Nebraska certified payroll and prevailing wage reporting.

Nebraska prevailing wage: the state has no rate-setting law, only a 1939 fair labor standards statement. Davis-Bacon applies on federally funded work over $2,000.

Illustrative Buildalytic payroll review workspace showing received, missing and ready submissions.
Illustrative product scene · example records

Compliance at a glance

Nebraska prevailing wage and certified payroll rules.

Reviewed November 17, 2026. Each item comes from the agency or statute listed under official sources.

Nebraska compliance summary
LawNo rate-setting law. The 1939 fair labor standards law, Neb. Rev. Stat. sections 73-102 to 73-104, applies to public works bids and contracts.
AgencyNone. Awarding authorities apply the fair labor standards law. The U.S. Department of Labor enforces Davis-Bacon on federal work.
Covered projectsState and local public works contracts, unless the authority's contracts already set hours, pay and conditions. Davis-Bacon covers federally funded work over $2,000.
How rates are setNo state rates. Fair labor standards mean wages and conditions kept by at least half of contractors in the same field. Davis-Bacon rates are on SAM.gov.
Certified payrollNot required by state law. Federal Davis-Bacon work only: weekly certified payroll with a signed Statement of Compliance. Form WH-347 is optional.
Where to fileNo state filing. Bidders file a fair labor standards compliance statement with the awarding authority. Davis-Bacon payrolls go to the federal agency or the sponsor.
Contractor registrationAll contractors must register with the Nebraska Department of Labor before doing construction work, unless they earn under $5,000 a year from construction.
ApprenticesNo state rule. On Davis-Bacon work, apprentices must be in a program registered with the U.S. Office of Apprenticeship or a recognized state agency, within the program's ratio.
Other requirementsEach public works contract must include a fair labor standards clause, and each bidder files a compliance statement.
Record retentionNo state rule. Davis-Bacon payroll records must be kept for 3 years after all work on the prime contract is completed.
PenaltiesNo fines. A low bidder shown at a public hearing to violate fair labor standards can be disqualified. Davis-Bacon withholding and debarment apply on federal work.
Recent changesNone found.
Federal overlayDavis-Bacon applies to federally funded or assisted construction over $2,000 in addition to state law.

01 / In practice

Nebraska has no state prevailing wage rates

Nebraska does not have a prevailing wage law that sets rates, names an agency or requires state certified payroll. What it has is a 1939 fair labor standards law in sections 73-102 to 73-104 of the Nebraska Revised Statutes. No state agency publishes Nebraska prevailing wage schedules. Contractors on state and local public works deal with that statute and the terms of their contract. Federally funded projects follow federal Davis-Bacon rules.

02 / In practice

What the fair labor standards law requires

Under section 73-102, public bodies must require bidders on public works contracts to file a statement that they comply with fair labor standards and will keep doing so. Every public works contract must also include a fair labor standards clause. Section 73-104 defines fair labor standards as wages and conditions paid and kept by at least half of the contractors in the same business or field. The statute does not set rates, a payroll form or a reporting schedule.

Where teams get burned

Most Nebraska payroll problems are found after the money is gone.

Underpaid fringe, a missing week from one sub or an apprentice over the ratio usually surfaces in an audit or a withheld payment, months later, when the sub has been paid and the crew has moved on. Buildalytic checks every sub's payroll the week it arrives.

Sample of what Buildalytic flags in one week of subcontractor payroll
SubcontractorPayrollWhat was flaggedResult
Ridgeline ElectricWeek 6Electrician paid $46.10 base; determination is $48.20Short $84.00 for 40 hours
Valley ConcreteWeek 6Fringe credit $9.50/hr from a health plan, not annualizedCredit should be $6.00/hr
Summit DrywallWeek 5Payroll not receivedBrody called and texted the payroll contact twice
Summit DrywallWeek 6Three apprentices for one journeyworker; ratio is 1:1Two paid the journeyworker rate
Northside MechanicalWeek 6Worker classified as laborer, daily report shows pipefittingAsk for split classification hours

Sample exception report with illustrative subcontractors and rates.

03 / In practice

How the statute is enforced

The law has no fines and no state enforcement agency. Section 73-103 gives one remedy. An interested party can show at a public hearing that a low bidder who filed the statement is not meeting fair labor standards. If the awarding authority agrees, the low bid is disqualified and the contract goes to the next lowest responsible bidder. The statute does not apply to authorities whose contracts already set hours, pay rates and working conditions.

04 / In practice

Davis-Bacon applies on federally funded work

Federal Davis-Bacon and Related Acts rules apply to federally funded or assisted construction contracts over $2,000 in Nebraska. Contractors pay at least the wage determination rates for the county and type of work. Wage determinations are posted on SAM.gov and included in the contract. This covers federal contracts and many projects paid for with federal grants, loans or loan guarantees, such as highway, housing and water projects.

05 / In practice

Submit weekly certified payroll on federal projects

On Davis-Bacon projects, each contractor and subcontractor submits certified payroll every week. Payrolls go to the federal agency when it is a party to the contract. Otherwise they go to the applicant, sponsor or owner, who passes them to the funding agency. Form WH-347 is optional, but the weekly payroll information and the signed statement of compliance are required. Review each week internally before you sign and submit it.

Official sources

Start with the agency’s instructions.

Reporting requirements depend on the contract and applicable program. Check the current instructions with the team responsible for your project.

Sources checked November 17, 2026.

FAQ

Questions people ask

Something else? Ask the team

Does Nebraska have a prevailing wage law?

Not one that sets rates. Nebraska has a 1939 fair labor standards law in sections 73-102 to 73-104. Bidders file a compliance statement and contracts include a fair labor standards clause. No state agency publishes rates or collects certified payroll. Federal Davis-Bacon applies to federally funded work.

What are fair labor standards in Nebraska?

Section 73-104 defines them as wages and working conditions paid and kept by at least 50 percent of the contractors in the same business or field as the bidder. The statute does not convert that into a published rate schedule.

When does Davis-Bacon apply in Nebraska?

Davis-Bacon and Related Acts rules apply to federally funded or assisted construction, alteration or repair contracts over $2,000. Contractors must pay the rates in the wage determination, found on SAM.gov and in the contract, and submit weekly certified payroll.

Do I have to use Form WH-347?

No. The U.S. Department of Labor says Form WH-347 is optional. You still have to submit the same payroll information every week with a signed statement of compliance. Many agencies accept a contractor's own report or an electronic system if it has all the required fields.