Executive Order OE-2022-014 sets a construction wage floor; the $10.50 minimum wage applies under Puerto Rico law, with the Minimum Wage Review Commission created by Act 47-2021. |
| Agency | Puerto Rico Department of Labor and Human Resources (DTRH) enforces OE-2022-014. U.S. DOL Wage and Hour Division enforces federal Related Acts labor standards. |
| Covered projects | OE-2022-014: construction contracted by Puerto Rico executive agencies or public corporations and funded wholly or partly with federal recovery funds. Not municipal or private projects. |
| How rates are set | OE-2022-014 sets $15.00 per hour for skilled and $11.00 for non-skilled workers. On federally assisted work, DOL wage determinations on SAM.gov apply (for example PR20260001). |
| Certified payroll | Weekly, for each week covered work is done. Form WH-347 is optional; any format with the same data and a signed Statement of Compliance works. No territorial certified payroll form confirmed. |
| Where to file | The federal agency if it is a party to the contract; otherwise the applicant, sponsor, owner, or territorial agency named in the contract, which forwards it. DTRH can demand payroll copies during OE-2022-014 investigations. |
| Apprentices | Under OE-2022-014, non-skilled workers may be classified as apprentices. Under federal rules, apprentice rates apply only to apprentices registered in a program recognized by the DOL Office of Apprenticeship or a State Apprenticeship Agency. |
| Other requirements | Agencies must put OE-2022-014 terms in bids and contracts; primes must flow them down and notify covered workers of the rates. Fringe benefits cannot count toward the floor. |
| Record retention | Contracting agencies keep proof of OE-2022-014 compliance for at least 5 years. Federal rule: keep payrolls and basic records for at least 3 years after all work on the prime contract is completed. |
| Penalties | Under OE-2022-014, the agency may withhold invoice payments until underpayment is corrected. DTRH investigates complaints. Federal Related Acts sanctions apply separately. |
| Recent changes | OE-2025-015 (March 19, 2025) repealed the project labor agreement pilot (Sections 4 to 8 and the last paragraph of Section 2) but kept the wage floor. |
| Federal overlay | DOL says the Davis-Bacon Act does not apply in Puerto Rico, but some Related Acts, such as federal-aid highway law, bring Davis-Bacon rates and weekly certified payroll to assisted projects. |
01 / In practice
The Davis-Bacon Act itself does not reach Puerto Rico
The Davis-Bacon Act at 40 U.S.C. 3142 covers federal construction contracts over $2,000 for public buildings and public works located in a State or the District of Columbia. The U.S. Department of Labor says the Act does not apply to construction in Puerto Rico. It also says some Davis-Bacon Related Acts do apply to construction in the territories. So on a project in Puerto Rico, the funding program decides whether Davis-Bacon wage rates and certified payroll are required. Read the contract for the federal labor standards clauses.
02 / In practice
Related Acts bring Davis-Bacon rates to many projects
Congress has written Davis-Bacon labor standards into many grant and loan programs. Federal highway law is one example. Under 23 U.S.C. 113, workers on federal-aid highway projects must be paid at least the rates the Secretary of Labor sets under the Davis-Bacon Act. The Puerto Rico Highway Program in 23 U.S.C. 165 funds a highway program in the Commonwealth. Housing, transit, water, and disaster recovery money can also carry these clauses. When they are in the contract, the federal wage and payroll rules apply to every covered worker.
Where teams get burned
Most Puerto Rico payroll problems are found after the money is gone.
Underpaid fringe, a missing week from one sub or an apprentice over the ratio usually surfaces in an audit or a withheld payment, months later, when the sub has been paid and the crew has moved on. Buildalytic checks every sub's payroll the week it arrives.
| Subcontractor | Payroll | What was flagged | Result |
|---|---|---|---|
| Ridgeline Electric | Week 6 | Electrician paid $46.10 base; determination is $48.20 | Short $84.00 for 40 hours |
| Valley Concrete | Week 6 | Fringe credit $9.50/hr from a health plan, not annualized | Credit should be $6.00/hr |
| Summit Drywall | Week 5 | Payroll not received | Brody called and texted the payroll contact twice |
| Summit Drywall | Week 6 | Three apprentices for one journeyworker; ratio is 1:1 | Two paid the journeyworker rate |
| Northside Mechanical | Week 6 | Worker classified as laborer, daily report shows pipefitting | Ask for split classification hours |
Sample exception report with illustrative subcontractors and rates.
03 / In practice
Find Puerto Rico wage determinations on SAM.gov
The Department of Labor publishes Puerto Rico wage determinations on SAM.gov. For example, General Decision PR20260001 covers building construction statewide. Many of its rates are $7.25 an hour, based on a 1993 survey. Puerto Rico's own minimum wage is higher. The Department of Labor lists it at $10.50 an hour for employees covered by the federal Fair Labor Standards Act, with exceptions for agricultural and government employees. Pay at least the higher of the two. Use the determination attached to your contract, and classify workers by the work they actually perform.
04 / In practice
The $15 and $11 rule on federal recovery projects
Executive Order OE-2022-014 sets a separate floor for construction contracted by Puerto Rico government agencies and paid in whole or in part with federal reconstruction or recovery funds. Skilled workers must get at least $15.00 an hour and non-skilled workers at least $11.00. The Department of Labor and Human Resources (DTRH) enforces it. Its Circular Letter 2022-01 says fringe benefits cannot count toward the rate. The rule does not cover municipal projects or private work. Order OE-2025-015 ended the project labor agreement pilot but left this wage floor in place.
05 / In practice
Review weekly payroll, then submit it
Covered contractors and subcontractors submit certified payroll every week that covered work is done. If a federal agency is a party to the contract, payroll goes to that agency. If not, it goes to the applicant, sponsor, or owner that keeps the records, such as a territorial agency running a federal grant. Form WH-347 is optional, but each payroll needs a signed Statement of Compliance. Check rates, hours, and fringes internally first. Then submit to the recipient named in the contract. Keep payroll records for at least 3 years after all work on the prime contract is done.
06 / In practice
Keep records for every set of rules
One project can fall under several rules at once. The federal wage determination, Puerto Rico's minimum wage and overtime law, and the $15 and $11 floor may all apply. Track each worker's classification, skill level, hours, and pay so you can show compliance with each one. Under Circular Letter 2022-01, the contracting agency keeps proof of compliance with the $15 and $11 floor for at least five years. DTRH investigators can ask for payroll copies, and the agency can withhold payments until underpayments are corrected.
State guides
Certified payroll and prevailing wage rules in every state and territory.
Filing systems, thresholds, rates and deadlines by state, from each state's agency and statutes. Federal Davis-Bacon rules apply on top of state law on federally funded work.
- Federal (Davis-Bacon)
- Alabama
- Alaska
- American Samoa
- Arizona
- Arkansas
- California
- Colorado
- Connecticut
- Delaware
- District of Columbia
- Florida
- Georgia
- Guam
- Hawaii
- Idaho
- Illinois
- Indiana
- Iowa
- Kansas
- Kentucky
- Louisiana
- Maine
- Maryland
- Massachusetts
- Michigan
- Minnesota
- Mississippi
- Missouri
- Montana
- Nebraska
- Nevada
- New Hampshire
- New Jersey
- New Mexico
- New York
- North Carolina
- North Dakota
- Northern Mariana Islands
- Ohio
- Oklahoma
- Oregon
- Pennsylvania
- Puerto Rico
- Rhode Island
- South Carolina
- South Dakota
- Tennessee
- Texas
- US Virgin Islands
- Utah
- Vermont
- Virginia
- Washington
- West Virginia
- Wisconsin
- Wyoming
Compare every state side by side in the prevailing wage laws by state table, or work out a paycheck with the prevailing wage calculator.
Official sources
Start with the agency’s instructions.
Reporting requirements depend on the contract and applicable program. Check the current instructions with the team responsible for your project.
- U.S. Department of Labor · Davis-Bacon and Related Acts training presentation ↗
- SAM.gov · Davis-Bacon General Decision PR20260001 ↗
- Puerto Rico DTRH · Circular Letter CC-2022-01 ↗
- Puerto Rico Department of State · Executive Order OE-2025-015 ↗
Sources checked November 17, 2026.
Does the Davis-Bacon Act apply in Puerto Rico?
Not directly. The Department of Labor says the Davis-Bacon Act applies only in the fifty states, the District of Columbia, and the Northern Mariana Islands. Some Related Acts, such as federal highway law, still bring Davis-Bacon rates and weekly certified payroll to projects in Puerto Rico. Check the contract for the federal labor standards clauses.
Where do I find Davis-Bacon rates for Puerto Rico?
Search SAM.gov for Puerto Rico wage determinations. General Decision PR20260001, for example, covers building construction statewide. Use the determination attached to your bid documents or contract. If a listed rate is below Puerto Rico's $10.50 minimum wage, pay at least the minimum wage.
What is the Puerto Rico minimum wage in 2026?
The U.S. Department of Labor lists Puerto Rico's minimum wage at $10.50 an hour. It applies to employees covered by the federal Fair Labor Standards Act, except agricultural employees and employees of the municipalities and the Commonwealth. Overtime is due after 8 hours a day and 40 hours a week.
Who must pay the $15 construction wage?
Contractors and subcontractors on construction contracted by a Puerto Rico government agency or public corporation and funded in whole or in part with federal reconstruction or recovery funds. Skilled workers get at least $15.00 an hour and non-skilled workers at least $11.00. Municipal and private projects are not covered.
Does Puerto Rico require its own certified payroll form?
No territorial certified payroll form applies to every public project. On federally assisted work, the federal rule controls. Payroll is weekly, WH-347 is optional, and a signed Statement of Compliance is required. Follow the contract for the recipient. DTRH can ask for payroll copies when it checks the $15 and $11 floor.